FINAL_ABSTRACT - OF1419.pdf
PDF 205 KB Posted
- Attached to
- 124 FW East Ramp Crack Seal and Marking Project
- Solicitation number
- W50S7325BA003
- Issued by
-
Department of the Army National Guard
About this file
This is an Abstract of Offers - Construction document for the Gowen Field Airfield Lighting Project, Solicitation Number W50S7325BA002, issued by the 124th MSG/MSC. The solicitation was issued on 13 August 2025 and opened on 15 September 2025, with one amendment acknowledged. Five contractors submitted bids: Charter Contractor Solutions, C.R. Contracting, LLC, NNAC, Cascade Enterprises, Reagent World Construction, and Eastern Harbour Group. The project includes base bid and optional line items for airfield lighting work, such as Area A, Area B, and Area C improvements, arm/de-arm tasks, ramp signage updates, parking area painting, and highlight painting. Bid prices range from approximately $9,189 to $326,295 per job, with total estimated project amounts varying between contractors from $429,426.62 to $1,199,217.61. Two contractors (C.R. Contracting and NNAC) provided a 20% bid bond, while others did not include a bid security.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
X 7A.
ITEM
7C. EST.
QUANTITY
D.
UNIT
E. UNIT
PRICE
D. UNIT
PRICE
1 1 Job $120,474.20 $555,155.00
2 1 Job $114,450.49 $555,155.00
3 1 Job $66,260.80 $297,285.00
4 1 Job $28,380.00 $16,002.38
5 1 Job $14,190.00 $5,421.78
6 1 Job $11,825.00 $6,190.60
7 1 Job $63,855.00 $22,704.50
2. PROJECT TITLE
4. OFFERS (Continued)
AUTHORIZED FOR LOCAL REPRODUCTION NOTE: If more than two offers are received, continue on OF 1419A. OPTIONAL FORM 1419 (11-88) Prevoui s editionNisGuBsaM2023 C-43
ABSTRACT OF OFFERS - CONSTRUCTION
CONTINUATION SHEET
1. SOLICITATION NUMBER
W50S7325BA002
PAGE OF
2 2 PAGES
INSTRUCTIONS Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 13 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 13 and attach additional continuation Sheets (OF 1419A) as needed.
(Option 3) Paint highlights $63,855.00 $22,704.50 $18,337.00 $18,337.00
$419,435.49 $1,457,914.26 $1,153,041.00
(Option 1) Update ramp signage $14,190.00 $5,421.78 $10,104.00 $10,104.00 (Option 2) Paint alert parking $11,825.00 $6,190.60 $11,360.00 $11,360.00
(Option 2) AREA C $66,260.80 $297,285.00 $228,000.00 $228,000.00 BASE BID Arm/De-arm $28,380.00 $16,002.38 $21,240.00 $21,240.00
BASE BID AREA A $120,474.20 $555,155.00 $432,000.00 $432,000.00
(Option 1) AREA B $114,450.49 $555,155.00 $432,000.00 $432,000.00
6. NUMBER OF AMENDMENTS ISSUED C. REASONABLE CONTRACT
(Including Profit)
C. AMENDMENTS ACKNOWLEDGED
C. AMENDMENTS ACKNOWLEDGED
YES
7B. DESCRIPTION OF OFFERED ITEM F. ESTIMATED
AMOUNT
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
4. ISSUING OFFICE
124TH MSG/MSC
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
NAME AND TITLE OF CERTIFYING OFFICIAL (Type)
PATRICK T. BURRY, CONTRACTING OFFICER
SIGNATURE DATE SIGNED
5. PROJECT TITLE
Gowen Field Airfield Lighting Project
8. GOVERNMENT ESTIMATE
(Check A, B or C and complete D, E, and F)
9. OFFERS
NO. 1 NO. 2
A. OFFEROR
Charter Contractor Solutions
A. OFFEROR
C.R. CONTRACTING, LLCA. HIRED LABOR
B. REASONABLE CONTRACT
(Without Profit)
B. BID SECURITY (Type and amount)
NOT PRESENT
B. BID SECURITY (Type and amount)
BOND 20%
ABSTRACT OF OFFERS - CONSTRUCTION 1. SOLICITATION NUMBER
W50S7325BA002
2. DATE ISSUED
13 AUG 2025
3. DATE OPENED
15 SEP 2025
PAGE OF
1 2 PAGES
D. UNIT PRICE E. ESTIMATED
AMOUNT
1 JOB $326,295.00 $259,700.00
1 JOB $326,295.00 $253,700.00
1 JOB $177,537.00 $140,400.00
1 JOB $33,536.00 $15,700.00
1 JOB $10,938.00 $8,300.00
1 JOB $9,189.00 $6,500.00
1 JOB $67,426.00 $35,800.00
$720,100.00
Pre C-44
7 $67,426.00 $35,800.00 $74,813.00 $74,813.00 $39,070.87 $39,070.87
$951,216.00 $429,426.62 $1,199,217.61
5 $10,938.00 $8,300.00 $14,962.60 $14,962.60 $6,289.05 $6,289.05
6 $9,189.00 $6,500.00 $52,369.10 $52,369.10 $5,070.47 $5,070.47
3 $177,537.00 $140,400.00 $47,880.32 $47,880.32 $237,894.34 $237,894.34
4 $33,536.00 $15,700.00 $44,887.80 $44,887.80 $11,461.92 $11,461.92
1 $326,295.00 $259,700.00 $104,738.20 $104,738.20 $449,715.48 $449,715.48
2 $326,295.00 $253,700.00 $89,775.60 $89,775.60 $449,715.48 $449,715.48
3. CONTRACT ITEMS C. AMENDMENTS ACKNOWLEDGED
YES
C. AMENDMENTS ACKNOWLEDGED
YES
C. AMENDMENTS ACKNOWLEDGED
YES
C. AMENDMENTS ACKNOWLEDGED
1 OF 2A. ITEM
NO.
B. ESTIMATED
QUANTITY
C. UNIT
E. ESTIMATED
AMOUNT
D. UNIT PRICE D. UNIT PRICE E. ESTIMATED AMOUNT D. UNIT
PRICE
E. ESTIMATED
AMOUNT
Gowen Field Airfield Lighting Project NO.: NO.: NO.: NO.:
A. OFFEROR
NNAC
A. OFFEROR
Cascade Enterprises
A. OFFEROR
Reagent World Construction
A. OFFEROR
Eastern Harbour Group .
B. BID SECURITY (Type and amount)
BOND 20%
B. BID SECURITY (Type and amount)
BOND 20%
B. BID SECURITY (Type and amount)
NOT PRESENT
B. BID SECURITY (Type and amount)
NOT PRESENT
Table 1
| 2025-09-16T12:06:54-0600 | |
| BURRY.PATRICK.THOMAS.1152620019 |
File details come from the government source that posted it. Updated .