This is a Statement of Work (SOW) for a gas valve replacement project at Fresno Air National Guard Base in California.
The project, titled "Replace Main Gas Valve at BLDG 100" (Project No. HAYW061824), requires the contractor to reconfigure approximately 30 linear feet of existing gas piping connecting to the main gas valve and regulator for the 144th Fighter Wing installation at Building 100. The contractor must conduct an on-site review of the existing natural gas system, meet with government representatives to review layout and confirm routing, provide a proposed piping layout diagram, identify shutdown requirements, and document existing conditions with pre-construction photographs. Work includes removing the existing regulator and installing one new commercial-grade regulator sized for building load and operating pressure requirements, replacing all necessary existing natural gas valves with new commercial-grade valves, installing a minimum of three cut-off valves to control gas flow to Building 100, Building 102, and the remaining downstream installation, and finishing new gas piping with safety yellow paint per UFC/industry standards with directional flow arrows and identification labels. All work must comply with specified codes and standards including UFC 3-420-01, UFC 3-430-05, Uniform Plumbing Code, NFPA 54, ASME B31.3, ASME B31.8, ASTM standards, OSHA requirements, and manufacturer installation instructions. The contractor must complete all pressure testing, leak testing, and functional testing prior to service restoration.
The period of performance spans no longer than 30 calendar days, with work occurring between 7:00 a.m. and 4:30 p.m. Monday through Friday, excluding weekends and federal holidays. The contractor must obtain base access approval for all personnel, maintain a Quality Control Plan, provide closure documentation including certificates of no debts to suppliers, before and after photographs, and applicable O&M manuals. The contractor must possess proper qualifications including relevant licenses (e.g., CA C-36), certificates of completion, and training records demonstrating experience with plumbing and gas system work per Unified Plumbing Code requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1.0 DESCRIPTION OF SERVICES
This Statement of Work describes contractor requirements for the project titled "Replace Main Gas Valve at BLDG
100". All work will occur at the Fresno Air National Guard Base, California. The contractor is responsible to furnish and install all labor and materials to complete the items listed in this Statement of Work. The contractor shall provide the government a complete and usable product that will be inspected/accepted by the government at the completim of the project. All information included in this document, a long with the instructions and standards referenced in the document, shall be considered as part of the Statement of Work.
2.0 SITE OF WORK
All work will occur at the:
Fresno Air National Guard Base
5323 McKinley Ave Fresno, CA 93727
3.0 STATEMENT OF WORK
3.1 Objectives: The purpose of this project is to reconfigure approximately 30 linear feet of the existing gas pipe that connects to the main gas valve and main gas regulator for the 144th Fighter Wing installation at building 100. The work includes but is not limited to the following:
3.1.1 Visit the site to;
• Conduct an on-site review of the existing natural gas system.
• Meet with the Government (CE/COR) to review layout and confirm system routing.
• Provide a proposed piping layout diagram showing new valves, regulator, and reconfigured piping.
• Identify shutdown requirements and coordinate gas outage procedures.
• Document existing concealed or differing conditions discovered at the site visit.
• Provide pre-construction photographs of existing conditions.
3.1.2 All work performed shall be in accordance with the following codes and Standards;
• UFC 3-420-01 (Plumbing Systems)
• UFC 3-430-05 (Utility Systems)
• Applicable UFGS sections
• Uniform Plumbing Code (UPC)
• NFPA 54 - National Fuel Gas Code
• ASME B31.3 - Process Piping
• ASME B31.8 - Gas Transmission & Distribution Piping Systems
• ASTM A53/A106 - Steel Pipe Standards
• ASTM A234 - Steel Pipe Fittings
• OSHA 1926 Subpart P - Excavation Safety
• OSHA Hot Work Standards
• AFI and AFMAN engineering/safety standards
• Manufacturer installation instructions
File details come from the government source that posted it. Updated .