This document is an amendment to a federal solicitation for W50S8524B0002, titled "VGLZ 212001 REPAIR SIMULATOR HEATING". The amendment makes the following key changes: 1) Updates the applicable wage determination, 2) Clarifies that no transformers are required for this project, and 3) States that there are no other changes and all other terms and conditions remain the same.

The underlying solicitation is for a firm-fixed price contract to repair existing air conditioning systems and install an independent AC system to provide additional cooling capacity for B34 simulators at Selfridge ANGB, MI. The project also includes minor construction of a building access ramp and sidewalk. The solicitation is 100% set aside for small businesses, and the NAICS code is 238220 - Plumbing, Heating, and Air-Conditioning Contractors. Prospective bidders are required to attend a pre-bid conference and site visit. The period of performance is 365 calendar days after the notice to proceed, and the government anticipates funding will be available prior to but no later than September 30, 2024.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F8Y36H4024A001 VGLZ 212001

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to make the follow ing changes in accordance w ith the enclosed " Summary of Changes"

1. Update the Wage Determination to General Decision Number: MI20240091 04/05/2024.

2. Clarify that there are no transformers required for this project.

3. There are no other changes and all other terms and conditions shall remain the same.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 15

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 24-Apr-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W50S8524B0002

X 9B. DATED (SEE ITEM 11)

02-Apr-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

24-Apr-2024

CODE

USPFO MI 127 MISSION SUPPORT CONTRACTING

43200 MAPLE ST

SELFRIDGE ANGB MI 48045-5213

W50S85 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W50S8524B0002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 21 00 - INSTRUCTIONS

The following have been modified:

INSTRUCTIONS TO BIDDERS

SECTION 00 21 00 INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

1. Description of the Project: Repair existing air conditioning systems by installing an independent air conditioning system to provide additional cooling capacity to B34 simulators due to excess heat. Minor construction of building access ramp and sidewalk is also included

2. INSTRUCTIONS TO BIDDERS:

2.1. You are invited to submit a bid in response to our Invitation for Bid (IFB) titled:

W50S85-24-B-0002, VGLZ 212001 REPAIR SIMULATOR HEATING at Selfridge

ANGB, MI 48045.

2.2. As a result of this solicitation, the Government intends to award a Firm Fixed Price (FFP) contract resulting from this solicitation to the responsible bidder whose bid, conforming to the invitation for bids, will be most advantageous to the Government, considering only price.

2.3. This solicitation is set aside 100% for small business.

2.4. A formatted disk (CD) with all documents required by this bid shall be submitted.

3. NOTICE OF PRE-BID CONFERENCE AND SITE VISIT:

3.1. A pre-bid conference will be conducted, See Clause 52.236-27 “Site Visit” for time, date, and location.

3.2. Due to security conditions, all Bidders must register to attend this conference and site visit. For entrance please fill out and submit the attached “Selfridge Base Vetting” Excel Spreadsheet to Steven Stocking at steven.stocking.2@us.af.mil and Anna Randall at anna.randall.1@us.af.mil at least 3 business days prior to the Site Visit.

3.3. This information must be provided in advance, 3 business days prior to the meeting, in order to ensure access to the military base and conference site and ensure adequate seating for the conference attendees. Even if you have access to the base you must register to ensure adequate seating. The furnishing of the above information is voluntary; however, your failure to furnish all or part of the requested information may result in the Government’s denial of your access to the pre-proposal conference. This information will be provided to the Base Security Forces, who will authorize your entrance to the site.

3.4. Visitors must pick up their passes at the Installation’s Main Entry Gate prior to arrival.

You will be required to present the following information upon arrival: (1) Vehicle Registration, (2) Valid Driver’s License, (3) Proof of Insurance for Vehicle, (4) Safety Inspection and Car Rental agreement if applicable, official documentation of a social security number. Any of the above information furnished by you is protected under the Privacy Act and shall not be released unless permitted by law and/or you have consented to such.

3.5. Information provided at this conference or site visit shall not qualify the terms and conditions of the solicitation and specifications. Terms of the solicitation and specifications remain unchanged unless the solicitation is amended in writing. If an amendment is issued, normal procedures relating to the acknowledgment and receipt of solicitation amendments shall apply.

3.6. A record of the conference shall be made and furnished to all prospective bidders via posting at www.SAM.gov. The record will include minutes of the meeting, including questions (on a non-attribution basis) and answers

4. FORMAL COMMUNICATION, BIDDER EXPLANATIONS:

4.1. Submit all questions in the format shown below by email to the contracting office at the addresses show below. Do NOT contact AE or Engineering personnel directly. Doing so will only delay your answer. All questions must come through the Contracting Office.

Subject Line: Reference No. SOLICITATION W50S85-24-B-0002 Email:

steven.stocking.2@us.af.mil and anna.randall.1@us.af.mil .

PRE-BID INQUIRY FORMAT

Date of Bid Inquiry:

From: Company Name:

Address:

Phone Number:

Fax Number

Email address:

Bid Inquiry: (Please clearly state your question. If sent via an attachment, word documents are preferred to facilitate posting of answers to the master Q&A document.)

4.2. Any explanation desired by a bidder regarding the meaning or interpretation of the solicitation, or proposals, drawings, specifications, etc. must be requested in writing and with sufficient time allowed for a reply to reach bidders before the submission of their bid.

4.3. All questions and requests for information (RFI) must be received NOT LATER THAN the fifth working day prior to bid opening. BIDDERS ARE STRONGLY

ENCOURAGED TO SUBMIT QUESTIONSEARLY IN THIS PROCESS.

4.4. Any changes to the drawings, specifications, etc. will be issued in the form of an amendment. However, any answers that clarify or provide an interpretation to the drawings, specifications, etc. will NOT be posted via amendment but rather as a response to the RFI on SAM.gov at https://www.SAM.gov .

4.5. Receipt by the bidder must be acknowledged in the space provided on the SF 1442 or by returning a signed copy of the amendment by the time set for receipt of bids.

4.6. For security reasons, all technical and engineering data related to this solicitation will be distributed using the Contract Opportunities (SAM.gov) system. Plans and specifications are locked on SAM.gov and require Contractors to request explicit access from the Contracting Officer OR export controlled access through DLA. See complete instructions on SAM.gov. SAM.gov is a web-based dissemination tool designed to safeguard acquisition- related information for all Federal agencies. Interested bidders/offerors must register with SAM.gov before accessing the system.

4.7. Amendments, if/when issued will be posted to https://www.SAM.gov for electronic downloading. This will normally be the only method of distributing amendments prior to closing; therefore, it is the Bidders responsibility to check the website periodically for any amendments to the solicitation. Websites are occasionally inaccessible due to various reasons.

5. BID REPOSITORY AND BID OPENING:

5.1. A bid repository is provided for hand carried bids and is located at 43200 Maple Street, Bldg. 105, Selfridge ANGB, MI 48045-5213 (North West Entrance, Contracting Conference Room). Hand carried bids must be deposited in the repository prior to the time established for opening of bids. Bidders are cautioned that they will be required to sign-in and obtain a visitor’s pass to enter the facility and should allow time to accomplish this. See instructions for obtaining access to the base in the Site Visit instruction. Follow the same instruction for obtaining entry to hand carry a bid. Late receipt of bids due to entry delays may not be deemed excusable and the Contracting Officer may declare the bid “late” in accordance with

FAR 14.304.

5.2. The bid opening will occur at the time and date specified in Block 13 of the SF1442, and will be held at 43200 Maple Street, Bldg. 105, Selfridge ANGB, MI 48045-5213 (North West Entrance, Contracting Conference Room). All interested Bidders and their major subcontractors are encouraged to attend the bid opening.

6. WAGE DETERMINATION:

6.1. Construction Wage Rates are applicable to this project are Construction –Building for Macomb County, Michigan (48045) as shown in Section 00 73 00.

7. BID PREPARATION EXPENSES AND PRE-CONTRACT COSTS:

7.1. This IFB does not commit the Government to pay costs incurred in preparation and submission of bids or for other costs incurred prior to award of a formal contract.

8. CLAUSES:

8.1. Clauses and provisions from the Federal Acquisition Regulation (FAR) and supplements thereto are incorporated in this document by reference and in full text. Those incorporated by reference have the same force and effect as if they were given in full text.

9. DISPOSITION OF UNSUCCESSFUL BIDS:

9.1. In compliance with FAR Subpart 4.8, the Government will retain one copy of all unsuccessful bids including the bid bond.

10. BIDDERS QUALIFICATIONS

10.1. To establish its responsibility, the apparent low bidder may be requested by the Government prior to award, to submit a statement regarding his previous experience in performing comparable work, his business and technical organization, financial and bonding resources and plant available to be used in performing the work. This action may be requested to determine if the contractor is responsible.

11. SUBCONTRACTING PLAN: N/A

12. BRAND NAME REQUIREMENTS: Automated Logic Direct Digital ControlsNGB

13. NGBAgency Protest Information:

NG Agency Protest Program is intended to encourage interested parties to seek resolution of their concerns with the National Guard (NG) as an Alternative Dispute Resolution forum, rather than filing a protest with the Government Accountability Office (GAO) or other external forum.Contract award or performance is suspended during the protest to the same extent, and within the same time periods as if filed at the GAO.

The NG protest decision goal is to resolve protests within 35 calendar days from filing. An agency protest may be filed with either the Contracting Officer or the NG Agency’s Protest Decision Authority, but not both, in accordance with NG protest procedures.

13.1 To be timely, the protests must be filed with the periods specified in FAR 33.103. To file a protest under the NG Agency Protest Program, the protest must request resolution under that program and be sent to the address below:

National Guard Bureau Office of the Director of Acquisitions/ Head of Contracting Activity ATTN: NGB-AQ-O 111 S. George Mason Dr. Arlington, VA 22204 Email: ng.ncr.ngb-arng.mbx.ngb-task-order-ombudsman@mail.mil

13.2 All other agency-level protests should be sent to the Contracting Officer for resolution at the address in the solicitation. See FAR clause 52.233-2.

SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS

The following have been modified:

WAGE DETERMINATION

"General Decision Number: MI20240091 04/05/2024

Superseded General Decision Number: MI20230091

State: Michigan

Construction Type: Building

County: Macomb County in Michigan.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.

Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).

|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.20 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2024. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $12.90 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2024. |

The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.

Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/05/2024 1 01/19/2024 2 04/05/2024

* ASBE0025-002 06/01/2023

Rates Fringes

ASBESTOS WORKER/HEAT & FROST

INSULATOR........................$ 37.98 34.27

* BOIL0169-001 01/01/2024

Rates Fringes

BOILERMAKER......................$ 39.65 35.68

BRMI0001-001 06/01/2022

Rates Fringes

BRICKLAYER.......................$ 38.87 25.18

TILE FINISHER....................$ 30.75 22.67

TILE SETTER......................$ 37.88 22.67

CARP0687-003 06/01/2023

Rates Fringes

CARPENTER (Including Acoustical Ceiling Installation, Drywall Hanging, Form Work, Metal Stud Installation & Scaffold Building)........................$ 40.98 30.22

CARP1045-001 06/01/2023

Rates Fringes

CARPENTER (Floor Layer - Carpet, Resilient, & Vinyl Flooring)........................$ 34.00 27.53

CARP1102-002 06/01/2023

Rates Fringes

MILLWRIGHT.......................$ 35.47 39.24

ELEC0058-001 07/21/2022

Rates Fringes

ELECTRICIAN (Low Voltage Wiring and Installation of Alarms) Installer...................$ 30.12 14.57 Technician..................$ 39.33 14.95

ELECTRICIAN......................$ 48.52 26.11

ELEV0036-002 01/01/2023

ELEVATOR MECHANIC................$ 59.82 37.335+a+b

FOOTNOTES:

A. PAID HOLIDAYS: New Years Day; Memorial Day; Independence Day; Labor Day; Veterans' Day; Thanksgiving Day; the Friday after Thanksgiving Day; and Christmas Day.

B. Employer contributes 8% basic hourly rate for 5 years or more of service of 6% basic hourly rate for 6 months to 5 years of service as vacation pay credit.

ENGI0324-017 06/01/2023

Rates Fringes

OPERATOR: Power Equipment

GROUP 1....................$ 47.49 25.35

GROUP 2....................$ 46.29 25.35

GROUP 3....................$ 44.79 25.35

GROUP 4....................$ 44.49 25.35

GROUP 5....................$ 43.67 25.35

GROUP 6....................$ 42.81 25.35

GROUP 7....................$ 41.84 25.35

GROUP 8....................$ 40.13 25.35

GROUP 9....................$ 31.79 25.35

FOOTNOTES:

Tower cranes: to be paid the crane operator rate determined by the combined length of the mast and the boom. If the worker must climb 50 ft. or more to the work station, $.25 per hour additional.

Derrick and cranes where the operator must climb 50 ft. or more to the work station, $.25 per hour additional to the applicable crane operator rate.

POWER EQUIPMENT OPERATOR CLASSIFICATIONS

GROUP 1: Crane with boom and jib or leads 400' or longer

GROUP 2: Crane with boom and jib or leads 300' or longer

GROUP 3: Crane with boom and jib or leads 220' or longer

GROUP 4: Crane with boom and jib or leads 140' or longer

GROUP 5: Crane with boom and jib or leads 120' or longer

GROUP 6: Regular crane operator, and concrete pump with boom operator

GROUP 7: Backhoe/Excavator/Trackhoe, bobcat/skid Loader, broom/sweeper, bulldozer, grader/blade, highlift, hoist, loader, roller, scraper, tractor & trencher

GROUP 8: Forklift & extend-a-boom forklift

GROUP 9: Oiler

IRON0025-019 06/01/2022

Rates Fringes

IRONWORKER

REINFORCING.................$ 31.43 34.77

STRUCTURAL..................$ 34.85 40.42

IRON0025-022 06/01/2022

Rates Fringes

IRONWORKER STRUCTURAL (Metal Building Erection Only)..........$ 25.81 26.43

LABO0259-002 08/01/2023

Rates Fringes

LABORER: Asbestos Abatement (Removal from Floors, Walls & Ceilings)........................$ 34.53 15.47

LABO0334-005 06/01/2023

Rates Fringes

LABORER: Landscape & Irrigation

GROUP 1.....................$ 25.97 8.60

GROUP 2.....................$ 23.75 8.60

CLASSIFICATIONS

GROUP 1: Landscape specialist, including air, gas and diesel equipment operator, lawn sprinkler installer, skidsteer (or equivalent)

GROUP 2: Landscape laborer: small power tool operator, material mover, truck driver and lawn sprinkler installer tender

LABO1191-002 06/01/2023

LABORER

Common or General; Grade Checker; Mason Tender - Brick/Cement/Concrete;

Pipelayer; Sandblaster......$ 32.95 16.95

PAIN0022-003 06/01/2022

Rates Fringes

PAINTER: Brush and Roller.......$ 32.85 20.41 PAINTER: Drywall Finishing/Taping.................$ 32.85 20.41 PAINTER: Spray..................$ 26.86 17.66

PAIN0357-002 06/01/2023

Rates Fringes

GLAZIER..........................$ 38.66 20.98

PAID HOLIDAYS: New Year's Day, Decoration Day, Fourth of July, Labor Day, Thanksgiving Day and Christmas Day;

provided that the employee has worked the last full regular scheduled work day prior to the holiday, and the first full regular scheduled work day following the holiday, provided the employee is physically able to work.

PLAS0067-001 04/01/2014

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 30.63 14.07

PLAS0067-004 04/01/2014

Rates Fringes

PLASTERER........................$ 30.63 14.07

PLUM0098-001 06/01/2023

Rates Fringes

PLUMBER, Excludes HVAC Pipe and Unit Installation............$ 35.79 28.28

PLUM0636-003 06/05/2023

PIPEFITTER, Includes HVAC

Pipe and Unit Installation.......$ 44.70 35.37

ROOF0149-001 07/01/2021

Rates Fringes

ROOFER...........................$ 38.16 25.91

SFMI0704-001 08/01/2023

Rates Fringes

SPRINKLER FITTER (Fire Sprinklers)......................$ 49.16 32.86

SHEE0080-004 06/01/2022

Rates Fringes

SHEET METAL WORKER (Including HVAC Duct Installation;

Excluding HVAC System Installation)....................$ 47.64 26.15

TEAM0247-002 06/01/2023

Rates Fringes

TRUCK DRIVER

GROUP 1

Dump; Flatbed; Pickup......$ 29.82 0.70+a+b

GROUP 2

Semi.......................$ 29.97 0.70+a+b

GROUP 3

Lowboy.....................$ 30.07 0.70+a+b

PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day. If any of the above holidays fall on a Sunday, the following Monday shall be considered the holiday and, if work is performed, the rate shall be double time.

FOOTNOTE:

a. $456.70 per week, plus $67.10 per day.

* SUMI2011-016 02/01/2011

Rates Fringes

INSTALLER - OVERHEAD DOOR........$ 27.98 0.00

IRONWORKER, ORNAMENTAL...........$ 18.48 7.93

TRUCK DRIVER: Tractor Haul

Truck............................$ 13.57 ** 1.18

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($17.20) or 13658 ($12.90). Please see the Note at the top of the wage determination for more information. Please also note that the minimum wage requirements of Executive Order 14026 are not currently being enforced as to any contract or subcontract to which the states of Texas, Louisiana, or Mississippi, including their agencies, are a party.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour National Office because National Office has responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION"

(End of Summary of Changes)