This document is an amendment to Solicitation W50S7U-24-Q-0002 for the CES Seal Masonry Building 46 & 48 project at the 183d Wing Air National Guard Base in Springfield, Illinois. The purpose of the amendment is to incorporate the updated general wage determination, provide responses to requests for information (RFIs), and confirm that all other conditions remain unchanged. The solicitation is set-aside 100% for small businesses, and the government intends to award a firm-fixed-price contract to the responsible bidder whose quote is most advantageous, based solely on price. A mandatory pre-bid conference and site visit are scheduled for June 18, 2024, and all attendees must register in advance and provide security information. Quotes may be submitted by email, mail, or hand delivery, with the preferred method being email. The wage determination and applicable executive orders are provided, along with instructions for the wage determination appeal process.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DCFT 212002

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to incorporate the follow ing to Solicitation # W50S7U-24-Q-0002, CES Repair Masonry Building 46 & 48, Project # DCFT212002, 183WG, Springf ield, IL:

a. General Decision Number: IL20240004 w as updated on 21 June 2024.

b. Request For Information (RFI's) and responses provided.

c. All other conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 15

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 27-Jun-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W50S7U24Q0002

X 9B. DATED (SEE ITEM 11)

03-Jun-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

27-Jun-2024

CODE

USPFO IL 183 MISSION SUPPORT CONTRACTING

3101 J DAVID JONES PARKWAY

SPRINGFIELD IL 62707-5003

W50S7U 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W50S7U24Q0002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

The following have been modified:

BIDDING SCHEDULE/INSTRUCTIONS

SECTION 00100 INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

1. Description of the Project: The project, CES Seal Masonry Building 46 & 48 ,is to repair and seal various portions of masonry on Buildings 46 and 48 in Springfield, IL (Sangamon County).

2. Instructions to Bidders/Offerors:

2.1. You are invited to submit a quote in response to our Request for Quotes (RFQ) entitled W50S7U-24-Q-0002, CES Masonry Sealing , DCFT 212002 at the 183d Wing Air National Guard Base, Springfield, IL.

2.2. As a result of this solicitation, the Government intends to award a Firm Fixed Price (FFP) contract resulting from this solicitation to the responsible bidder whose quote, conforming to the request for quotes, will be most advantageous to the Government, considering only price.

2.3. This solicitation is set-aside 100% for small businesses.

3. RESERVED

4. NOTICE OF PRE-BID CONFERENCE AND SITE VISIT:

4.1. A pre-bid site visit for this solicitation will be conducted on 18 June 2024 at 1300 hours (1:00PM CDT) for the purposes of briefing on the bid requirements and answering questions regarding this solicitation. This conference will be held at 3101 J David Jones Parkway, Building P-48, Room 100, Springfield, Illinois 62707. Interested Contractors are highly encouraged to attend the pre-bid conference. The site visit will be held following the conference.

4.2.Due to security conditions, all offerors must register to attend this conference and site visit.

Email a completed SF 1705 – Consent for Background Check and a copy of a Government issued ID such as a Driver’s License, for all attendees, to 1st Lt Alicia C. Braun and CMSgt Brent Keller at the following addresses: Alicia.Braun@us.af.mil and Brent.Keller.1@us.af.mil.

4.3.This information must be provided in advance, 3 business days prior to the meeting, in order to ensure access to the military base and conference site and ensure adequate seating for the conference attendees. Even if you have access to the base you must register to ensure adequate seating. The furnishing of the above information is voluntary; however, your failure to furnish all or part of the requested information may result in the Government’s denial of your access to the pre-bid/quote conference. This information will be provided to the Base Security Forces who will authorize your entrance to the site.

4.4.Visitors must pick up their passes at the Installation’s Main Entry Gate prior to arrival.

You will be required to present the following information upon arrival: (1) Vehicle Registration,

(2) Valid Drivers License, (3) Proof of Insurance for Vehicle, (4) Safety Inspection and Car Rental agreement if applicable. Any of the above information furnished by you is protected under the Privacy Act and shall not be released unless permitted by law and/or you have consented to such.

4.5.Information provided at this conference or site visit shall not qualify the terms and conditions of the solicitation and specifications. Terms of the solicitation and specifications remain unchanged unless the solicitation is amended in writing. If an amendment is issued, normal procedures relating to the acknowledgment and receipt of solicitation amendments shall apply.

4.6.A record of the conference shall be made and furnished to all prospective bidders/offerors via posting at https://sam.gov. The record will include minutes of the meeting, including questions (on a non-attribution basis) and answers.

5. FORMAL COMMUNICATION, OFFEROR EXPLANATIONS:

5.1 Submit all questions in the format shown below by email to the contracting office at the addresses show below. Do NOT contact AE or Engineering personnel directly. Doing so will only delay your answer. All questions must come through the Contracting Office.

Subject Line: Reference No. SOLICITATION W50S7U-24-Q-0002 Email: Alicia.Braun@us.af.mil and Brent.Keller.1@us.af.mil *NOTE* - Submit Request for Information (RFI) below as a Word document attachment in email.

PRE-BID/QUOTE INQUIRY FORMAT

Date of Bid Inquiry: _______________ From: ______________________________ Company Name:

Address:______________________________________________________________________ Phone Number: _____________________________ Fax Number:______________________________ Email address:

Bid/Quote Inquiry: (Please clearly state your question)

5.2. Any explanation desired by an offeror regarding the meaning or interpretation of the solicitation, or proposals, drawings, specifications, etc. must be requested in writing and with sufficient time allowed for a reply to reach bidders before the submission of their bid.

5.3. All questions and requests for information (RFI) must be received NOT LATER THAN the fifth working day prior to quote closing. OFFERORS ARE STRONGLY

ENCOURAGED TO SUBMIT QUESTIONS EARLY IN THIS PROCESS.

5.4. Any changes to the drawings, specifications, etc. will be issued in the form of an amendment. However, any answers that clarify or provide an interpretation to the drawings, specifications, etc. will NOT be posted via amendment but rather as a response to the RFI on Contract Opportunities (formally FBO) at https://sam.gov.

5.5. Receipt by the offeror must be acknowledged in the space provided on the SF 1442 or by returning a signed copy of the amendment by the time set for receipt of bids.

5.6. For security reasons, all technical and engineering data related to this solicitation will be distributed using the Contract Opportunities (https://sam.gov) system. Plans and specifications are locked on FBO and may require Contractors to request explicit access from the Contracting Officer OR export controlled access through DLA. See complete instructions on Contract Opportunities (formally FBO). Contract Opportunities is a web-based dissemination tool designed to safeguard acquisition-related information for all Federal agencies. Interested bidders/offerors must register with Contract Opportunities before accessing the system.

5.6.1. Amendments, if/when issued will be posted to https://sam.gov for electronic downloading. This will normally be the only method of distributing amendments prior to closing; therefore, it is the offerors responsibility to check the website periodically for any amendments to the solicitation. Websites are occasionally inaccessible due to various reasons.

6. RFQ REPOSITORY:

6.1. A RFQ repository is provided for hand carried quotes and is located at 183d Wing, 3101 J David Jones Pkwy, Buildling P-48, Room 313, Springfield, IL 62707. Hand carried quotes must be deposited in the repository prior to the time established for the RFQ closing. Bidders/Offerors are cautioned that they will be required to sign-in and obtain a visitor’s pass to enter the facility and should allow time to accomplish this. See instructions for obtain access to the base in the Site Visit instruction. Follow the same instruction for obtaining entry to hand carry quote. Late receipt of quote due to entry delays may not be deemed excusable and the Contracting Officer may declare the bid/quote “late” in accordance with FAR 14.304.

6.2. The only acceptable deliveries of the RFQ will be: Hand Carried, Mail Delivery, or Electronic Mail (E-Mail). The preferred method of delivery is E-Mail.

7. WAGE DETERMINATION:

7.1. Construction Wage Rates are applicable to this project are WD IL20240004 as shown in Section 00800.

8. RFQ PREPARATION EXPENSES AND PRE-CONTRACT COSTS: This RFQ does not commit the Government to pay costs incurred in preparation and submission of quotes or for other costs incurred prior to award of a formal contract.

9. CLAUSES:

9.1. Clauses and provisions from the Federal Acquisition Regulation (FAR) and supplements thereto are incorporated in this document by reference and in full text. Those incorporated by reference have the same force and effect as if they were given in full text.

10. DISPOSITION OF UNSUCCESSFUL QUOTES:

In compliance with FAR Subpart 4.8, the Government will retain one copy of all unsuccessful quotes including the bid bond (if applicable).

11. OFFERORS QUALIFICATIONS:

To establish its responsibility, the apparent low bidder/offeror may be requested by the Government prior to award, to submit a statement regarding his previous experience in performing comparable work, his business and technical organization, financial and bonding resources and plant available to be used in performing the work. This action may be requested to determine if the contractor is responsible.

12. RESERVED

13. RESERVED

SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS

The following have been modified:

WAGE DETERMINATION

"General Decision Number: IL20240004 06/21/2024

Superseded General Decision Number: IL20230004

State: Illinois

Construction Types: Building and Residential

County: Sangamon County in Illinois.

BUILDING & RESIDENTIAL CONSTRUCTION PROJECTS (including single family homes and garden apartments up to and including 4 stories)

Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.

Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).

|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.20 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2024. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $12.90 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2024. |

The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.

Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/05/2024 1 02/23/2024 2 03/22/2024 3 05/03/2024 4 06/21/2024

ASBE0001-002 10/03/2022

Rates Fringes

ASBESTOS WORKER/HEAT & FROST

INSULATOR........................$ 43.73 26.29

BOIL0363-001 01/01/2024

Rates Fringes

BOILERMAKER......................$ 42.50 35.00

BRIL0008-021 05/01/2020

Rates Fringes

Bricklayer, Caulker, Cleaner, Pointer & Stonemason.............$ 33.49 24.93

BRIL0008-026 05/01/2017

Rates Fringes

Marble, Tile & Terrazzo Workers..........................$ 32.20 18.51

CARP0270-002 05/01/2017

Rates Fringes

CARPENTER (Building) Carpenter and Lather........$ 31.64 25.74 Piledriver..................$ 32.64 25.74 CARPENTER (Residential)..........$ 28.48 25.74

CARP1051-006 05/15/2020

Rates Fringes

MILLWRIGHT.......................$ 33.06 29.36

ELEC0193-005 07/01/2023

Rates Fringes

ELECTRICIAN

Building Construction (all buildings over 4 Stories)...$ 39.36 5%+18.95 Residential Construction (up to and including 4 stories)....................$ 23.61 3.5%+14.50

ELEV0055-002 01/01/2024

ELEVATOR MECHANIC................$ 55.57 37.885+a+b

FOOTNOTES:

A. Employer contributes 8% of regular basic hourly rate as vacation pay credit for employees with more than 5 years of service, and 6% for under 5 years of service.

B. Paid Holidays: New Year's Day; Memorial Day;

Independence Day; Labor Day; Thanksgiving Day; Day after Thanksgiving; Veterans' Day & Christmas Day

ENGI0965-003 05/01/2023

Rates Fringes

POWER EQUIPMENT OPERATOR

Group 1.....................$ 40.71 28.75 Group 2.....................$ 38.18 28.75 Group 3.....................$ 34.30 28.75 Group 4.....................$ 42.32 28.75

PREMIUM PAY-

CRANES WITH BOOMS - 120-200 ft. 1.00 per hour; $.02 Per Foot For Each Foot Above 200; MULTIPLE UNIT MACHINES- 1.00 per hour; UNDERGROUND WORK- 1.00 per hour; UNDER AIR PRESSURE-

1.00 per hour; LONG BOOMS ON STATIONARY TOWER CRANES-1.00 per hour. Above Long Boom Scale

Hazardous Waste/Asbestos Removal Workers receive the following wages and fringe benefits:

Level A (highest level of respiratory, skin, and eye protection) receives $2.00 per hour above journeyman.

Level B (same as Level A, but a lower level of skin protection) receives $1.50 per hour above journeyman.

Level C (same as Level B, but a lower level of respiratory protection) receives $1.00 per hour above journeyman.

OPERATING ENGINEER CLASSIFICATIONS:

GROUP 1: Asphalt Plant Engineer; Asphalt screed man; Apsco concrete spreader; Asphalt paver; Asphalt roller on bituminous contrete; Athey loaders; Cableways; Cherry Picker; ClamShell; C.M.I. & Similar Type Autograde Formless Paver,Autgrade Placer & Finisher; Concrete Breaker;Concrete plant Oper; Concrete Pumps; Cranes; Derricks;Derrick boats;

Draglines; Earth auger boring machine, Elevating Graders;

Engineers on dredge; Gravel processing machines;Head equipment greaser;High lift or fork lift;Hoist with two drums or 2 or more loadlines; Locomotive;Mechanics; Motor graders or auto patrols; Operators or levelman on dredges;

Power boat oper; Pug mill oper; (Asphalt plat); Orange peels; Overhead cranes; Paving mixer; Piledrivers; Pipe wraper & Painting machines; Push dozers, or Push cats; Rock crusher; Ross carrier or similar machine; Scoops; Skimmers 2 cu yd capacity & Under: Sheep foot roller (self propelled);Shovels; Skimmer; Scoops; Test hole drilling machines; Tower machine; Tower mixer; Track Tupe & Loaders;

Track type forklifts or high lifts; Track jacks & Tampers;

Trackors; Sideboom; Trenching machine; Ditching machine;

Tunnel lugger; Wheel type end loader; Winch cat; Scoops (Allor tournapull)

GROUP 2: Asphalt booster & Heater; Asphalt distributor;

Asphalt plant fireman;Building Elevator; Bull float or flexplane; Concrete finshing machine; Concrete saw, self propelled; Concrete spreader machine; Gravel or stone spreader, Power operated; Hoist automatic; Hoist with one drum & one load line; Oiler on 2 paving mixers when used in tandem boom or winch truck; Post hole diggers; Mechanical;

Road or street sweeper, Self-propelled; Scissors hoist;

Seaman tiller; Straw machine; Vibratory compactor; Well drill machine; & Mud jacks.

GROUP 3: Air compressor, Track or self-propelled; Bulk cement batching- plants; Conveyors; Concrete miers (Except Plant,Paver,Tower) Firement, Generators; Greasers; Light plants; Mechanical theater; Oilers; Power from graders;

Power sub-grader; Pug mill, When used other than asphalt operation; Rollers (Except bitumin ous); Tractors w/o Power attachments regardless of size or type; Truck crane oiler; & driver ( one man ); Vibratory hammer; Wat er pump; Welding machine ( one 300 amp or over) Combinations of five of any air compressors; Conveyors, Welding Machines, Water pumps; Light plants or Generators shall be in batteries or with in 300 FT.

Group 4: Lattice Boom crawler crane, Lattice Boom truck crane, Telescopic truck mounted crane, Tower crane

IRON0046-008 05/01/2023

Rates Fringes

IRONWORKER.......................$ 35.20 30.05

LABO0477-003 05/01/2024

LABORER

Asbestos Abatement Worker...$ 35.90 29.26 General Laborer.............$ 32.90 29.26

PAIN0090-004 09/01/2021

Rates Fringes

PAINTER

Building....................$ 32.23 20.58 Residential.................$ 29.73 20.58

Epoxy or Toxic-Lead-Based Paint Work-$1.00 Premimum

All work over 40 ft. above floor or ground level - $1.00 Premium

PAIN1168-002 05/01/2023

Rates Fringes

GLAZIER..........................$ 38.60 22.40

PLAS0018-033 05/01/2017

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 28.51 21.93

PLASTERER........................$ 28.50 19.12

PLUM0137-002 04/01/2023

Rates Fringes

Plumber, Pipefitter, Steamfitter Building....................$ 43.48 23.66 Residential.................$ 36.33 18.87

* ROOF0112-002 06/01/2024

Rates Fringes

ROOFER...........................$ 35.00 25.18

SHEE0218-002 06/01/2022

Residential

Rates Fringes

Sheet Metal Worker...............$ 26.73 26.48

SHEE0218-003 06/01/2023

BUILDING

SHEET METAL WORKER...............$ 38.54 30.37

TEAM0916-001 05/01/2022

Rates Fringes

TRUCK DRIVER

Group 1.....................$ 41.00 22.37 Group 2.....................$ 41.58 22.37 Group 3.....................$ 41.90 22.37 Group 4.....................$ 42.25 22.37 Group 5.....................$ 43.36 22.37

CLASSIFICATIONS:

GROUP 1: Drivers on 2 axles hauling less than 9 tons; air compressor & welding machines and brooms, including those pulled by separate units; Truck Driver Helper, warehouse employees; Mechanic Helpers; greasers and tiremen; pick-up trucks when hauling material, tools, or workers to and from and on the job site; and forklifts up to 6,000 lb capacity.

GROUP 2: 2 or 3 axles hualing more than 9 tons but hauling less than 16 tons; A-frame winch trucks; hydrolift trucks;

Vactor Trucks or similar equipment when used for transportation purposes; Forklift over 6,000 lb.capacity;

winch trucks; and four axle combiation units.

GROUP 3: 2, 3 or 4 Axles hauling 16 tons or more; 5-Axles or more combination units; drivers on water pulls; articulated dump trucks; mechanics and working forepersons.

GROUP 4: Low Boy and Oil Distributors.

GROUP 5: Drivers who require special protective clothing while employed on hazardous waste work.

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

State Adopted Rate Identifiers

Classifications listed under the ""SA"" identifier indicate that the prevailing wage rate set by a state (or local) government was adopted under 29 C.F.R �1.3(g)-(h). Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.

01/03/2024 reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour National Office because National Office has responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION"