QUESTIONS AND ANSWERS RELATED TO:
W50S85-22-Q-0013 Electrical Lateral Utility Investigation - MV Feeder Raceways & Manholes as of 23 June 2022 @ 2:11pm
Dated: 7 June 2022
Q1. If you look at the drawing + 1+12+2022. I see 34 Red Boxes highlighted in yellow. What does that signify?
A1. There are 36 locations signified by numbered Red Boxes highlighted in yellow. Each test location is 3 conductors in accordance with the “Description of Service”. Example: (MV switch-to- MV Switch, MV switch to MV side of Transfromer) need to tested under this contract.
Q2. Also, just feeder #1 (shown in dark red). How many individual cable tests?
A2. Yes, feeder #1 shown in dark red,Total 36 MV cable test locations with 3 conductors each plus grounding test at each location.
Dated: 23 June 2022
Q3. I also see a sample report from the Detroit Arsenal. Is that how you want the cables tested at Selfridge?
A3. Test report not found, Submit test report IAW the Description of Service.
Dated: 8 June 2022
Q4. Please advise regarding the method / means for obtaining the specifications and drawings for this project. The response to RFI: question Q1 references drawing 1+12+2022.
A4. The drawings are an attachment in the SAM system, file name, “Drawings 1 Apr 12 2022 update”
Q5. Will you provide a SF1442 for this project?
A5. No, attachment “22Q0013_Combined Synopsis Solicitation” states “This announcement constitutes the only solicitation; quotes are being requested and a written solicitation will not be issued.”
Dated: 9 June 2022
Q6. Can this work be performed during normal business hours? Also, can we test all 34 locations simultaneously having several test sets. This would require Feeder 1 to be shutdown.
A6. Can this work be performed during normal business hours?
Response: No, this work can not be performed during normal business hours since the Base is completely operarional M-F during normal business hours and MV Feeder 1 feeds lots of mission critical loads so MV feeder 1 can not be shutdown during normal business hours.
Also, can we test all 36 locations simultaneously having several test sets. This would require Feeder 1 to be shutdown.
Response: There are 36 numbered locations for testing, Generally VLF testing can take 1 hour per cable. With several test sets a testing firm may accomplish much of the task per outage event. The base (customer) will need coordination for the shut down events and announcements will be made via public affairs. Please read all accociated documents, IE: drawing and PWS (Description of service).
Dated: 13 June 2022
Q7. Will the base allow the contractor to pump out the man holes the day before the scheduled shutdown.
A7. This contract does not expect to pump out manholes, if needed base will allow the contractor to pump out the man holes the day before the scheduled shutdown, The contractor shall follow all OSHA lock out and tag out procedures and disconnect the supply from the switch hose bldg. 854 and disconnect the MV feeders from MV transformers and Load Break switch and test all drops mentioned on the drawings.
Q8. Has the owner identified any manholes deemed to be unsafe to enter while the cables inside them are energized.
A8. The owner has not identified any manholes deemed to be unsafe to enter while the cables inside them are energized. The contractor shall not perform hot any work. The contractor shall coordinate with the Base personnel and follow OSHA safety lock out and tag out procedure and shut down the electric supply before performing any work.
Q9. Who (Contractor or base personnel) performs the switching operations during switching activities.
A9. Contractor shall coordinate with base personnel and perform the switching operations during switching activities. Feeder will be locked out for testing.
Q10. Are there current Arc Flash stickers on the equipment requiring operation during switching activities.
A10. No, Please see attachment. “Arc Flash Incident Energy and PPE class from Selfridge ANGB Electrical Study”
Q11. What is the Contractor’s responsibility should a cable fail during testing.
A11. The contractor shall inform base personal immediately if the cable fails during testing. The contractor shall take all precautions not to damage the cables.
Q12. Please identify which table (Acceptance or Maintenance) to be used to determine test voltages.
A12. Use Acceptance table.
Q13. The response to RFI question 3 references a “sample report from the Detroit Arsenal”. Please provide a copy of the sample report.
A13. A sample report was not provided, awarded contractor to provide report as directed in Description of Service
Q14. The response to RFI question 2 indicates that a “grounding test” is to be performed at each location. Please provide the testing standards to be used to perform this testing.
A14. Please use reference IEEE standard.
Q15. What is the Contractor’s responsibility should the owners equipment experience a failure during switching operation’s performed by the Contractor.
A15. If any equipment experiences a failure, the contractor shall notify the base immediately.
Q16. What is the deadline for Contractor’s questions.
A16. June 16, 2022
Q17. Drawing note 1 indicates that weekend work may be required for extended outages. Please define the criteria for an extended outage which will require week end work.
A17. All work is expected to be performed on weekends, Extended outage means outage more than 15min.
Q18. Will scaled site plan drawings be made available to the successful bidder.
A18. A site plan can be provided to awarded contractor
Q19. Specification 2.1.1 indicates that unscheduled gate closures by Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. What is the historic number of these events for the past five (5) years.
A19. 5 to 7 times per year
Q20. Specification 2.1.6 requires AT Level 1 Training. What is the cost for this training. Where is this training performed. What is the estimated duration in hours of this training.
A20. There is not cost it is a powerpoint presentation with a signature page.
Q21. The drawings do not indicate how many spare / empty conduits there are in each section of duct bank. How many spare / empty conduits per duct bank section should the Contractor base its cost proposal on.
A21. The contractor is not pulling and installing any cables under this contract.
Dated: 14 June 2022
Q22. Who (Contractor or base personnel) provides the equipment to access and open / drop pole mounted fuse pulls necessary to isolate sections of cable for testing.
A22. The contractor shall provide the equipment to access and open / drop pole mounted fuse cutouts necessary to isolate sections of cable for testing.
Dated: 17 June 2022
Q23. The quote requires the 52.212-3 Alt 1 provision to be sent along with it, however we do not see a way to fill this out on the website.
A23. The provision should be completed in your SAM account information on sam.gov. You will need to login to your SAM account to ensure this is up to date. If you are unsure contact the SAM helpdesk.
Dated: 22 June 2022
Q24. The project title includes manhole and raceway investigation but it is not addressed in Description of service, please advise if it is to be included in the bid.
A24. No, please disregard the title portion (“investigation of man holes and raceways”), this is not in the contract.
Q25. How are the cables to be tested at Selfridge?
A25. IAW: IEEE 400.2 Guide for (VLF low frequency) to include Tan/ Delta testing of shielded power cable systems.
Dated: 23 June 2022
Q26. Do we need to provide bid bond?
A26. No, this is a service contract.