RFI 1.pdf

PDF 70 KB Posted

Attached to
Bldg. 208 Floor Pit Repairs Federal contract opportunity
Solicitation number
W50S8D24Q0007
Issued by
Department of the Army National Guard

About this file

This document is a Request for Information (RFI) related to the federal contract opportunity for Bldg. 208 Floor Pit Repairs, Solicitation Number W50S8D24Q0007.

The key details are:

  1. The statement made during the site visit that all fill removed from the pit was to be disposed of off base was incorrect. Per the Statement of Work, the contractor shall place the removed fill and spoils in a stockpile on base, with the location to be determined by the Contracting Officer's Representative (COR).
  2. There are no depths provided for the removal of existing debris and stone in the pits, nor for the depth of the concrete slab or underlayment. The contracting agency has referenced attached as-built files 208-s1.jpeg, 208-s2.jpeg, and 208-s3.jpeg to provide this information.

View the file

Other files for this federal contract opportunity

Other files attached to Bldg. 208 Floor Pit Repairs, newest first.
File Type Posted
208-s3.jpeg JPEG file
208-s1.jpeg JPEG file
208-s2.jpeg JPEG file
Solicitation Amendment W50S8D24Q0007_0001.pdf PDF
Statement of Work - Revised 19 April 2024.pdf PDF
Pre-Proposal Conference Minutes.pdf PDF
Pre-Proposal Conference Attendance Sheet.pdf PDF
Bldg. 208 Floor.jpg JPG image
Statement of Work.pdf PDF
W50S8D24Q0007.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. At the site visit it was stated that all fill removed from the pit was to be disposed of off base.

The statement of work states that it will be placed in a stockpile on base. Please clarify?

The information disseminated at the site visit was incorrect. The contractor shall remove the crushed stone and debris from inside the pit. The contractor shall place the removed fill and spoils in a stockpile on base, location to be determined by the COR per the Statement of Work.

2. There are no depths given for the removal of existing debris and stone in the pits. Also, no depth of concrete slab or underlayment is given to allow us to calculate the volume of concrete required?

Please reference the attached as-built files 208-s1.jpeg, 208-s2.jpeg, and 208-s3.jpeg.