W50S8F-21-B-0001_MunDr_Ph03_Bid_QA_20210720.pdf

PDF 174 KB Posted

Attached to
AQRC212002- Replace Munitions Storage Igloo Doors, Ph. 3
Solicitation number
W50S8F-21-B-0001
Issued by

About this file

This solicitation seeks bids for a firm fixed-price contract to replace munitions storage igloo doors at an Air National Guard base. The contractor will remove and dispose of 18 existing steel doors, provide blast engineering for new doors, fabricate, deliver and install replacement doors in phases. The base work includes 4 doors, option 1 adds 6 doors, and options 2 and 3 each add 4 more doors. The contract duration is 300 days from notice to proceed. The opportunity is set aside exclusively for small businesses with a NAICS code of 236220 and size standard of $39.5 million. Bids are due by July 30th and pre-bid conference was held on July 13th. The solicitation includes instructions for bidding and requires payment and performance bonds with bids. All correspondence must be sent to the listed contracting office email addresses with the specified subject line.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation #: W50S8F‐21‐B‐0001 Project Name & Number: AQRC172008B: B260 Replace Munitions Storage Igloo Doors, Ph03

Updated: Tuesday, July 20, 2021

RFI # Submitted Answered Question Response Response By

1 13‐Jul‐21 13‐Jul‐21 It appears they are double leaf – can they have a center frame support?

Should this support be removable?

No. The doors can NOT have a center frame support. 177 CES

2 13‐Jul‐21 13‐Jul‐21 Is the blast pressure internal (Unseating) or external (Seating)? Internal 177 CES

3 13‐Jul‐21 13‐Jul‐21 It is stated that all outside testing agencies will be procured and paid by the Air National Guard, will these tests be required?

1. Testing shall be performed IAW with the drawing and specifications.

2. The Government reserves the right to conduct testing and inspections IAW 52.246‐1 Contractor Inspection Requirements and 52.246‐12 Inspection of Construction.

2.1 https://www.acquisition.gov/content/52246‐1‐contractor‐inspection‐ requirements

2.2 https://www.acquisition.gov/content/52246‐12‐inspection‐construction

177 MSC

4 13‐Jul‐21 13‐Jul‐21 Does the storage cells being worked on need to able to locked at night or weather tight if the removal & installation takes longer than 1 day?

No. The individual cells being worked on will be empty. They do not need to be secured or weathertight at the end of the work day.

177 MXG

5 14‐Jul‐21 20‐Jul‐21

Is there a basis of design for the blast doors?

The door systems are not a Commercially Off the Shelf (COTS) item and there is no Basis of Design.

The contactor shall provide engineering, blast calculations, & fabrication in accordance with the Drawings & Specifications.

6 14‐Jul‐21 20‐Jul‐21 Please confirm that the supervisor can perform multiple roles, such as the site supervisor & quality control manager.

The Site Supervisor may perform mutliple roles. The individual identified for each key role SHALL contain the appropiate training, certifications, & requisite experience as indentified in the Scope of Work and Solicitation Provisions & Clauses.

177 MSC

7 14‐Jul‐21 20‐Jul‐21 On Sheet S‐001, Special Instructions, Note 1: Is the contractor to include the cost of testing in our proposal or is this on the customer?

The contractor SHALL include the cost of all testing required in his cost proposal.

For additional information on testing; see question 3 above.

8 15‐Jul‐21 20‐Jul‐21 Drawing SF‐101; Keynote#1 calls to remove loose concrete and apply corrosion inhibitor.

Please confirm if this work is included in our scope for this phase? If so, please provide the exact locations required for patching.

Key Note #1 ‐ Removal & Repaird of loosed concrete is NOT part of this Project.

Only the door systems as descibed in the Scope of Work (SOW) are included in this Solicitation.

177 MSC

177th Fighter Wing Pre-Bid RFI Questions & Clarifications

2021-07-20T09:33:55-0400
SHERRY.KIRK.EDWARD.1031221893