Sewer Pipe Realignment RFI Questions.docx

DOCX document 16 KB Posted

Attached to
117 Sewer Pipe Realignment
Solicitation number
W50S6M26QA014
Issued by

About this file

This is a Request for Information (RFI) Questions and Answers document for solicitation W50S6M26QA014, addressing contractor inquiries regarding sewer pipe realignment services at the 117th Air Refueling Wing in Birmingham, Alabama.

The RFI clarifies that this is a brand-new contract with no incumbent contractor. The project involves full inspection and repairs of existing piping systems across six facilities, with all buildings equipped with 4-inch ductile iron pipe. Contractors have flexibility in selecting access points, with the main sewer line entry into each building identified as a primary option. The government provided a current sewer map as an attachment and specified that work shutdown procedures would involve notifying building occupants of temporary restroom unavailability with advance notice. The solicitation is being issued via Standard Form 1449 with a Firm Fixed Price (FFP) contract award structure based on Lowest Price Technically Acceptable criteria. Offers must include a signed SF 1449, completed CLIN schedule with pricing, representations and certifications (or SAM.gov confirmation), and two to three past performance references. A mandatory site visit is scheduled for September 1, 2026, at 10:00 AM CST, with the updated Statement of Work dated August 26, 2026. All offerors must be registered in SAM.gov and submit proposals electronically to MSgt Jonathan Werkmeister and William Hall, referencing solicitation number W50S6M26QA014.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sewer Pipe Realignment RFI Questions

1. We would like to know if this is a brand-new contract OR if there is (was) an incumbent performing these services. If not brand new, could you please provide the current / previous contract number?

a. This is a brand-new contract, there was no incumbent performing these services.

2. Pipe diameters and materials, exact sections requiring lining, available drawings or CCTV reports, access points, and any shutdown or bypass requirements?

a. All buildings have 4 inch ductile iron pipe.

b. The contractor to determine what access point is the best for them but the main sewer line going into the building is one option.

c. See Attachment for the most current sewer map.

d. Shutdown procedure would be to notify building occupants that the restrooms are unavailable during work. We would give plenty of advance notice to the building occupants.