BXRH252003 ERCS SOW R1 V1 16 JUL 2025.pdf

PDF 513 KB Posted

Attached to
124 FW East Ramp Crack Seal and Marking Project
Solicitation number
W50S7325BA003
Issued by

About this file

This Statement of Work (SOW) details a crack seal project for the East Ramp at the Idaho Air National Guard's Gowen Field in Boise, Idaho. The project involves removing existing sealant, cleaning, and resealing approximately 91,000 linear feet of construction joints and significant cracks across three designated areas (A, B, and C) of an 820,000 square foot concrete ramp surface. The work is intended to prevent moisture damage, vegetation growth, and potential Foreign Object Damage (FOD) to aircraft.

The contract (BXRH 252003) is structured with three Contract Line-Item Numbers (CLINs): CLIN 1 covers Area A (36,000 linear feet), CLIN 2 covers Area B (36,000 linear feet), and CLIN 3 covers Area C (19,000 linear feet). The project will use jet fuel-resistant silicone sealant conforming to ASTM D5893/D5893M standards, with work to be performed in compliance with various federal specifications and Unified Facilities Criteria. The contractor must adhere to strict environmental, safety, and base access requirements, including obtaining necessary permits, completing anti-terrorism force protection training, and maintaining a clean work site.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

East Ramp Crack Seal

For Idaho Air National Guard

BXRH 252003

BXRH 252003

East Ramp Crack Seal

TABLE OF CONTENTS

TAB A: Project Description

1. Project Number and Title 3

2. Scope 3

3. Facility Function/Construction 3

4. Plans 3

5. Location 3

6. Hours of Operation 4

7. Utilities 4

8. Contract Line-Item Number 4

9. Occupancy and Phasing 4

10. Scheduling and Notice to Proceed 5

11. Period of Performance 5

12. Project Requirements 5

13. Construction 7

TAB B: General Requirements

1 Base Access 16

2. Performance 17

3. Meetings 17

4. Environmental 18

5. Site Conditions 22

6. Traffic Control 22

7. Supervision 23

8. Site Safety 24

9. Anti-Terrorism Force Protection 24

10. Clean Up 25

TAB A

PROJECT DESCRIPTION

1. PROJECT NUMBER AND TITLE:

1.1. BXRH 252003 East Ramp Crack Seal

2. FACILITY FUNCTION/CONSTRUCTION:

2.1. The East Ramp is an approximately 820,000 SF concrete surfaced, secured parking area for military aircraft. The ramp is comprised of multiple cast-in-place concrete blocks which require joint and crack sealant to prevent moisture damage. The sealant is deteriorated or failed in many areas and needs to be removed and replaced to prevent deterioration and Foreign Object Damage (FOD) to aircraft.

3. SCOPE: MINOR CONSTRUCTION.

3.1. The purpose of this project is to maintain and preserve the concrete ramp surface by removing existing sealant, cleaning and resealing all construction joints and significant cracks to prevent moisture related damage and vegetation growth.

3.2. Due to the size of the East Ramp and operational requirements, the work has been divided into three (3) areas A, B, & C. Work is expected to proceed from East to West to accommodate operational requirements.

3.3. This is a companion project to BXRH 252007 East Ramp Airfield Markings. It is anticipated that both projects will be done simultaneously.

4. PLANS:

4.1. Refer to attached drawings and/or plan sheets. Additional Facility locations, Floor plans, as-built drawings, reports from previous surveys, or other relevant information shall be provided by Base Civil Engineer (BCE) representative if needed.

5. LOCATION:

5.1. Project is located at Gowen Field, on Boise Air Terminal, Boise Idaho (see map).

5.2. Gowen Field is a controlled access National Guard military installation.

• Refer to Tab B, Section 1 BASE ACCESS for more information.

6. HOURS OF OPERATION:

6.1. Normal business hours on Gowen Field are 0630-1730, Monday through Friday, and one weekend per month for Unit Training Assembly (UTA), excluding holidays.

7. UTILITIES:

7.1. Utility maps will be provided by BCE representative upon request.

7.2. Contractor is responsible for identifying and locating all underground utilities before and during all excavation activities.

• Idaho Power furnishes overhead electrical service to the base at 13.8 kV.

• Intermountain Gas furnishes existing natural gas service.

• Veolia (formerly Suez) Water furnishes existing water service.

• City of Boise furnishes existing sanitary sewer service.

• Communications manhole/duct system is owned by the Government and provided by the 124th Communications Squadron.

8. CONTRACT LINE-ITEM NUMBER (CLIN) STRUCTURE:

8.1. Cost proposals shall be broken out into the following CLIN Structure. CLINs may be executed individually or in combination dependent on funding.

• CLIN 1 (BASE BID): Remove existing sealant, clean and reseal all construction joints and significant cracks. Restore airfield markings where sealant work damages or removes paint. Area A, (approx. 36,000 LF).

• CLIN 2 (OPTION 1): Same work as above, only in area B (approx. 36,000 LF).

• CLIN 3 (OPTION 2): Same work as above, only in area C (approx. 19,000 LF).

9. OCCUPANCY & PHASING:

9.1. All buildings and surrounding areas will remain occupied throughout construction. A phasing plan of work shall be submitted prior to construction starting, with consideration for minimal downtime during work in these areas.

9.2. When necessary, the Contractor will provide work site protection and traffic control measures sufficient to prevent vehicles and/or pedestrian traffic from inadvertently entering the construction area.

10. SCHEDULING AND NOTICE TO PROCEED:

10.1. A proposed construction schedule on an AF Form 3064 will be submitted to the

Contracting Officer (KO) 7 working days prior to the Pre-construction meeting. The

Contracting Officer (KO), the Base Civil Engineer (BCE) and/or BCE representative will review the schedule and approve or request changes during the Pre-construction meeting.

10.2. Construction schedules shall outline critical paths, project milestones, submittal deadlines, and all scheduled meetings.

10.3. If project is delayed the Contractor shall submit an updated AF 3064 for approval.

10.4. Schedule will be required and approved via submittal before notice to proceed (NTP) is given.

10.5. This project requires Airfield Driving training for all Contractor and subcontractor personnel operating motorized vehicles and equipment before Notice to Proceed

(NTP) is given.

• Contact Airfield Management (AFM) at 208-422-5229 to schedule training.

• Contractor is responsible for ensuring personnel have met all training requirements before working on Gowen Field.

11. PERIOD OF PERFORMANCE:

11.1. The period of performance for this work will be negotiated between Contracting

Officer (KO), BCE representative, and Contractor based on facility requirements and

CLIN option execution.

12. PROJECT REQUIREMENTS:

12.1. Contractor:

• Contractor shall investigate the site for existing site conditions, existing utilities and easements, and demolition requirements. Utilities must be maintained for buildings in the vicinity.

• Refer to the following specifications and reference documents for all technical details.

In conflict between this SOW and the below reference documents and specifications, the Contractor shall submit an RFI for guidance.

• Manufacturer's instructions for handling, applying, and installing products are considered a part of these specifications. In the event of conflict between the requirements of this SOW and the manufacturer's recommendations, the Contractor shall submit an RFI for guidance.

12.2. Material Specifications:

• Sealant, Jet Fuel Resistant (JFR), conforming to ASTM D5893/D5893M, Standard

Specification for Cold Applied, Single-Component, Chemically Curing Silicone Joint

Sealant for Portland Cement Concrete Pavements.

D.S. Brown 800/900 Series or approved equal

• Backing Material shall conform to ASTM D5249, Standard Specification for Backer

Material for Use with Cold- and Hot-Applied Joint Sealants in Portland Cement

Concrete and Asphalt Joints.

• Paint shall conform to Fed Specification TT-P-1952F, Paint, Traffic and Airfield

Marking, Waterborne, Type I or II

• Glass Beads, meeting AASHTO M 247-81, Glass Beads used in Traffic Paint, Type I

12.3. Reference Documents:

• References shall include but not be limited to the following specifications, manuals, and Unified Facilities Criteria (UFC)’s. All UFC may be found at https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc

• UFC 1-200-01 DoD Building Code (General Building Requirements), w/ Change 1.

• UFC 3-250-04 Standard Practice for Concrete Pavement Construction.

• UFC 3-250-08FA Standard Practice for Sealing Joints and Cracks in Rigid and

Flexible Pavements.

• UFC 3-270-01 O&M Manual, Asphalt and Concrete Pavement Maintenance and

Repair w/ Change 1.

• ASTM C1193 Standard Guide for Ude of Joint Sealants

12.4. Submittals:

• All submittals will be processed with an AF Form 3000 as the coversheet and routed through the Contracting Office (KO) for approval.

• Materials must be approved by the Contacting Office (KO) and the Base Civil

Engineer (BCE) prior to installation.

• Prior to the start of work on Base, a schedule using AF 3064 or similar document shall be submitted and approved, through the Contracting Office (KO) and the Base Civil

Engineer (BCE). Any changes to the schedule must be submitted for acceptance.

• Prior to installation or use, the Contractor shall submit to the Contracting Office (KO) and the Base Civil Engineer (BCE) for approval of the manufacturer's product information, specifications and instructions for the materials intended for use on the job.

• An AF Form 66, material submittal schedule, shall be submitted within 10 calendar days of the NTP indicating when each material item shall be submitted for approval.

• Government shall not be held responsible if disapproved materials delay the project.

• Allow for a minimum of 5 calendar days for the Government’s processing of material submittals.

https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc

• The Contractor shall not order, deliver, or install any materials without Contracting

Office (KO) and BCE material approval, or remove any materials on site which have not been properly approved.

• The Contractor will provide a warranty packet with all facilities and materials listed.

• If a crane is needed for this project a FAA form 7460-1 will need to be submitted, approved, and a copy turned into 124 CE prior to receiving a notification to proceed.

The FAA form 7460-1 can be filled out and found at https://oeaaa.faa.gov/oeaaa/external/portal.jsp.

13. CONSTRUCTION REQUIREMENTS:

13.1. Submittals:

Submit the following in accordance with Section 12.4

• Product Data:

Submit catalog cuts, specifications, Safety Data Sheets and other information documenting conformance to Contract requirements.

• Certificates:

Equipment List.

Manufacturer’s Certification and Test reports showing conformance to Contract requirements.

• Manufacturer's Instructions:

Provide instructions that include, but not limited to: storage requirements, ambient temperature and humidity ranges, and moisture condition of joints for successful installation; requirements for preparation of joints; safe heating temperature; mixing instructions; installation equipment and procedures; application and disposal requirements; compatibility of sealant with filler material; curing requirements; and restrictions to be adhered to in order to reduce hazards to personnel or to the environment. Submit instructions at least 30 days prior to use.

13.2. Test Requirements:

Test the sealant and backup or separating material for conformance with the referenced material specification. Perform testing of the materials in an approved independent laboratory and submit certified copies of the test reports for approval 10 days prior to the use of the materials at the job site. Submit samples to be retained by the Government for possible future testing if the materials appear defective during or after application. Conformance with the requirements of the laboratory tests specified does not constitute final acceptance of the materials. Base final acceptance on the performance of the in-place materials. Submit samples of the materials (sealant, primer if required, and backup material), in sufficient quantity for testing and https://oeaaa.faa.gov/oeaaa/external/portal.jsp approval 10 days prior to the beginning of work. Do not use material until it has been approved.

13.3. Trial Joint Sealant Installation:

Prior to cleaning and sealing the joints for the entire project, prepare a test section at least 200 ft long using the specified materials and approved equipment, so as to demonstrate the proposed joint preparation and sealing of the types of joints in the project. Following the completion of the test section and before any other joint is sealed, inspect the test section to determine that the materials and installation meet the requirements specified. Inspect joint seal test section. Correct deficiencies and obtain approval of test section prior to installing joint seals. If it is determined that the materials or installation do not meet the requirements, remove the materials, and reclean and reseal the joints at no cost to the Government. Permit the test section meeting the requirements to be incorporated into the permanent work and paid for at the Contract unit price per linear foot for sealing items scheduled. Prepare and seal other joints in the manner approved for sealing the test section. Notify the Contracting

Office and BCE representative upon completion of the test section.

13.4. Delivery, Storage and Handling:

Inspect materials delivered to the site for visible damage, and unload and store with a minimum of handling. Deliver joint materials in original sealed containers and protect from freezing or overheating. Provide jobsite storage facilities capable of maintaining temperature ranges within manufacturer’s recommendations.

13.5. Environmental Requirements:

Do not proceed with work when weather conditions detrimentally affect the quality of cleaning joints or applying sealants. Proceed with joint preparation and sealing only when weather conditions are in accordance with the manufacturer’s instructions.

Install joint sealant to dry surfaces and protect sealant and bond breakers from moisture.

13.6. Traffic Control:

Do not permit vehicular or heavy equipment traffic on the pavement in the area of the joints being sealed during the protection and curing period of the sealant. Permit traffic on the pavement at the end of the curing period.

13.7. Materials:

• Sealant

Use materials for sealing cracks and joints in accordance with ASTM

D5893/D5893M

• Blocking Media/Backup Materials

Provide backup (joint filler) material that is a compressible, nonshrinking, nonstaining, nonabsorbing, nonreactive material with the sealant. Use backup material compliant with ASTM D5249. Use material with a melting point at least 5 degrees F greater than the pouring temperature of the sealant being used when tested in accordance with ASTM D789. Use material with a water absorption of not more than 5 percent of the sample weight when tested in accordance with ASTM C1016.

Use backup (joint filler) material that is 25 plus or minus 5 percent larger in diameter than the nominal width of the crack. Use blocking media consistent with the sealant manufacturer's installation instructions.

13.8. Equipment:

Submit equipment list and description of the equipment to be used and a statement from the supplier of the sealant that the proposed equipment is acceptable for installing the specified sealant. Use equipment for heating, mixing, and installing seals in accordance with the instructions provided by the sealant manufacturer.

Provide equipment, tools, and accessories necessary to clean existing joints and install liquid joint sealants. Maintain machines, tools, and other equipment in proper working condition. Submit a list of proposed equipment to be used in performance of construction work including descriptive data, 10 days prior to use on the project.

• Tractor Mounted Routing and Plowing Tool:

Use routing tools for removing old sealant from the joints, of such shape and dimensions and so mounted on the tractor that do not damage the sides of the joints.

Use tools designed to be adjusted to remove the old material to varying depths and widths as required. Use equipment capable of maintaining accurate cutting depth and width control. Use a joint plow equipped with a spring or hydraulic mechanism to release pressure on the tool prior to spalling the concrete. Do not permit the use of V-shaped tools or rotary impact routing devices. Permit the use of hand-operated spindle routing devices to clean and enlarge random cracks.

• Concrete Saw:

Provide a self-propelled power saw, with water-cooled diamond or abrasive saw blades, for cutting joints to the depths and widths specified, for refacing joints, cleaning sawed joints where sandblasting does not provide a clean joint, widening, or deepening existing joints as specified without damaging the sides, bottom, or top edge of joints. Permit single or gang type blades with one or more blades mounted in tandem for fast cutting. Select saw adequately powered and sized to cut specified opening with not more than two passes of the saw through the joint.

• Sandblasting Equipment:

Include with the sandblasting equipment an air compressor, hose, and long-wearing venturi-type nozzle of proper size, shape and opening. Do not permit the maximum nozzle opening to exceed 1/4 in. Use a portable air compressor capable of providing not less than 150 cfm and maintaining a line pressure of not less than 90 psi at the nozzle while in use. Demonstrate compressor capability, under job conditions, before approval. Use a compressor equipped with traps that maintain the compressed air free of oil and water. Use a nozzle with an adjustable guide that holds the nozzle aligned with the joint approximately 1 in above the pavement surface. Adjust the height, angle of inclination and the size of the nozzle to secure satisfactory results.

• Waterblasting Equipment:

Include with the waterblasting equipment a trailer-mounted water tank, pumps, high-pressure hose, wand with safety release cutoff control, nozzle, and auxiliary water resupply equipment. Provide water tank and auxiliary resupply equipment of sufficient capacity to permit continuous operations. Use a nozzle with an adjustable guide that holds the nozzle aligned with the joint approximately 1 in above the pavement surface. Adjust the height, angle of inclination and the size of the nozzle to obtain satisfactory results. Use a pressure gauge mounted at the pump that shows the pressure in kPa psi at which the equipment is operating.

• Air Compressor:

Use a portable air compressor capable of operating the sandblasting equipment and capable of blowing out sand, water, dust adhering to sidewalls of concrete, and other objectionable materials from the joints. Use a compressor that provides air at a pressure not less than 90 psi and a minimum rate of 150 cubic ft of air per minute at the nozzles and free of oil.

• Vacuum Sweeper:

Use a self-propelled, vacuum pickup sweeper capable of completely removing loose sand, water, joint material, and debris from pavement surface.

• Hand Tools:

Permit the use of hand tools, such as brooms and chisels, when approved, for removing defective sealant from a crack and repairing or cleaning the crack faces.

• Cold-Applied, Single-Component Sealing Equipment:

Use equipment for installing ASTM D5893/D5893M single component joint sealants that consists of an extrusion pump, air compressor, following plate, hoses, and nozzle for transferring the sealant from the storage container into the joint opening. Use a nozzle with dimensions that allows the tip of the nozzle to extend into the joint to allow sealing from the bottom of the joint to the top. Maintain the initially approved equipment in good working condition, serviced in accordance with the supplier’s instructions, and unaltered in any way without obtaining prior approval. Use lined hoses and seals to prevent moisture penetration and withstand pumping pressures.

Use equipment free of contamination from previously used or other type sealant.

Permit use of small hand-held air-powered equipment (i.e., caulking guns) for small applications.

13.9. Preparation of Joints:

• Unless otherwise indicated, remove existing material, saw, clean and reseal joints. Do not proceed with final cleaning operations by more than one working day in advance of sealant.

• Clean joints by removing existing joint sealing compound, bond-breakers, dirt, laitance, curing compound, filler, and protrusions of hardened concrete from the sides and upper edges of the joint space to be sealed, and other foreign material with the equipment.

• Do not permit cleaning procedures that damage joints or previously repaired patches by chipping or spalling.

• Remove existing sealant to the required depth.

• Precise shape and size of existing joints vary, and conditions of joint walls and edges vary and include but are not limited to rounding, square edges, sloping, chips, voids, depressions, and projections.

13.10. Existing Sealant Removal:

• Cut loose the in-place sealant from both joint faces and to the required depth.

• Provide a depth sufficient to accommodate blocking media required to maintain the depth of new sealant to be installed.

• Prior to further cleaning operations, remove loose old sealant remaining in the joint opening by blowing with compressed air.

• Permit use of hand tools to remove sealant from random cracks.

• Do not permit chipping, spalling, or other damage to the concrete.

• Clean pavement surface with vacuum sweeper.

• Protect previously cleaned joints from being contaminated by subsequent cleaning operations.

13.11. Refacing of Joints:

• Accomplish refacing of joints using a concrete saw as specified in paragraph

EQUIPMENT to remove residual old sealant and a minimum of concrete from the joint face to provide exposure of newly cleaned concrete, and, if required, to enlarge the joint opening to the width and depth shown on the drawings

• Provide exposure of newly clean concrete through removal. Remove burrs and irregularities from sides of joint faces. Stiffen the blade with a sufficient number of dummy (used) blades or washers.

• Clean, immediately following the sawing operation, the joint opening using a water jet to remove saw cuttings and debris and adjacent concrete surface.

• Protect adjacent previously cleaned joint spaces from receiving water and debris during the cleaning operation.

• Joint Widening: Saw joints having grooves less than 3/8 in wide and less than 1 in deep to a minimum width of 3/8 in and to the minimum depth of 1 in.

13.12. Refacing of Random Cracks:

• Use a vertical spindle routing device to clean random cracks. Sandblast clean random cracks that are less than approximately 1 inch wide to prevent additional widening of the crack instead of sawing or routing.

13.13. Final Cleaning of Joints:

• Following removal of existing sealant, and sawing, and immediately before resealing, clean newly exposed concrete joint faces and pavement surface extending to a minimum of 1/2 inch up to 2 inches from each joint edge by sandblasting until concrete surfaces in the joint space are free of sealants, dust, dirt, water and other foreign materials that prevent bonding of new sealants to the concrete.

• Use sand particles of the proper size and quality for the work. Perform sandblasting with specified nozzles, air compressor, and other appurtenant equipment. Position nozzles to clean the joint faces.

• Make at least two passes; one for each joint face. Make as many passes as required for proper cleaning.

• Immediately prior to sealing the joint, blow out the joint spaces with compressed air until completely free of sand, water, and dust.

• Install joint sealants to dry joints.

• Replace expansion joint filler material damaged in performing the work with new materials of the same type and dimensions as the existing material, or with appropriate blocking media.

13.14. Blocking Media:

• When the joint opening is of a greater depth than indicated for the sealant depth, plug or seal off the lower portion of the joint opening using a blocking media/back-up material to prevent the entrance of the sealant below the specified depth.

• Take care to ensure that the blocking media/backup material is placed at the specified depth and is not stretched or twisted during installation.

13.15. Rate of Progress of Joint Preparation:

Limit the stages of joint preparation, including sandblasting, air pressure cleaning and placing of the back-up material to only that lineal footage that can be sealed during the same day.

13.16. Preparation of Sealant:

Inspect the ASTM D5893/D5893M sealant and containers prior to use. Reject materials that contain water, hard caking of any separated constituents, nonreversible jell, or materials that are otherwise unsatisfactory. Do not reject sealants that exhibit settlement of constituents in a soft mass that can be readily and uniformly remixed in the field with simple tools.

13.17. Installation of Sealant:

• After approval of the test section, seal joints immediately following final cleaning and placing of bond breakers.

• Commence sealing joints when walls are dust free and dry, and when weather conditions meet sealant manufacturer’s instructions. If the above conditions cannot be met, or when rain interrupts sealing operations, reclean and permit the joints to dry prior to installing the sealant.

• Do not install joint sealant until joints to be sealed have been inspected and approved.

Install bond breaker just prior to pouring sealant. Fill the joints with sealant from bottom up until joints are uniformly filled solid from bottom to top using the specified equipment for the type of sealant required. Fill joints to 1/8 inch plus or minus 1/16 inch below top of pavement, and without formation of voids or entrapped air.

• Do not permit gravity methods or pouring pots to be used to install the sealant material.

• Except as otherwise permitted, tool the sealant immediately after application to provide firm contact with the joint walls and to form the indicated sealant profile below the pavement surface.

• Remove excess sealant that has been inadvertently spilled on the pavement surface.

• Do not permit traffic over newly sealed pavement until authorized.

• When a primer is recommended by the manufacturer, apply it evenly to the joint faces in accordance with the manufacturer's recommendations.

• Check sealed joints frequently to ensure that newly installed sealant is cured to a tack-free condition within the specified time.

• Protect new sealant from rain during curing period.

13.18. Inspection/Field Quality Control:

• Joint Cleaning

Inspect joints during the cleaning process to correct improper equipment and cleaning techniques that damage the concrete pavement in any manner. Approve cleaned joints prior to installation of the separating or back-up material and joint sealant.

• Sampling Sealant

Obtain a one-gallon sample of each type of sealant on the project from material used for each 10,000 linear ft or less of joints sealed. Store samples according to sealant manufacturer's instructions. Retain samples until final acceptance of the work.

• Sealant Application Equipment

Inspect the application equipment to ensure conformance to temperature requirements, proper proportioning and mixing (if two-component sealant), and proper installation. Suspend operations if there is evidence of bubbling, improper installation, or failure to cure or set until causes of the deficiencies are determined and corrected.

• Joint Sealant

Inspect the joint sealant for proper rate of cure and set, bonding to the joint walls, cohesive separation within the sealant, reversion to liquid, entrapped air and voids.

Remove sealants exhibiting these deficiencies prior to the final acceptance of the project from the joint, wasted, and replace at no additional cost to the Government.

Obtain approval for each joint seal installation.

13.19. Acceptance:

Reject sealer that fails to cure properly, or fails to bond to joint walls, or reverts to the uncured state, or fails in cohesion, or shows excessive air voids, blisters, surface defects, swelling, or other deficiencies, or is not properly recessed within indicated tolerances. Remove rejected sealer and reclean and reseal joints. Perform removal and reseal work promptly by and at the expense of the Contractor.

13.20. Disposal of Debris:

• Sweep pavement surface to remove excess joint material, dirt, water, sand, and other debris by vacuum sweepers or hand brooms.

• Remove the debris to an approved disposal facility.

• Contractors are responsible for demolished materials and their proper disposal.

• The weight for all material waste generated from this project must be recorded.

• Refer to Tab B Section 4 ENVIRONMENTAL for additional information.

13.21. Existing Conditions:

• If during any phase of work the existing or surrounding finishes are disturbed/damaged, the contractor will be responsible for replacing/repairing and reinstalling affected material as part of the project with no additional cost to the government.

13.22. Clean-up:

• Contractor will be responsible for ensuring the work site is cleaned and organized in an orderly fashion at the end of each workday and before final acceptance.

13.23. Closeout:

• Provide O&M manuals, warranty information/documentation, and owners training if applicable, to BCE at final acceptance.

13.24. Warranty Period:

• The contractor’s warranty periods shall begin with date of Final Acceptance, Substantial Completion Date.

• Subcontractor installation date shall not constitute the beginning of the warranty period.

TAB B

GENERAL REQUIREMENTS

1. BASE ACCESS:

1.1. Base access procedures can be found on the Idaho Military Division Visitors Control

Center webpage at the below URL: https://www.imd.idaho.gov/visitor-control-center/

1.2. The contractor shall comply with all applicable installation/facility access and local security policies and procedures. The Contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces. The Contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in Contractor security matters or processes.

1.3. Beginning May 7, 2025, all personnel wishing to access a federal building or military installation (Gowen Field) will need a Star card, US Passport, Military ID, or some other form of federally accepted identification. Forms of identification accepted in lieu of a license or ID card with the Star can be found at https://www.tsa.gov/travel/security-screening/identification

1.4. Contractor must have prior approval for personnel to work in any restricted areas, aircraft taxiway or aircraft parking ramps. A letter to the Contracting Office and BCE with employee's name, SSN, and what dates they will be working in any restricted areas.

• This letter will be made available to the Contracting Office and BCE no-less-than 7 working days prior to the start of work to allow for coordination with Base Security-

Forces.

1.5. All workers will have a flight line restricted area security, noise safety, and Foreign

Object Detection (FOD) briefing before being allowed to enter aircraft taxiway or parking ramp area.

1.6. The Contracting Office and/or BCE representative shall provide guidance and directions for restricted area access during the Pre-Construction meeting and anytime thereafter.

2. PERFORMANCE:

https://www.imd.idaho.gov/visitor-control-center/ https://www.tsa.gov/travel/security-screening/identification

2.1. Submission of bids by a Contractor shall be accepted as prima fascia evidence that they have examined the specifications and drawings and have satisfied themselves as to the nature and location of the work and all other matters, which can in any way affect the work or cost thereof under this contract.

2.2. Any failure of the Contractor to acquaint themselves with all available information, including a physical survey of the site of the proposed work, will not relieve them from successfully performing all the work required to be done for a complete, finished job.

2.3. The above brief outline of principle features of the work in no way limits the responsibilities of the Contractor to perform all work and furnish all plant, labor, and material required by the specifications and plans referred herein.

2.4. All work performed under this scope of work shall be conducted in accordance with applicable Federal, State, and Local regulations, ANG policies and regulations.

2.5. Work will conclude with final acceptance by the Contracting Office and BCE representative, warranty delivery, and financial closeout.

2.6. Contractors are responsible for verifying all measurements required for bidding purpose during site walk through.

2.7. Questions asked after site visit must be submitted in writing to Contracting Office and

BCE representative no later than 7 calendar days after the site walk through.

3. MEETINGS:

3.1. The Contractor will record and provide meeting minutes for all construction meetings to include the Pre-Construction meeting.

3.2. All meeting minutes will be on letter head, memo format and will include attendance sheet, date of meeting, time of meeting, location of meeting, list of decisions, and comments provided.

3.3. All meeting minutes will be submitted to the Contracting Office and BCE representative no less than 5 calendar, and no more than 10 calendar days after the date of the meeting for acceptance.

4. ENVIRONMENTAL:

4.1. The Contractor shall comply with all Federal, State, and Local regulations pertaining to the protection of the environment and the emission of hazardous pollutants in the performance of this contract. All correspondence or discussions with Federal, State, and Local environmental regulatory agencies will be discussed and coordinated with the Contracting Office, the BCE representative, and the ANG Civil Engineering

Environmental Program Manager.

4.2. Environmental Protection Plan (EPP):

• Will be submitted and approved before NTP is given.

• Will identify any hazardous materials brought on base.

• Will identify how hazards will be stored and staged on base.

• Will identify residual materials that are deemed solid waste to be covered when traversing on base as well as on DOT roads.

• Submit the EPP within 15 days after Contract award and not less than 10 days before the preconstruction meeting. Revise the EPP throughout the project to include any reporting requirements, changes in site conditions, or contract modifications that change the project scope of work in a way that could have an environmental impact.

• Recycling & Refuse Weight Tickets to be submitted to the Environmental office prior to final acceptance being given.

• SDS for any chemicals brought onto the installation.

4.3. No requirement in this section will relieve the Contractor of any applicable federal, state, and local environmental protection laws and regulations. During Construction, identify, implement, and submit for approval any additional requirements to be included in the EPP. Maintain the current version onsite.

4.4. A brief description of each specific plan required by environmental permit or elsewhere in this Contract such as storm water pollution prevention plan, spill control plan, solid waste management plan, wastewater management plan, air pollution control plan, contaminant prevention plan, a historical, archaeological, cultural resources, biological resources and wetlands plan, or traffic control plan.

4.5. Air Quality:

• Submit truck and material haul routes along with a Dirt and Dust Control Plan for controlling dirt, debris, and dust on Installation roadways. As a minimum, identify in the plan the subcontractor and equipment for cleaning along the haul route and measures to reduce dirt, dust, and debris from roadways.

Haul route must be submitted prior to NTP being given.

• Identify air pollution generating equipment or processes that may require federal, state, or local permits under the Clean Air Act. Determine requirements based on any current installation permits and the impacts of the project. Provide a list of all fixed or mobile equipment, machinery or operations that could generate air emissions during the project to the Contracting Office and BCE.

• Identify planned air pollution-generating processes and management control measures (including, but not limited to, spray painting, abrasive blasting, demolition, material handling, fugitive dust, and fugitive emissions). Log hours of operations and track quantities of materials used.

4.6. Waste Management:

• Identify planned air pollution-generating processes and management control measures (including, but not limited to, spray painting, abrasive blasting, demolition, material handling, fugitive dust, and fugitive emissions). Log hours of operations and track quantities of materials used.

• Monthly, submit a solid waste disposal report to the Contracting Office and BCE. For each waste, the report will state the classification (using the definitions provided in this section), amount, location, and name of the business receiving the solid waste.

• Waste removed from the base will be disposed of in accordance with applicable

Federal, State, and Local regulations.

• Contractor shall follow this plan once it has been approved by the Contracting Office and BCE.

• Under no circumstances will the Contractor bring hazardous waste onto the facility.

4.7. Hazardous Material (HM) Management:

• All HM required to support the contract shall be reported to the Environmental Office using the Contractor HM Identification Form attached. The Form may be altered to improve tracking. This listing will be provided prior to work beginning and will strictly be enforced by the KO/KOR. Additional HM needed by the Contractor shall be identified to the Contracting Officer’s Representative (KOR) for approval by the

HMMP. The form shall constitute a materials submittal in the form of a quarterly report being submitted to the Base Environmental Office throughout the course of the project. In addition, Contractor shall maintain a Contractor HM Identification Form for all HM on the job site for inspection/verification. In addition:

• Contractor is required to provide Safety Data Sheets (SDSs), via the submittal process in section 7, for all materials being used in the performance of this contract with the

HM Identification Form. These SDS shall also be maintained in a Binder within the

Job Trailer or wherever the construction project is headquartered out of.

• Unused materials shall be inventoried and removed from Base property prior to close-out of the contract or expiration date of the HM.

• Contractor shall accompany the KOR and the installation Environmental Manager

(CEV) on project close-out inspection to ensure all used and unused HM has been removed from the installation. This requirement shall not be a punch list item and must be accomplished prior to the government accepting beneficial occupancy of the facility or construction item.

4.8. Hazardous Waste:

• Hazardous wastes generated as part of this project must be managed in accordance with all applicable laws.

• Identify construction activities that will generate hazardous waste or debris. Provide a documented waste determination for resultant waste streams. Identify, label, handle, store, and dispose of hazardous waste or debris in accordance with federal, state, and local regulations, including 40 CFR 261, 40 CFR 262, 40 CFR 263, 40 CFR 264, 40

CFR 265, 40 CFR 266, and 40 CFR 268.

• Manage hazardous waste in accordance with the approved Hazardous Waste

Management Section of the EPP. Store hazardous wastes in approved containers in accordance with 49 CFR 173 and 49 CFR 178.

• Hazardous waste generated within the confines of Government facilities is identified as being generated by the Government. Prior to removal of any hazardous waste from

Government property, hazardous waste manifests must be signed by the base

Environmental Manager.

• Should wastewater be generated from construction activities, the Contractor will be responsible for disposing it appropriately. Construction wastewater, regardless of its characteristics, is prohibited from being discharged into drains or water ways.

• Do not bring hazardous waste onto Government property.

• Provide the Contracting Office and BCE with a copy of waste determination documentation for any solid waste streams that have any potential to be hazardous waste or contain any chemical constituents listed in 40 CFR 372-SUBPART D.

4.9. Water Quality:

• Contractor shall not pollute storm drainage ways, streams, or reservoirs with fuels, oils, bitumen, calcium chloride, acids, construction wastes or other harmful materials.

It is the responsibility of Contractor to investigate and comply with all applicable federal, state, and municipal regulations.

• Contractor shall take particular care to prevent chemical, fuels, oils, greases, bituminous materials, waste washings, herbicides, cement, and surface drainage from entering public waters.

• In the event of a spill the Base Fire Department (9-1-1) and Environmental Office

(208-422-5327) shall be notified immediately. Subsequent communication shall be accomplished to the Contracting Office representative who will notify the

Contracting Officer and BCE of the mishap.

• Identify if your facility must apply for an EPA Construction General Permit. If so, the contractor is responsible for obtaining the permit, associated permit fees, and complying with the permit requirements. Upon completion of the project, the contractor will coordinate with the Environmental Manager the submittal of a Notice of Termination.

4.10. Unexpected Site Conditions:

• Contaminated Soil or Groundwater: Unless otherwise specified elsewhere in the

Contract Documents, the jobsite has been inspected and is, consistent with best professional judgment, free of environmental contamination or pollution.

• However, unexpected conditions can always arise. Contractor or subcontractor personnel may encounter soil or groundwater that is suspected to be contaminated, either because of odors, colors, free liquids, or other suspicious conditions.

• Should this occur, Contractor will immediately notify the Base Civil Engineer and the Base Environmental Manager and take necessary initial measures to protect workers, the site, and other personnel.

• Contractor will be provided a copy of the Installation Environmental Commitment

Statement and ensure all personnel working on the project have read and understand the Statement.

• The Base Civil Engineer and Base Environmental Manager may conduct inspections without notice at on-base work sites to ensure environmental compliance. Any items of non-compliance will be reported to the Contracting Officer (KO) for action.

• Environmental, Safety and Bioenvironmental representatives from the installation will have the opportunity to meet with the Contractor prior to commencing work, and to collaborate with the Contractor to resolve any safety/occupational health/environmental concerns.

4.11. Contactor’s Liability for Environmental Damages:

• Contractor agrees to hold harmless and indemnify the Government for any and all damages of any kind resulting from environmental violations by the Contractor, Contractor’s employees, agents or subcontractors.

• Damages include, but are not limited to, personal injury, property damage (including diminution of value), or death, environmental restoration and response costs, natural resource damages, expert witness and attorney’s fees.

• Reimbursement of any and all expenses incurred to obtain permits as a result of

Contractor’s failure to identify or obtain permits shall be borne by the Contractor.

4.12. Penalties for environmental Non-Compliance:

• Contractor shall be responsible for paying any fines or penalties assessed against the

Air Force for environmental violations resulting from acts or omissions of Contractor or its employees, subcontractors, or agents.

• This obligation is in addition to any fines or penalties that may be assessed against

Contractor for the same conduct.

• Contractor may either reimburse these fines or penalties through the Contracting

Officer, or with the consent of the Base Civil Engineer, conveyed through the

Contracting Officer, Contractor may pay such fines or penalties directly to the regulatory agency or agencies concerned.

5. SITE CONDITIONS:

5.1. Demolition And Preparation Work:

• The Contractor is responsible to protect existing facilities from damage resulting from the demolition associated with this project.

• The Contractor shall replace all damaged materials with new materials, to the satisfaction of the Contracting Office and BCE representative, at no additional cost to the Government.

• The Contractor shall bring any unforeseen project conditions to the attention of the

Contracting Office and the BCE representative immediately.

• Differing site conditions, which may alter the scope of work, shall be approved by the Contracting Office prior to such work to be performed.

5.2. Weather Conditions:

• Government shall not be responsible for providing protection from the elements for contractor’s materials, personnel, or equipment.

5.3. Field Measurements:

• The Contractor shall verify all measurements at the project site and become fully acquainted with the location and project conditions before bidding the work.

6. TRAFFIC CONTROL:

6.1. The following standards shall be always observed. Careful attention and strict adherence to these precautions can prevent accidental damage and possible injury to both pedestrians and drivers. Disregard of these rules, at the very least, will be grounds for removal from the base.

6.2. Vehicles operators must be in the possession of a valid driver’s license and current vehicle registration and insurance.

6.3. Vehicle operators shall obey the speed limits set by local officials. Vehicles shall not be driven over 25mph and will not exceed 10mph when near joggers or troops.

6.4. Vehicle operators will not use a cell phone while driving. It is acceptable to pull over and park a vehicle to use a cell phone.

6.5. Vehicle operators shall ensure that all equipment carried on their vehicles is properly stowed and secured.

6.6. No privately owned firearms are allowed on base. This includes concealed carry permit holders.

6.7. The use of seatbelts is mandatory for all vehicle occupants during any vehicle operations.

7. SUPERVISION:

7.1. The Contractor shall always have a competent superintendent in charge of the work.

Anyone found incompetent shall be removed at once and replaced by someone satisfactory when requested by the Contracting Officer or the BCE representative.

7.2. The Contractor shall report ALL labor hours (including subcontract labor hours) required for performance of services provided under this contract for the Idaho

National Guard via a secure data collection site. The Contractor is required to completely fill in all required data fields using the following Contract Manpower

Reporting Application (CRMA) web address: https://www.ecmra.mil/

7.3. Reporting inputs will be for the labor executed during the period of performance during each Government Fiscal Year (FY), which runs October 1 through September 30.

While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2017. Contractors may direct questions to the help desk at http://www.ecmra.mil/.

8. SITE SAFETY:

8.1. The Contractor shall provide and maintain work environments and procedure which will:

• Maintain OSHA compliance at the job site and while on Idaho National Guard, Gowen Field.

• Safeguard the public and government personnel, property, materials, supplies, and equipment exposed to Contractor operations and activities.

• Avoid interruptions of Government operations and delays in project completion dates.

• Control costs in the performance of this contract.

8.2. The Contractor shall ensure that any additional measures the Contracting Office or the

BCE representative determines to be reasonable and necessary for the purposes of safety are applied.

8.3. Welding, brazing, soldering, metal cutting or grinding and any work which has the potential to create a flammable hazard will require the Contractor to obtain a Hot Work

Permit from the Idaho National Guard, Gowen Field Fire Department.

8.4. The Contractor will provide barricades sufficient to prevent vehicles and pedestrian traffic from inadvertently entering the construction area on an “as needed” basis, where it is reasonable or required.

8.5. The Contractor is required to provide a current mishap prevention plan to the

Contracting Office and the BCE Representative before the ‘Notice to Proceed’ will be issued.

8.6. If the contract requires confined space entry the Contractor will provide, to the

Contracting Office and the BCE Representative, a copy of their training plan and proof that personnel conduction the confined space entry have been trained according to

IAW and OSHA guidelines.

9. ANTITERRORISM FORCE PROTECTION:

9.1. The Contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Office or the BCE representative. The Contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s security forces. The Contractor shall ensure compliance with all personal identity verification requirements as directed by local policy.

• Should the Force Protection Condition (FPCON) change, the Government may require changes in Contractor security measurers or processes.

9.2. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center

Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB)

(AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

9.3. All Contractor employees, to include subcontractor employees, requiring badged access to Government Installations, Facilities and Controlled Access areas shall complete AT Level 1 awareness training within 30 calendar days after contract start date. Certificates of completion for each affected Contractor employee and subcontractor employee will be maintained by the Contracting Office and the BCE representative. AT level 1 Awareness Training is available at the following website:

https://jko.jten.mil/courses/atl1/launch.html

10. CLEAN-UP:

10.1. During the progress of this project, the Contractor shall always keep the residue from work from being dragged, tracked off, or blown onto the active taxiways and runway adjacent to the work area. The immediate work area will be cleaned up at the end of each workday.

10.2. Any debris carried out of the work…