B7 - Site Visit Slides - JKSE222409 RPR Sewermain Sliplining.pdf

PDF 646 KB Posted

Attached to
RPR Main Sewer Line - Montana Air National Guard
Solicitation number
W50S7L25QA003
Issued by

About this file

This document is a site visit presentation for a sewer main line repair project for the 120th Airlift Wing located in Great Falls, Montana. The solicitation (Solicitation Number: W50S7L-25-Q-A004) seeks a contractor to repair the clay sewer main line from buildings 62-79 using the Cure-in-Place-Pipe (CIPP) slip lining method, which offers minimally invasive repair and long-term durability. The project is a 100% small business set-aside with a project magnitude between $100,000 to $250,000 and a contract duration of 30 days.

Key details include quotes due on 16 September 2025 at 5:00 PM MDT, with electronic submissions required via email to specific contracting personnel. Payment and performance bonds are mandatory, and no late or facsimile submissions will be accepted. Contractors must submit proposals with quantities, unit prices, mobilization, and total costs, and provide all necessary supplies, equipment, labor, and management to complete the sewer main line repair. The solicitation will be posted on SAM.gov, and potential bidders are advised to check the website regularly for amendments and to carefully review all solicitation requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

**Welcome, Please Sign in as you enter**

Site Visit

08 September 2025 @ 10:00 AM

BCE Building 60, Great Falls, MT

Repair Sewer Main Line

120th Airlift Wing

W50S7L-25-Q-A004

Agenda Repair Sewermain B62-B79

• Introductions (Gov’t and Contractor)

• Synopsis

• Important Dates

• Solicitation

• Disclaimers/Questions

08 September 2025 2

Introduction / Purpose

Buildings 62 & 79 Repair and Replace Roofs

Intros:

CIV Kayla Rasmussen- Contracting Specialist

MSgt. Anthony Barille– Contracting Officer

Maj Aaron Jewett– Contracting Officer Representative

Purpose:

Familiarization with site

Not intended for re-design/technical questions or interpretations by technical personnel

08 September 2025 3

Contractor Introduction

Your Name

Company

Position in Company

Prime or Subcontractor

08 September 2025 4

Synopsis

This project will repair the clay sewer main line from building 62-79. The Cure-in-Place- Pipe (CIPP) slip lining method has been selected due to its minimally invasive nature and long-term durability, offering substantial cost savings compared to full replacement.

The Contractor proposal shall be submitted with quantities, unit prices, mobilization and costs included. The Contractor shall dispose of all excess packaging, materials, and other items at their cost. The contractor shall provide all supplies, parts, equipment, tools, labor, personnel, transportation, supervision, permits, insurance, and management necessary to repair the sewer main line on site. The project will be completed in accordance with the project contract documents, drawings, specifications, Federal and State law, and the terms and conditions of the contract.

08 September 2025 5

Synopsis Cont.

08 September 2025 6

Synopsis Cont.

CLINs 0001-0004 CLINs 0002-0004 Are Optional Depending on Funding Availability

Contract Duration: 30 Days ANP

100% Small Business Set-Aside

Magnitude of Project: $100,000 to $250,000

08 September 2025 7

Quote Due Dates

Quotes Due: 16 September 2025 @ 1700

(5:00 PM MDT)

Payment & Performance Bonds Required

No late submissions will be accepted

No Facsimile offers

Quotes must be signed by the person authorized

08 September 2025 8

Quote Due Dates Cont.

Complete quote package listing in Section 00 10 00 (Page 04 of Solicitation)

Electronic Quotes

Submit quotes via email to:

MSgt Anthoy Barille: anthony.barille@us.af.mil

CIV Kayla Rasmussen: kayla.a.Rasmussen.civ@army.mil

Complete quote submission instructions in Section 00 21 00 (Page 7 of Solicitation)

08 September 2025 9 mailto:anthony.barille@us.af.mil mailto:kayla.a.Rasmussen.civ@army.mil

Solicitation

On the Web – https://SAM.gov Check website regularly for Amendments Amendments must be acknowledged on quote

Questions / Answers will be posted on SAM.gov Must be received 5 days prior to quote due date

(09/11/2025)

Contractor’s responsibility to read entire Solicitation and all amendments

08 September 2025 10 https://sam.gov/

Solicitation Questions

Questions must be submitted in writing to Contract Specialist listed in the solicitation

ONLY questions/answers and information through an amendment are part of the solicitation/contract process

All questions, on a non-attribution basis, and the answers will be posted to the FBO website as an amendment

Check web site regularly for amendments to solicitation

Refer to Description on the SAM.gov posting for Q&A due date

Do not call technical personnel (BCE, Base Electrical Personnel)

Suspense Date for Questions (11 September 2025 @ 5:00PM MST) 08 September 2025

Disclaimer

Quoters are strongly cautioned to carefully read the requirements of the solicitation and comply accordingly

08 September 2025 12

Questions

The briefing slides, Site visit minutes, list of attendees and any question and answers that were provided during the meeting should be recorded and posted to the GPE (Contract Opportunities) with other solicitation documents.

This will ensure that all bidders/offerors are provided the same information.

Site Visit

08 September 2025 13

**Welcome, Please Sign in as you enter**
Agenda
Introduction / Purpose
Contractor Introduction
Synopsis
Synopsis Cont.
Synopsis Cont.
Quote Due Dates
Quote Due Dates Cont.
Solicitation
Solicitation Questions
Disclaimer
Questions

File details come from the government source that posted it. Updated .