This Statement of Work (SOW) details roof repair requirements for two buildings at the 187th Fighter Wing in Montgomery, Alabama. The project involves repairs for Munitions Building 1804 and Civil Engineer Building 1801, which include removing and replacing existing roof components, metal parapet wall panels, flashing, and vent stack boots. For Building 1804, work focuses on wall sections over the admin portion, while Building 1801 requires complete second-floor roof membrane replacement with a new .060 Fully Adhered TPO Roof System.

The contract is set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) with an estimated project value between $100,000 and $250,000. The performance period is 60 days after contract award, with work to be completed between 0700-1700 hours Tuesday through Friday, excluding federal holidays. Contractors must provide a one-year workmanship warranty and a 20-year roof system warranty. The project is managed by the 187th Civil Engineer Squadron, with a contracting officer's representative to be designated. Funds are contingent upon appropriation availability, and all debris must be disposed of at an off-base landfill.

View the file

Other files

File Type Posted
Bldg_1801_Floor_Plan.pdf PDF
Solicitation Amendment W50S6N25QA0120002 SF 30.pdf PDF
RFIs.docx DOCX document
187FW B1801_B1804 Map.pdf PDF
1804 A2.jpg JPG image
1804_1808_1A01.pdf PDF
1804 A.jpg JPG image
B1804 Roof 2.jpg JPG image
B1804 Roof 4.jpg JPG image
1804_1808_1A02.pdf PDF
Solicitation Amendment - W50S6N25QA0120001.pdf PDF
Solicitation Amendment W50S6N25QA0120001 SF 30.pdf PDF
Site Visit Slides_Roof Repair 1801 1804.pdf PDF
Site Visit Attendance Sheet..pdf PDF
2. SOW - MUNS B1804 and CE B1801 Roof Repair.docx DOCX document
Solicitation - W50S6N25QA012.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Munitions B1804 & Civil Engineer B1801 Roof Repair

Alabama Air National Guard

187th FW 5187 Selma Hwy Montgomery, AL 36108

General Information The Air National Guard has a requirement for roof repairs on Building 1804 in the Munitions Complex and on the Civil Engineer Building 1801 at the 187th Fighter Wing. The work covered by this Statement of Work consists of furnishing all labor, equipment, and travel to make the needed repairs.

General Scope of Work:

The project is being managed from the 187th Civil Engineer Squadron (187th CES) and 187th Contracting offices located at Montgomery Air National Guard Base in Montgomery, Alabama. A contracting officer’s representative (COR) will be designated at the 187th CES.

Description of Work:

The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items needed to remove and replace the existing roof components and damaged lightning protection components at the 187th FW as defined below:

Munitions Building 1804 (CLIN 001) Remove existing vertical metal parapet wall panels, coping, and flashing along the roof wall sections located over the admin portion of the facility. Existing wall panels over work bays to remain. All existing horizontal metal roof to remain.

Seal block on north parapet wall with commercially available waterproofing.

Furnish and install new flashing on block parapet wall.

Furnish and install new metal wall panels, coping, and flashing on metal parapet walls.

Remove and replace all extrusion boots around vent stacks.

Dispose of all demolished material off site.

Provide one year workmanship warranty.

Civil Engineer Building 1801 (CLIN 002) Remove existing 2nd floor roof membrane.

Remove any existing roof insulation that is damaged or wet. (CLIN 003) Furnish and install new insulation as needed. R-value to be in-kind with existing insulation. (CLIN 003) Note: Please provide unit pricing – Sq Foot. (Government shall use estimated amount of 4,000 sq foot for comparison.

Furnish and install new .060 Fully Adhered TPO Roof System With Associated TPO Flashings.

Remove and replace all extrusion boots.

Dispose of all demolished material off site.

Provide one year workmanship warranty.

Provide 20 year roof system warranty.

Period of performance:

The period of performance shall be 60 days after notice to proceed following contract award.

Place and hours of Performance The contractor is responsible for conducting business between the hours of 0700-1700 hours Tuesday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings.

The project location is in a controlled area. The 187th CES will provide an escort for all contractor personnel within the controlled area.

If contractor desires to work on Monday’s prior coordination with the 187th CES will be required to obtain an escort to the work area.

The Contractor must at all times maintain an adequate workforce for the uninterrupted execution of all tasks defined within this SOW when the Government facility is not closed for the above reasons.

Recognized Holidays:

New Year’s Day
Labor Day
Martin Luther King Jr.’s Birthday
Columbus Day
Washington’s Birthday
Veterans Day
Memorial Day
Thanksgiving Day
Juneteenth National Independence Day
Christmas Day

Independence Day

Prior to the award of the contract the Contractor will attend a Pre-Bid Conference at a time and date determined by the 187th Contracting Office. During this conference the Contractor will visit the site and conduct a preliminary walk-through with 187th CES personnel. During the site visit, the Contractor will identify any issues that may conflict with or affect the outcome of the work. The Contractor is expected to include any cost required for the accommodation of such items within the original cost proposal.

Disposal Requirements:

The Contractor is responsible for the collection and disposal of all debris, rubble, residue and waste material generated in the execution of work under this contract. All such materials shall be disposed of at an off-base landfill by the CONTRACTOR. The CONTRACTOR is not permitted to deposit any such materials in base trash collection containers or at any on base location without prior approval of the Contracting Officer.

Existing Conditions:

The Contractor is responsible for returning all conditions of the site to the condition it was in prior to work beginning, to include but not limited to soils, grass, pavements, and utilities.

Security Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within Government controlled installation, facility, or area. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

For Contractors that do not require CAC, but require access to a DoD Facility and/or Installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 10-245, AFI 31-101 and AFMAN 31-113), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

Antiterrorism Awareness Level I Training (AT Level I). This standard language is for contractor employees with an area of performance within a US Government controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access to US Government installations, facilities and controlled access areas shall complete AT Level I training within XX calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. AT Level I may be accomplished by a Level I qualified instructor; completing the Force Protection computer-based training (CBT) course on the Advanced Distributed Learning System (ADLS), or Joint Knowledge Online at http://jko.jten.mil. Tracking for each contractor or subcontractor employee is the responsibility of the COR or unit AT Representative.