Attach_08_ArmDrm_Submittal_Register_20240708.xlsx

XLSX spreadsheet 21 KB Posted

Attached to
Asphalt Paving: Mill & Overlay Airfield Pavement
Solicitation number
W50S8F-24-R-0002
Issued by

About this file

This document is an Attachment for a federal contract opportunity titled "Asphalt Paving: Mill & Overlay Airfield Pavement". The attachment is a Schedule of Material Submittals for the Mill & Overlay Airfield Pavements project, AQRC222011. It lists the various submittal items required from the contractor, such as safety plans, quality control plans, project schedules, material data sheets, paint and milling depth information, recycling slips, asphalt submittals, field test reports, and close-out documents. The due dates for these submittals range from prior to mobilization to prior to final payment.

The related federal contract opportunity is a Request for Quote (RFQ) for the Mill and Overlay of Airfield Asphalt Pavements at the 177th Fighter Wing in Egg Harbor Township, NJ. The work involves milling 2 inches and overlaying 2 inches of asphalt pavement across approximately 35,000 square feet, split between two separate locations on the active airfield. This is a 100% small business set-aside contract with a magnitude of construction between $100,000 and $250,000. Bid guarantee, payment, and performance bonds are required for offers above $150,000. The contract will be awarded in accordance with FAR Parts 13 and 36.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

SCHEDULE OF MATERIAL SUBMITTALSMill & Overlay Airfield PavementsAQRC222011AQRC222011
TO BE COMPLETED BY PROJECT ENGINEERContractorTO BE COMPLETED BY CONTRACT ADMINISTRATOR
NUMBER OF COPIES REQUIREDDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
SUBMITTAL NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATION OF COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONMFGR'S RECOMMENDATIONSMANUFACTURER'S WARRANTYCATALOG DATAOPERATION INSTRUCTIONPERFORMANCE TEST REPORTOTHERSUBMISSION DATEDATE CONTRACTOR NOTIFIED
APPROVEDDISAPPROVED
1Job Specific Safety PlanxPrior to Mobilizaton1
2Job Specific Quality Control PlanxPrior to Mobilizaton2
3AF 3064 (or equivalent)– Project SchedulexPrior to Mobilizaton3
4AF 3065 – Progress ReportxPrior to Mobilizaton4
5Key Personnel LetterxNTP5
6MSDS Sheets as requiredxNTP6
7Type of paint and quantity of beads requiredxxxxxNTP7
8Yellow Reflective paintxxxxxNTP8
9Milling depthxxxxxNTP9
10Recycling SlipsxNLT 5 Days from recycling10
11Asphalt submitalxxxxxNTP11
12Other submittals as required by Specifications or DrawingsxxxxxNTP12
1313
14Field Test ReportsxNLT 5 Days from date of test14
15Close-out Documents - Electronic copies onlyPrior to Final Payment15
16Contractor Warranties3Prior to Final Payment16
17Record Drawings3Prior to Final Payment17
18O&M Manual (if applicable)3333Prior to Final Payment18
19Maintenance Summary Forms3Prior to Final Payment19
20DD 1354 Worksheet1Prior to Final Payment20

File details come from the government source that posted it. Updated .