This is Standard Form 30 Amendment No. 0002 to Solicitation W50S6M26QA0140014, issued by the 117th Air Force Reserve Command (W/MT USPFO Activity) on August 21, 2026, with an effective date of August 21, 2026. The solicitation is not extended, and offers must acknowledge receipt of this amendment prior to the hour and date specified in the original solicitation or as amended.

The amendment modifies the Statement of Work (SOW) for project BRKR262005—Sewer Pipe Re-Ligner at Sumpter Smith Joint National Guard Base in Birmingham, Alabama. The contractor must provide sprayinplace pipe lining rehabilitation services for six facilities (151, 141, 142, 175, 149, and 030), encompassing approximately 1,000 linear feet of piping. Key work elements include full pipe inspection and camera scoping assessment, mechanical cleaning and preparation, sprayinplace epoxy or polymer lining installation, post-lining camera inspection and testing, and site cleanup. The contractor is responsible for verifying actual pipe dimensions during the mandatory site visit, which is scheduled for September 1, 2026 at 10:00 AM CDT at Building 700, Civil Engineering Squadron Conference Room. Pre-registration for the site visit is required at least three business days prior, with attendees providing firm name, telephone number, visitor's full name, Social Security number, and driver's license information to MSgt Jonathan Werkmeister (jonathan.werkmeister@us.af.mil). The total contract performance period is 120 days. Additional requirements include compliance with Antiterrorism Level I training, facility access and security procedures, U.S. Air Force Quality Assurance standards, and federal regulatory guidance including Unified Facilities Criteria and applicable ANG and AF forms.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Solicitation/Contract Form

The following changes have been made:

Miscellaneous text in this section has been added to:

A site visit is highly encouraged for all interested offerors.

Date: Sept 1, 2026

Time: 10AM CDT

Location: Attendees will meet at 5401 East Lake Blvd. Birmingham, AL 35217, Bldg. 700 Civil Engineering Squadron Conference Room.

Site Visit Registration: Due to security requirements, all attendees must pre-register. Please email the following information to MSgt Jonathan Werkmeister email jonathan.werkmeister@us.af.

mil at least three (3) business days prior to the site visit.

-Firm Name and Telephone number

-Visitor's Full Name

-Social Security Number

-Driver's License Number and State of Issue

Failure to provide this information may result in denial of access to the installation.

Description/Specifications/Statement of Work

Miscellaneous text in this section has been modified to:

W50S6M26QA0140002

Statement of Work (SOW)

BRKR262005 - SEWER PIPE RE-LIGNER

117th ARW, Sumpter Smith Joint National Guard Base, Alabama

26 August 2026

Part 1 - GENERAL

1.1 Project Identification

1.1.1 The General Provisions of the Contract, including General and Supplementary Conditions and General Requirements (if any), apply to all work specified in this document.

1.2 Scope of Work

1.2.1 General Description

The contractor will provide all labor, materials, equipment, and supervision necessary to complete the sprayinplace pipe lining rehabilitation process for the following facilities:

Facility 151

Facility 141

Facility 142

Facility 175

Facility 149

Facility 030

*** IMPORTANT: Bidder/Contractor to verify actual pipe length and diameter during site visit during the solicitation period. Dimensions given in this statement of work are estimates. It is the bidder's responsibility to verify actual pipe dimensions before submitting a bid. ***

Work includes full pipe inspection, cleaning, preparation, lining installation, testing, and documentation for roughly 1,000 LF of piping.

2.1 Site Assessment

The contractor shall:

Conduct a full inspection of existing piping systems within each facility.

Perform a complete camera scoping assessment to accurately evaluate pipe condition, identify corrosion, blockages, structural defects, and determine suitability for lining.

Document all findings with video, photos, and written reports.

Identify any code compliance issues requiring correction.

Verify access points, pipe diameters, and system layout to ensure compatibility with the sprayinplace lining process.

2.2 Pipe Cleaning and Preparation

The contractor shall:

Isolate and depressurize piping systems as required.

Mechanically clean the interior of all designated pipes using descaling tools, highpressure jetting, or mechanical brushing.

Remove corrosion, scale, debris, and obstructions to ensure proper adhesion of the lining material.

Thoroughly dry the piping system to meet manufacturer requirements.

Rescope cleaned pipes with a camera to confirm readiness for lining.

2.3 SprayInPlace Pipe Lining Rehabilitation

The contractor shall:

Furnish and install an approved castinplace epoxy or polymer lining system suitable for the specific pipe type (potable water, wastewater, or mechanical).

Apply the lining material uniformly to the manufacturerspecified thickness to restore pipe integrity and extend service life.

Ensure proper curing times and environmental conditions during application.

Verify that all lined sections meet required adhesion, thickness, and smoothness standards.

Provide documentation of material batch numbers, application thickness, and cure verification.

2.4 PostLining Inspection and Testing

The contractor shall:

Conduct a final camera inspection of all lined pipes to verify full coverage, uniformity, and absence of defects.

Perform pressure testing or flow testing as required by code and manufacturer specifications.

Provide digital inspection reports, test results, and certification of system integrity.

Submit all documentation to the Contracting Officer for review and acceptance.

1.6 Site Cleanup

Thoroughly clean the work area of dust, dirt, and debris.

Restore all affected areas to their original condition.

Dispose of all materials in accordance with applicable regulations.

Follow ANGETL, ANG Handbook, and Unified Facilities Criteria throughout the project.

The Contracting Officer Representative will perform Contracting Officer Representative (COR) duties.

1.7 Contract Responsibilities

The contractor shall:

Notify the Contracting Officer immediately if work outside the scope is requested. No additional work shall begin without written authorization.

Cost increases beyond the original budget estimate will not justify additional fees unless caused by an approved scope change.

Contract directly with the Contracting Officer.

Provide and pay for all labor, materials, equipment, tools, and machinery.

Issue all required notices and comply with all applicable codes, ordinances, and regulations.

Notify the Contracting Officer in writing of any observed variances between contract documents and legal requirements.

Assume responsibility for work performed contrary to requirements if no notice is provided.

Accept modifications to contract documents required due to legal requirements.

Maintain strict discipline and good order among employees; do not employ unfit or unskilled personnel.

Provide all required submittals (shop drawings, catalog cuts, brochures, test reports, schedules, estimates, correspondence) in a timely manner.

1.8 Submittals

All materials must be approved prior to installation.

No work may begin until it is reviewed with the Contracting Officer.

Any deviations must be reported to the Contractor and Contracting Officer.

The contractor is responsible for full compliance with this SOW.

Milestones and deliverables must be submitted prior to mobilization.

Part 2 - PRODUCT SUBMITTAL

2.1 Construction Materials

Contractor shall use AF Form 3000 to document all provided materials.

Contractor shall review all materials to determine acceptability for government use.

Part 3 - EXECUTION

3.1 Regulatory Guidance

Applicable regulatory documents include:

Unified Facilities Criteria (UFC)

ANG Form 920 Report

AF Form 7115 Real Property Report

ANGH 321084 (27 Jan 2015) Space Authorization

The Contracting Officer Representative will provide all known regulations, standards, and directives.

Part 4 - QUALITY ASSURANCE

Contractor shall follow U.S. Air Force standard Quality Assurance (QA) and Quality Control (QC) procedures.

Contractor shall implement documented processes for testing, inspection, and verification of all deliverables.

Part 6 - MISCELLANEOUS

Insurance requirements apply as specified in the contract.

Payment will be made monthly in arrears through the Government's Wide Area Workflow (WAWF) system.

Contractor must complete required forms for all hazardous materials brought into the installation and for all waste generated.

Base hours of operation are Tuesday through Friday, 0700 - 1730 Central. Work may be performed outside of these hours with approval of the Base Civil Engineer or Deputy Base Civil Engineer. Work outside of the normal hours of operation may be permitted to prevent disruption of base activities during the project.

Part 7 - ANTITERRORISM / OPERATIONS SECURITY

7.1 Access and Security Requirements

- Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within Government controlled installation, facility, or area. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer's Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation's Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy.

Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

7.2 NonCAC Contractor Access

Contractors requiring installation access without a CAC must comply with:

- For Contractors that do not require CAC but require access to a DoD Facility and/or Installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 10- 245, AFI 31-101 and AFMAN 31-113), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

7.3 Antiterrorism Level I Training

- Antiterrorism Awareness Level I Training (AT Level I). This standard language is for contractor employees with an area of performance within a US Government controlled installation, facility or area. All contractor employees, including subcontractor employees, requiring access to US Government installations, facilities and controlled access areas shall complete AT Level I training within 45 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. AT Level I may be accomplished by a Level I qualified instructor; completing the Force Protection computer-based training (CBT) course on Joint Knowledge Online (JKO) at https://jkodirect.jten.mil/Atlas2/ faces/page/login/Login.seam. For those without a CAC, select "Non-CAC" user on the JKO site. Tracking for each contractor or subcontractor employee is the responsibility of the COR or unit AT Representative.

PERFORMANCE PERIOD

The total performance period for this contract is 120 days.

END OF DOCUMENT

IDCode: J
Page: 1
Pages: 8
AmendNo: 0002
EffDate: 21 AUG 2026
ReqNo:
ProjNo:
IssCode: W50S6M
AdmCode:
IssuedBy: W7MT USPFO ACTIVITY ALANG 117

KO FOR ALANG DO NOT DELETE, 5401 E LAKE BLVD54

BIRMINGHAM, AL 35217-3595

UNITED STATES

JONATHAN WERKMEISTER, EMAIL: JONATHAN.WERKMEISTER@US.AF.MIL TELEPHONE: 2057142719 AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: W50S6M26QA014
SolDate: 21 AUG 2026
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: A site visit will occur 1 September 2026 @ 10 AM CST for this project.

Posting updated Statement of Work dated 26 August 2026.

ContNameTitle:
CoNameTitle: WILLIAM HALL
ContDate:
CODate: 26 AUG 2026