STATEMENT OF WORK
KANSAS AIR NATIONAL GUARD, McCONNELL AFB PRQE202424 Repair Bldg 54 CRAC Units 16 January 2020
SW-1 LOCATION: McCONNELL Air Force Base, Wichita, KS. Arrangements for entrance onto the Base must be made by contacting Base Engineering at (316) 759-7477 between the hours of 7:00 a.m. and 4:00 p.m., Monday through Friday.
SW-2 SCOPE OF WORK: The work covered in this contract consists of furnishing all plant, labor, expertise, equipment, materials, facilities, transportation, and appliances necessary to perform operations in connection with the work described in paragraph SW-3. It is the intent of the government for the contractor to provide a complete and useable system. Any relevant details required for a complete system that are omitted in the contract plans and specifications will be provided by the Contractor at no cost to the government. Task Order Defalt Specifications apply to this project.
SW-3 SUMMARY OF WORK: Work shall consist of but is not limited to the following:
Task 1: Replace a portion of the existing copper line sets on three 30 Ton Liebert Air Conditioning Units.
Each Liebert Unit has two R-22 Freon circuits, due to operational requirements of the server farm, only one circuit of one Liebert Unit can be down at a time. Freon can be recycled if acid content is acceptable, otherwise virgin Freon is to be used. Each of the 6 line sets is comprised of one 1 inch line and one 1¼ inch line and the portion to be replaced ranges from 25 feet to 45 feet long (see drawing). Replacement lines will use ACR copper piping and will be insulated with Rubatex insulation. There will be a combination isolation/shraeder valve installed at the condenser end of the new portion of the line set as well as a isolation/shraeder valve installed on the lineset just outside the indoor unit (Evaporator) approximately 4 feet above the room floor. The result will be two isolation/shraeder valves on each line.
Linesets will exit the building through the Mechanical room cinder block wall at approximately 12 feet high. Lines will be supported to the condensing units keeping at least an 8 foot clearance above the ground until they reach the condensing units.
Note: The contractor will provide additional cooling to the server farm, if required, during the performance of this work. Air conditioning must be sufficient to keep the server farm continuously at 70 degrees +/- 2 degrees.
Task 2: Install seperate fuses for each of the individual fan motors in the Liebert Condensor Units. There are 3 condensor units and 4 fans in each unit. Only the three single speed, 3 phase, 480V, 1 Horsepower fans on each unit will require fuses, the one variable speed fan is not to be modified. Fuses will be installed inside the electrical compartment of the condensing units.
SW-4 CODES & STANDARDS: All work performed under this contract shall be in accordance with federal, state and local codes & standards, as well as widely accepted industry standards, including but not limited to: American Institute of Architects, American Concrete Institute, American Institute of Electrical Engineers, American Institute of Steel Construction, American National Standards Institute, American Society of Heating, Refrigerating and Air-Conditioning Engineers, American Society of Mechanical Engineers, American Society of Testing Materials, National Bureau of Standards, National Electric Code, American Welding Society, Brick Institute of America, Building Officials and Code Administrators, Federal Aviation Administration, National Fire Protection Association, National Electric Code, Occupational Safety & Health Administration, Rubber Manufacturers Association, Underwriters Laboratories, and the Kansas DOT. standard specification. Additionally, all requirements of the Kansas Department of Health must be satisfied in their entirety for any work performed or materials bought under this contract. Failure to comply with any of the aforementioned codes and standards shall be considered as a failure to comply to contract specifications.
SW-5 UTILITIES: Contractors shall coordinate with all local utilities having jurisdiction: Kansas Gas and Electric, Wichita Water Dept., Southwestern Bell, AT&T, Wichita Sewer Dept. and the Base Engineers Office.
SW-6 CALL BEFORE YOU DIG: All contractors shall be responsible for “Call Before You Dig” for any excavations or penetrations into the ground greater than 4” deep. In addition, all contractors shall apply for a digging permit to the Base Engineers Office for any excavations or penetrations into the ground, greater than 4” deep. The contractor should expect a minimum of 7 days from the date of the request to the issuance of a permit. The Contractor is encouraged to attend the Digging Permit Meeting.
These meetings are scheduled for every Tuesday at 10:00 A.M.
SW-7 CONFINED SPACE: The Contractor shall provide a confined space entry permit to the Base Engineers Office prior to any entry into a permit-required confined space. The following steps shall be accomplished to acquire authorization to open or enter a confined space:
1. The Contractor shall provide written notice to the Contracting Office Technical Representative, (COTR) defining exact location of space requiring entry.
2. A KANG Confined Space Supervisor shall brief the Contractor on the following:
a. The contents of the space and known hazards that make the space permit-required.
b. The precautions and procedures that have been implemented by the organization to protect KANG personnel.
c. Emergency rescue responsibilities to determine whether the Contractor supplies the rescue team or if the installation fire department is expected to supply a rescue function.
d. It is the Contractor’s responsibility to contact the Fire Chief on the installation if the
Contractor is planning to use the installation fire department as a rescue function.
e. Standard procedures if the project requires a combined effort involving both KANG and contracted personnel to access the space at the same time.
f. Contractor shall follow Air Force Occupational Safety and Health Standard 91-25 and
Occupational Safety and Health Administration 29 CFR 1910.146.
3. A written record of the briefing shall be signed by the Contractor and Confined Space
Supervisor and kept on file in the project folder.
4. The Contractor accepts full responsibility at this point to initiate and maintain the permit and supply all material, equipment and labor to test, monitor, enter and exit the space in a safe manner.
5. The Contractor’s Confined Space Entry Permit shall be kept on site during entry to the space.
A copy of the Contractor’s Permit shall be returned to the COTR at the completion of the project.
SW-8 MATERIALS: The materials shall conform to specifications, applicable industry codes and standards and the manufacturer's recommendations, which ever is more stringent. Certificates of compliance and Technical Data Sheets are required for all materials supplied.
SW-9 SITE INSPECTION: The Contractor is required to acknowledge, at time of Bid Opening that said contractor has inspected, and is fully cognizant of conditions at the site. No allowance or consideration will be given after award for any condition(s) which was(were) existing at the time of the site visit.
SW-10 BASE ACCESS: The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations. The contractor shall be provided an electronic Base
Access Form to be filed out and submitted electronically to the Project Manager. The security check process can take up to 5 days to be processed by the 22nd Security Forces. The Project Manager will notify the General Contractor once the requests have been processed. Approved individuals must provide picture identification and if driving they will need a valid driver’s license, auto registration and proof of insurance at the time they pick up their Badges at the Visitor Center located at the East Gate off Rock Road. After Contractors have their Badge they should enter the Base at the West Gate. Access is limited to locations noted on the Badge. All other areas are off limits. Vehicle Passes are not transferable to other vehicles. The Government reserves the right to deny access to any person, with no consequence to the contract.
SW-11 SAFETY: Compliance with OSHA and other applicable laws and regulations for the protection of employees is exclusively the obligation of the commercial contractor. Government employees must comply with AFOSH.
SW-12 CLEAN-UP: Clean-up and remove debris generated by this contract to an approved off-base location. Two (2) copies of the receiving (tipping or dumping) tickets, with a cover letter from the Prime Contractor stating the full name and address of the location to which debris was taken.
SW-13 GOVERNMENT RESOURCES: No Government resources shall be made available to the contractor, unless otherwise stated in this Statement of Work. The contractor shall provide for all necessary resources to provide a complete and usable facility or systems as described in the contract documents. The contractor shall not obligate Government resources in any manner. The Government shall seek remedy for any obligation or encumbrance imposed by the Contractors actions. Government resources include, but are not limited to, government owned materials, equipment, tools, vehicles, personnel and facilities.
SW-14 ATTACHMENTS
Building 54 Floor Plan with Construction Notes (1 Sheet)