01 PWS MTC- ANG Demo - 1405 (2) sf table r2.pdf
PDF 252 KB Posted
- Attached to
- VGLZ 232024 Demolition of B-1405
- Solicitation number
- W50S8524B0014
About this file
This document is a Performance Work Statement (PWS) for demolition services at Building 1405 on Selfridge Air National Guard Base in Michigan. The key objectives are to demolish and remove Building 1405, all paved surfaces, sidewalks, site amenities, and utilities, and to backfill and landscape the site to match the adjacent terrain.
The contractor shall provide all personnel, equipment, and materials to perform the demolition work. The period of performance is 180 calendar days. The contractor is responsible for obtaining all required permits and testing for asbestos prior to demolition. Disposal of all demolished materials shall be offsite. The contractor must comply with all applicable safety, environmental, and security regulations during performance.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
FOR
DEMOLITION SERVICES BUILDING 1405
SELFRIDGE AIR NATIONAL GUARD BASE, MICHIGAN
1.0 General:
1.1 Scope: The contractor shall provide all personnel, equipment, licenses, permits, tools, materials, supervision, and quality control necessary, except as specified in Paragraph 3.0 as Government Furnished, to perform Demolition Services, as defined in this PWS.
1.1.1 Objectives: Demolish and remove Building 1405, all paved surfaces, sidewalks and site amenities such as fences, light poles. Utilities shall be disconnected and capped. The landscape shall be backfilled and planted to match and blend with adjacent terrain.
1.2 Background: Selfridge is currently in excess of total building area defined by NGB’s criteria. As building 1405 is vacant with no foreseeable occupancy, it is determined this building shall be demolished to bring Selfridge total building area closer to compliance with the NGB requirements.
1.3 Period of Performance (PoP): The Period of Performance shall be 180 calendar days from award.
1.4 General Information: This building was constructed in the 1970’s. The structure is cast in place concrete columns and floors. The foundation is spread footings. The exterior walls are masonry, the interior wass a masonry and framed gypsum board partitions. There is a small basement in the southeast corner of the building for mechanical equipment. The roof is a low slope membrane system.
1.4.1 Place and Performance of Services: The contractor shall provide services between the hours of (0700-1700) on Monday through Friday, except on recognized US holidays or when the Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings. Performance shall be at Selfridge ANGB, Building 1405, West Perimeter Road, Harrison Township, Michigan 48045. The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential. Teleworking is not authorized.
1.4.1.1 Telework: This service is not conducive to Telework.
1.4.1.2 Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented.
Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.
1.4.1.3 The contractor’s employees shall become familiar with and obey the regulations of the installation, including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times and shall be subject to such checks as may be deemed necessary. The contractor shall ensure compliance with all regulations and orders of the installation, which may affect performance.
The Government reserves the right to direct the removal of an employee from Government property or revoke access to Government systems for misconduct, security reasons, or any overt evidence of communicable disease. Removal of contractor employees for reasons stated above does not relieve the Contractor from responsibility for total performance of this contract.
1.4.2 Recognized Holidays: The following are recognized United States (US) holidays. The contractor shall not perform services on these days:
New Year’s Day 1 January Martin Luther King, Jr.’s Birthday 3rd Monday in January Presidents Day 3rd Monday in February Memorial Day Last Monday in May Juneteenth 19 June Independence Day 4 July Labor Day 1st Monday in September Columbus Day 2nd Monday in October Veterans Day 11 November Thanksgiving Day 4th Thursday in November Christmas 25 December
1.4.3 Quality Control (QC): The contractor shall develop and maintain an effective QC Plan (QCP) to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract. As a minimum, the contractor shall develop QC procedures that address the areas identified in Technical Exhibit 1, Performance Requirements Summary (PRS). A final QCP shall be submitted to the Contracting Officer Representative (COR) NLT 10 days after contract award. After acceptance of the QCP, the contractor shall obtain the Contracting Officer’s (KO’s) acceptance in writing of any proposed changes to its QCP. See also Spec Section 01 00 00, Part 1.22, B.
1.4.4 Quality Assurance (QA): The Government will evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government will do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) or defect rate(s).
1.4.5 Access and General Protection /Security Policy and Procedures. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, Headquarters Air Force (HAF) and/or local policy.
Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
1. The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.
2. Prior to access the contractor shall submit a written request on the current Base Access Form to the contracting specialist providing all requested information. The contracting specialist will forward the request to the issuing base Pass and Registration office / Security Forces mailbox for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver’s license, current vehicle registration, valid vehicle insurance certificate, and official documentation of a social security number to obtain a dbids identification or base pass.
3. During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.
4. Reserved
5. Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.
6. Failure to comply with these requirements may result in withholding of final payment.
1.4.5.1 CAC Reserved
1.4.5.2 For Contractors that do not require CAC, but require access to a DoD Facility and/or Installation.
Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) DoDIO-2000.16v1, DAFI 31-101 and applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by Government representative)
1.4.5.3 Antiterrorism Awareness Level I Training (AT Level I). All contractor employees, to include subcontractor employees, requiring access to US Government installations, facilities and controlled access areas shall complete AT Level I training within 15 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. AT Level I may be accomplished by a Level I qualified instructor; completing the Force Protection computer-based training (CBT) course on Joint Knowledge Online at http://jko.jten.mil. Tracking for each contractor or subcontractor employee is the responsibility of the COR or unit AT Representative. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee to the COR within 15 calendar days after completion of training by each employee or subcontractor personnel.
1.4.5.4 iWATCH Training: (RESERVED)
1.4.5.5 Communications Security/Information Technology (COMSEC/IT) Security. All communications with DoD organizations are subject to COMSEC review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DoD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DoD organizations. Therefore, the contractor is advised that any time contractor personnel http://jko.jten.mil/
STOCKING, STEVEN A CIV USAF ANG 127 MSG/MSC
The inspectors handle base access requests post award. Helps to coordinate any last minute escort requirements.
place or receive a call they are subject to COMSEC procedures. The contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DoD information. The contractor shall abide by all Government regulations concerning the authorized use of the Government's computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.
1.4.5.6 through 1.4.5.14 (RESERVED)
1.4.6 Physical Security. The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.
1.4.6.1 Key Control. : (RESERVED)
1.4.6.2 Lock Combinations: (RESERVED)
1.4.6.3 Compliance with Laws and Regulations. The contractor shall be knowledgeable of and comply with all applicable Federal, State, and local laws, regulations, and requirements regarding environmental protection to include AFI 32-7001 Environmental Management and AFMAN 32-7002 Environmental Compliance and Pollution Prevention. In the event environmental laws/regulations/requirements change during the term of this contract, the contractor shall comply with such laws/regulations as changed.
1.4.7 Special Qualifications: The contractor shall ensure all employees possess all required licenses for operating heavy equipment used in the performance of this contract. This does not include education or other qualifications for the position in which the contractor employee is performing, dress codes, or other information. (NOTE: The Government does not provide training to contractors. Contractors must ensure that any personnel performing under a contract are fully trained, licensed, certified, and otherwise qualified to provide services.)
1.4.8 Post Award Conference/Periodic Progress Meetings: The contractor agrees to attend any post award conference convened by the KO in accordance with FAR 42.5. The KO, COR and other Government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the KO will apprise the contractor of how the Government views the contractor’s performance and the contractor shall apprise the Government of problems, if any, being experienced. The contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.
1.4.9 Contract Manager (CM): The contactor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR, to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.
1.4.10 Identification of Contractor Employees: All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately
This would be in addition to a Superintendent. Superintendents don’t often have such broad authority unless it’s a really small project.
disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence types (to include signature blocks on e-mail) and dealings with Government or non- Government entities. Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word “contractor” displayed.
1.4.10.1 The contractor shall retrieve all identification media (including vehicle passes) from its employees who depart employment for any reason. The contractor shall return all identification media (i.e., badges and vehicles passes) to the KO within 14 days of an employee’s departure.
1.4.11. Combating Trafficking in Persons: The United States Government has adopted a zero-tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. The contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at FAR 22.17.
1.4.12 Contractor Travel: (RESERVED)
1.4.13 Data Rights: (RESERVED)
1.4.14 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications, or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may impose other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.
1.4.15 Phase In / Phase Out Periods: (RESERVED)
2.0 Definitions and Acronyms:
2.1 Definitions:
2.1.1 Contractor: A supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.
2.1.2 Defective Service: A service output that does not meet the standard of performance associated with the PWS.
2.1.3 Deliverable: Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.
2.1.4 Key Personnel: Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.5 Physical Security: Actions that prevent the loss or damage of Government property.
2.1.6 Quality Assurance: The Government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.7 Quality Assurance Surveillance Plan (QASP): An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.8 Quality Control: All necessary measures taken by the Contractor to ensure that the quality of an end product or service shall meet contract requirements.
2.1.9 Subcontractor: One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.
2.2 Acronyms:
AEI Army Enterprise Infostructure AR Army Regulation AT/OPSEC Antiterrorism/Operational Security BI Background Investigation CM Contract Manager COR Contracting Officer Representative DA Department of the Army DFARS Defense Federal Acquisition Regulation Supplement DoD Department of Defense DSCA Defense Counterintelligence and Security Agency FAR Federal Acquisition Regulation GFP/M/E/S Government Furnished Property/Material/Equipment/Services HSPD Homeland Security Presidential Directive IA Information Assurance IS Information System(s) KO Contracting Officer NGB National Guard Bureau OCI Organizational Conflict of Interest PII Personally Identifiable Information PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program SCR Service Contract Reporting SSN Social Security Number TE Technical Exhibit USD(I) Under Secretary of Defense for Intelligence
3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S): The Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract: NONE
3.1 Property: NONE
3.2 Materials: NONE
3.3 Equipment: NONE
3.4 Services: Security Police and Fire Protection. Phone Number 911. If using a cell phone on base to call 911 the user must identify that they are at Selfridge and the call will then be transferred to Selfridge.
3.5 Utilities: NONE
4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E):
4.1 General: Except for those items specifically stated to be Government-Furnished in Paragraph 3.0, the contractor shall furnish everything required to perform these services as indicated in Paragraph 1.1.
4.2 Facility Clearance: N/A
4.3 Contractor Security Clearance: N/A
4.4 Personal Protection Equipment (PPE). Contractor shall provide all employees sufficient PPE for performing all tasks and shall ensure employees utilize the PPE at all times.
4.5 The contractor shall possess a current Contractor license as required for his trade issued by the State of Michigan. License shall be provided with quote.
4.6 All contractor employees who operate motorized vehicles on SANGB shall possess a current state driver’s license.
4.7 Vehicles. All vehicles used by the contractor shall be registered, licensed, and insured at all times. Vehicles found to be unsafe or unable to function as designed shall be removed from the installation at the contractor’s expense. Vehicle repairs shall not be accomplished on base.
4.7.1 Contractor vehicles shall have the company name prominently displayed on both sides of the vehicle.
4.8 The contractor shall provide their own temporary toilet facilities. Facilities shall meet the requirements of health authorities and shall be kept clean and in a sanitary contition at all times.
5.0 Requirements: The contractor shall:
5.1 Provide a detailed work schedule within 10 calendar days prior to start of work.
5.1.1 Permits: Contractor is responsible for obtaining all required permits before proceeding. & 2.2 A
5.1.2 Provide a perimeter construction fence with locking gate.
This should be contractor owned vehicles. Although a Superintendent might be using their own vehicle.
5.1.3 Provide silt protection at the site perimeter and at all drains and catch basins. Provide filters in the catch basins. Ensure that silt protections is inspected periodically. Repair or replace as needed to maintain the protection.
5.1.4 It is suspected there is asbestos present in the vinyl floor tile and/or the tile adhesive. There is approximately 29,240 s.f. of vinyl flooring with adhesive in the building. See the table below for a breakdown of the vinyl floor types.
Building 1405 Vinyl Tile Floor Areas (SF)
Vinyl Tile Carpet over
Vinyl Tile Adhesive
Only 1st Floor 7,7267 6,938 46 2nd Floor 7,203 7,326 sub-totals 14,930 14,264 46
Total (SF) 29,240
5.1.4.1 The Contractor shall test for asbestos in the building and suspected areas on the site.
Engage an independent certified testing agency to test suspected areas and submit findings to the Contracting Officer. The report to include existing quantities of hazardous material to be abated.
5.1.4.2 If the quantities of asbestos in the Contractor provided asbestos survey do materially differ from the asbestos quantities listed in the above table and cause an increase or decrease in the Contractor’s cost of, or the time required for, performing any asbestos abatement under this contract an equitable adjustment shall be made under this clause and the contract modified in writing accordingly.
5.1.4.3 All work including the handling of hazardous materials or the disturbance or dismantling of structures containing hazardous materials shall comply with the applicable requirements of 29 CFR 1910/1926. Work involving the disturbance or dismantling of asbestos or asbestos- containing materials; the demolition of structures containing asbestos; and/or disposal and removal of asbestos, shall also comply with the requirements of 40 CFR, Part 61, Subparts A and B, ETL 1110-1-118 and DA Circular 40-83-4. All work shall comply with applicable state and municipal safety and health requirements. Where there is a conflict between applicable regulations, the most stringent shall apply. The Safety Manual is available at the following web site: http://www.usace.army.mil/inet/usace-docs/eng-manuals/em385-1- 1/toc.htm. The Contractor shall assume full responsibility and liability for compliance with all applicable regulations pertaining to the health and safety of personnel during the execution of work. The Government shall not be held liable for any actions on the part of the Contractor, any tier subcontractor(s), or any of their respective employees that result in illness, injury, or death. Work shall conform to EM 385-1-1, US Army Corps of Engineers Safety and Health Requirements Manual.
B. The required inspections, tests and reports made by the Contractor, any tier subcontractor(s), specially trained technicians, equipment manufacturers, and others as required, shall be at the Contractor’s expense (herein attached). Reference FAR Clause: 52.236-13 Accident Prevention C. Special facilities, devices, equipment, clothing, and similar items used by the Contractor in the execution of work shall comply with applicable regulations.
All work including the handling of hazardous materials or the disturbance or dismantling of structures containing hazardous materials shall comply with the applicable requirements of 29 CFR 1910/1926
(https://www.osha.gov/laws/regulations/standardnumber/1026 (osha.gov)). Work involving the disturbance or dismantling of asbestos or asbestos- containing materials; the demolition of structures containing asbestos; and/or disposal and removal of asbestos, shall also comply with the requirements of 40 CFR, Part 61, Subparts A and B, ETL 1110-1-118 and DA Circular 40-83-4. (https://www.ecfr.gov/current/title-40/chapter-1/subchapter-C/part-61) All work shall comply with applicable state and municipal safety and health requirements. Where there is a conflict between applicable regulations, the most stringent shall apply.
5.1.4.4 The Safety Manual is available at the following web site: http://www.usace.army.mil/inet/usace-docs/eng-manuals/em385-1- 1/toc.htm. The Contractor shall assume full responsibility and liability for compliance with all applicable regulations pertaining to the health and safety of personnel during the execution of work. The Government shall not be held liable for any actions on the part of the Contractor, any tier subcontractor(s), or any of their respective employees that result in illness, injury, or death. Work shall conform to EM 385-1-1, US Army Corps of Engineers Safety and Health Requirements Manual.
5.1.4.5 Special facilities, devices, equipment, clothing, and similar items used by the Contractor in the execution of work shall comply with applicable regulations.
5.1.4.6 Where an employee can fall more than 6 feet, a fall protection system must be used;
29 CFR 1926.500 stipulates where this can occur and the different types of fall arrest systems.
5.1.4.7 The Contractor must provide Material Safety Data Sheets (MSDS) to the Contracting Officer and receive approval before they begin the work.
5.1.4.7 All references to protection of the site and adjacent buildings when trenching, shall include protection of all employees also.
5.1.5 Demolish and remove Building 1405 and structures entirely, all paved surfaces, foundation, sidewalks and site amenities such as fences, light poles.
5.1.5.1 Repair pavements, edges, and curbs to remain that are damaged by demolition activities.
5.1.5.2 Remove all trees, brush, and overgrowth from the project site, and as noted on the contract drawings.
5.1.5.3 Ash trees removed shall be hauled to a designated area on the Base as directed by the Contracting Officer.
5.1.4.4 Stockpile any topsoil and other spoils resulting from demolition for redistribution. All roots, stone, construction debris and any other foreign materials shall be removed from the topsoil before redistribution.
5.1.5.5 Provide fill to match adjacent soil materials to raise topography depressed by demolition to elevations as indicated on the drawings. Fill material shall be free of organic material, debris, and contaminants. Compact soils in maximum twelve (12) inch lifts and compact to 95 percent density. The top six (6) inches of the fill shall be topsoil.
5.1.5.6 Grade, level and seed all areas of disturbed landscape.
5.1.5.7 Dispose of all demolished material off site. See paragraph 2.7.3 below.
5.1.5.8 The Contractor shall submit a crane lift plan for Government review. For crane and lift operations, the Contractor shall obtain FAA and Airfield Operations permits.
5.1.5.9 All utility meters and gas regulators shall be turned over to Selfridge ANG Base at a location designated by the Contracting Officer.
5.1.5.10 NESHAP notification for demolition and abatement shall be reported to the State of Michigan.
https://www.osha.gov/laws/regulations/standardnumber/1026%20(osha.gov) https://www.ecfr.gov/current/title-40/chapter-1/subchapter-C/part-61
5.1.5.11 The Contractor shall, under regulations prescribed by the Contracting Officer, use only authorized roadways. When materials are transported in prosecution of the work, vehicles shall not be loaded beyond the loading limit established by Federal, State and Local law or regulation.
5.1.4.12 POLLUTION PREVENTION: See Specification Section 01 00 00, Part 1, 1.50 Pollution Prevention
5.1.4.13 ENVIRONMENTAL IMPACT: See Specification Section 01 00 00, Part 1, 1.52 Environmental Impact
5.1.4.14 MAINTENANCE OF TRAFFIC AND SAFETY: See Specification Section 01 00 00, Part 1,
1.45 Maintenance Of Traffic And Safety.
5.1.4.15 Utilities shall be disconnected and capped below grade.
5.2 Provide fill to the site. The landscape shall be backfilled and uniformly graded to ensure adequate drainage, planted to match and blend with adjacent terrain. Proportion grass species as follows:
Botanical Name Common Name Percent Festuca Arundiance Tall Fescue 85% Poa Pratensis Kentucky Bluegrass 15%
5.3 Due to proximity to the airfield the contractor shall maintain the site in as clean and orderly condition as possible. All refuse and/or salvage material shall be gathered and disposed of periodically to maintain the site. All roadways, taxiways and ramp areas within the work area shall be swept and vacuumed daily to assure safe operation of aircraft.
5.4 Field Office facilities are not required for this project.
5.4.1 STORAGE: See Specification Section 01 00 00, Part 1, 1.31 for storage on site.
5.5 SITE CLEANUP: See Specification Section 01 00 00, Part 1, 1.28 for site cleanup requirements.
5.6 Immediately clean up any debris tracked onto the Installation’s streets resulting from this construction operation.
5.7 INSPECTION AND ACCEPTANCE: See Specification Section 01 00 00, Part 1, 1.57. Final inspection by COR, then inspection by the KO and CE. Any discrepancies noted shall be corrected.
Entire site shall be free of debris or materials.
6.0 Applicable Publications: Publications applicable to this PWS are listed below:
Publication (Chapter/Page)
Date of Publication
Mandatory or
Advisory
Website
Federal Acquisition Regulation Mandatory https://www.acquisition.gov/?q=browsefar Defense Federal Acquisition
Regulation Supplement Mandatory http://www.acq.osd.mil/dpap/dars/dfarspgi/current/i ndex.html or https://www.acquisition.gov/dfars DoDIO-2000.16v1
DoD Antiterrorism Program Implementation: DoD Antiterrorism Standards
Nov 17, Chg #3 May 7, 2021
M https://www.esd.whs.mil/Directives/issuances/dodi/
DAFI 31-101
Integrated Defense (ID)
24 Mar
M https://www.e-publishing.af.mil/ https://www.acquisition.gov/?q=browsefar http://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html http://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html https://www.acquisition.gov/dfars https://www.esd.whs.mil/Directives/issuances/dodi/ https://www.e-publishing.af.mil/
AFI 32-7001
Environmental Management
Aug
M https://www.e-publishing.af.mil/
AFMAN 32-7002
Environmental Compliance and Pollution Prevention
FEB
M https://www.e-publishing.af.mil/
29 CFR 1910/1926 M https://www.ecfr.gov 40 CFR, Part 61 https://www.ecfr.gov
ETL 1110-1-118
Use of Asbestos Containing Materials
1 May
M https://standards.global spec.com/std/851503/coe-etl-1110-1-118 https://www.ecfr.gov/ https://www.ecfr.gov/
TECHNICAL EXHIBIT 1
Performance Requirements Summary (PRS)
This PRS includes performance objectives the Government will use to determine contractor performance and will compare contractor performance to the Acceptable Quality Level (AQL).
Performance Objective
Performance Standard Acceptable Quality Levels
(AQL)
Surveillance Method / By
Whom 5.1.1
Silt protection
• Silt protection is properly installed at all required locations.
Silt protection is maintained throughout service
AQL: Max.10 minor discrepancies found and corrected during inspection.
COR
5.1.2 Asbestos and
Lead – Testing Report
Testing for Asbestos and Lead is by a certified agency. Report is provided to COR within 2 calendar days of receipt.
AQL; Report is from a certified testing agency and is provided to COR within required timeframe.
Report includes quantities of material to be abated
COR
1.1.1 & 5.1.3 Demolish building, paved surfaces and site amenities
All visible items shall be identified, demolished, and removed from site.
Examples include loose and embedded metal, elevated concrete, abandoned equipment, and utility structures around the specified demo site.
AQL: Work meets requirements.
Minor discrepancies found are corrected.
COR
5.2 Site Fill
Fill is provided, landscaped, graded and planted to match and blend with adjacent terrain.
AQL: Sufficient quantity of fill is provided and properly landscaped.
COR and Customer Feedback / Complaint
TECHNICAL EXHIBIT 2
Deliverables Schedule
PWS Reference / Deliverable Title
Frequency Number of Copies
Medium/Format Submit To
1.4.3
QCP
Within 10 days after award 1 Electronic Submission
KO & COR
1.4.5 Base Access Information
Prior to accessing the installation
Electronic
KO
1.4.5.3 AT Level I
Provide proof of training within 15 calendar days after contract start
Electronic
Submission
COR
1.4.7 & 4 Special
Qualifications
Submit licenses and certifications with quote
1 Electronic Submission
COR
1.4.9 Contract
Manager (CM)
Provide within 10 days after award.
1 Electronic Submission
COR/KO
1.4.10.1 Contractor
Identification
Return within 14 days of an employee’s departure from contract performance
1 Original COR/CS
5.1 Work Schedule
Provide prior to start of work.
1 Electronic Submission
COR
TECHNICAL EXHIBIT 3
Estimated Workload Data
(RESERVED)