Pre-Bid RFI Log Floor Covering Installation.pdf
PDF 87 KB Posted
- Attached to
- Floor Covering Installation Federal contract opportunity
- Solicitation number
- W50S8U-24-B-0003
- Issued by
- Department of the Army National Guard
About this file
This document is a Pre-Bid RFI Log related to a federal contract opportunity for Floor Covering Installation. The key details are:
The contract opportunity is for concrete floor covering installation, repair, and polishing in 3 buildings totaling approximately 8,000 square feet at the Tulsa Air National Guard facility in Tulsa, Oklahoma. The contract is set aside 100% for small businesses with a size standard of $19M for NAICS code 238110. A site visit is scheduled for August 1, 2024, and the RFI close date is August 6, 2024, with bid opening on August 14, 2024 at 1pm CST. The Pre-Bid RFI Log addresses questions related to the use of electric vs. gas grinders, HVAC system requirements, dust control measures, and HEPA filtration, as well as confirms the availability of a secured staging area on site.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sealed Bid OF 1419 Floor Coverings.pdf | ||
| Pre-Bid RFI Log Floor Covering Installation_12Aug24.pdf | ||
| Site Visit Slides Floor Coverings.pdf | ||
| Site Visit Slides Floor Coverings.pptx | PPTX presentation | |
| Site Visit sign in_Redacted.pdf | ||
| SOW_XHZG202400890_Floor Coverings.docx | DOCX document | |
| W50S8U-24-B-0003.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Date: RFI No. RFI QUESTION GOVERNMENT RESPONSE
7/30/2024 1 Per the SOW, does it matter if the concrete grinder/sander is electric or gas?
Must be electric. The work to be performed will be on the interior.
8/5/2024 2 The PWS does not include the requirement to tagout the HVAC system and block all air intake and return vents. Is this required?
Base will shutdown HVAC as needed. It is required to block all supply and return vents in work area(s).
8/5/2024 3 The PWS does not require the installation of temporary barriers to prevent dust flow into adjacent areas of the building. Is this a requirement?
Temporary barriers or plastic sheeting are required to prevent excess dust flow
8/5/2024 4 The PWS does not include the usage of HEPA filtration. Is this a requirement? HEPA filtration is required in work area(s).
8/5/2024 5 Does the base have a secured area where equipment can be staged and stored for the duration of the project? Yes, a location can be provided.
Pre-Bid RFI Log for Floor Covering Installation
Sheet1