This federal contract solicitation seeks services to repair fire suppression systems at two aircraft maintenance hangars located in Birmingham, Alabama. The project involves replacing an existing aqueous film forming foam system with a high expansion foam system, resolving life safety and code deficiencies, upgrading the water supply system, and replacing all necessary valves, pumps and control systems to ensure a fully functional high expansion foam fire suppression system. The solicitation also requires the disposal of aqueous film forming foam products and equipment in accordance with applicable codes and laws. Responding contractors must provide all plant, labor, transportation, materials, tools, equipment, appliances and supervision necessary to complete the project in accordance with plans and specifications dated January 20, 2020. The soliciting agency is the Department of the Army Alabama Army National Guard.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Date: 1 July 2020
To: SMSgt. William Hall
Subject: ADDENDUM NO. 2
Project: REPAIR FIRE SUPPRESSION, FUEL CELL BUILDING 135
REPAIR FIRE SUPPRESSION, HANGAR BUILDING 138
Job #: ANG# BRKR162322 / SSL# 17069
ANG# BRKR162323 & SSL# 17070
From: David Donovan
The plans and Specifications for Repair Fire Suppression, Fuel Cell Building 135, dated 20 January 2020, revised 20 March 2020, are amended as follows: (Where there are conflicts between the plans and specifications and the addendum, this addendum shall govern).
Item No. 1: Refer to the drawings. Delete and replace the following drawing sheets with the attached revised drawing sheets:
1. E-100 – New Work Hangar 135 Power Plan (Revised date of 26
June 2020)
2. FA-003 – Fire Alarm Details Building 135 (Revised date of 26 June
2020)
3. FP-110 – Fire Protection Plan – Overall New Work (Revised date of 24 June 2020)
Item No. 2: Refer to specifications. Delete and replace the following specification sections with the attached revised specification sections:
1. Section 01 5000 - Temporary Facilities and Controls (Revised date of 30 June 2020)
2. Section 01 5100 – Temporary Utilities (Revised date of 30 June
2020)
3. Section 01 6116 – Volatile Organic Compound (VOC) Content
Restrictions (revised date of 30 June 2020)
4. Section 01 7000 – Execution and Closeout Requirements (Revised date of 30 June 2020)
5. Section 05 5213 – Pipe and Tube Railings (revised date of 30 June
2020)
REPAIR FIRE SUPPRESSION, FUEL CELL BUILDING 135 BRKR162322
REPAIR FIRE SUPPRESSION, HANGAR BUILDING 138 BRKR162323
ADDENDUM NO. 2 Page 2 of 3 Seay Seay & Litchfield, P.C. 1 July 2020
6. Section 07 4100 – Metal Wall Panels (revised date of 30 June 2020)
7. Section 31 2210 – Earthwork (revised date of 30 June 2020)
8. Section 32 1217 – Asphalt Concrete Paving (revised date of 30 June
2020)
Item No. 3: Refer to drawings. Add the attached drawing sheet A2.5 – Details with a revised date of 30 June 2020.
Item No. 4: Refer to drawing sheet E-100 “New Work Hangar 135 Power Plan. Refer to Power Riser Diagram. Delete the generator connection receptacle that is shown wired to the Manual Transfer Switch (MTS). The MTS shall be provided with lugs that are rated for a generator to be directly wired to the switch.”
The plans and Specifications for Repair Fire Suppression, Hangar Building 138, dated 20 January 2020, revised 20 March 2020, are amended as follows: (Where there are conflicts between the plans and specifications and the addendum, this addendum shall govern).
Item No. 1: Refer to the drawings. Delete and replace the following drawing sheets with the attached revised drawing sheets:
1. A2.1 – Pump House Plan (revised date of 22 June 2020)
2. A2.3 – Ground Floor Plan – Building 138 (revised date of 30 June
2020)
3. A2.5 – Details (revised date of 30 June 2020)
4. E-001 – Electrical Legend and General Notes (revised date of 26
June 2020)
5. E-002 – Lighting Schedule and Details (revised date of 26 June
2020)
6. E-004 – Fire Alarm Details Building 138 (revised date of 26 June
2020)
7. E-100 – New Work Electrical Plan Fire Pump Building (revised date of 26 June 2020)
8. E-101 – New Work Hangar 138 Power Plan (revised date of 26
June 2020)
9. ES-3 – Electrical Site Details (revised date of 26 June 2020)
10. FA-003 – Fire Alarm Details Building 138 (revised date of 26 June
2020)
11. FP110 – Fire Protection Plan – Overall New Work (revised date of
24 June 2020)
REPAIR FIRE SUPPRESSION, FUEL CELL BUILDING 135 BRKR162322
REPAIR FIRE SUPPRESSION, HANGAR BUILDING 138 BRKR162323
ADDENDUM NO. 2 Page 3 of 3 Seay Seay & Litchfield, P.C. 1 July 2020
Item No. 2: Refer to specifications. Delete and replace the following specification sections with the attached revised specification sections:
1. Section 01 5000 - Temporary Facilities and Controls (Revised date of 30 June 2020)
2. Section 01 5100 – Temporary Utilities (Revised date of 30
June 2020)
3. Section 01 6116 – Volatile Organic Compound (VOC) Content
Restrictions (revised date of 30 June 2020)
4. Section 01 7000 – Execution and Closeout Requirements
(Revised date of 30 June 2020)
5. Section 07 4100 – Metal Wall Panels (revised date of 30 June
2020)
6. Section 31 2210 – Earthwork (revised date of 30 June 2020)
7. Section 32 1217 – Asphalt Concrete Paving (revised date of 30
June 2020)
Item No. 3: Refer to drawing sheet E-101 “New Work Hangar 138 Power Plan. Refer to Power Riser Diagram. Delete the generator connection receptacle that is shown wired to the Manual Transfer Switch (MTS). The MTS shall be provided with lugs that are rated for a generator to be directly wired to the switch.”
End of Addendum #2
60" MAX.
TO TOP
ELEVATION
NOT TO SCALE
10"
ELEVATION
72"
1"
MOUNTING HEIGHT
PER NFPA 72 24.5.14
NEC HAZARDOUS CLASSIFICATIONS
FA-003
F
IR
E A
L
R M
D
T
IL
S
B U
IN
G
Sheet Number
Sheet Title
Project Title e a y e a i t c h f i e l d r c h i t e c t s
Architects & Interior Designers www.sslarch.com
Job Number
Date
Drawn By
Checked By
Revised
1115 South Court Street
Montgomery, AL 36104
334. 263. 5162
BRKR162323/SSL17070
D. BAGWELL
F. BRADLEY
P
IO
N
H
W
20 JANUARY 2020
BAGWELL ENGINEERING, INC
Job Number:
216 E. Government St.
Pensacola, FL 32502
Phone: (850) 462-8040
AL Authorization No. 4901
AL PE No. 33694
Be 17-073
26 JUNE 2020
AutoCAD SHX Text
4" SQ. J-BOX
SPD
LOW LOSS COAX CABLE IN 1" RGS CONDUIT TO ANTENNA
120 V. CIRCUITRY (2 # 12, 1 # 12 GND., 1/2" EMT) FROM 20/1 CIRCUIT BREAKER IN EXISTING PANEL
FIRE ALARM SYSTEM CONDUIT AND WIRING AS REQUIRED
SURFACE MOUNT MASS NOTIFICATION SYSTEM LOC UNIT TO EXISTING WALL
EXISTING FINISHED FLOOR
EXISTING FINISHED CEILING (ACOUSTICAL CEILING TILE)
NEW TRANSCEIVER "TR" (MONACO BTX)
4" SQUARE JUNCTION BOX
3/4" EXPOSED CONDUIT AND WIRING AS REQUIRED FOR SYSTEM
MASS NOTIFICATION SYSTEM LOC UNIT
MASS NOTIFICATION LOCAL OPERATORS CONSOLE (EMERGENCY AHU SHUTDOWN PUSHBUTTON INSIDE)
ALL NEW LOCAL OPERATORS CONSOLES (LOC'S) SHALL BE FURNISHED WITH LAMINATED PLASTIC NAMEPLATES. NAMEPLATES SHALL BE MELAMINE PLASTIC, 0.125" THICK, WHITE WITH BLACK CENTER CORE. SURFACE SHALL BE MATTE FINISHED. CORNERS SHALL BE SQUARE. ACCURATELY ALIGN LETTERING AND ENGRAVE INTO THE CORE. MINIMUM SIZE OF NAMEPLATES SHALL BE 1" X 10". LETTERING SHALL BE A MINIMUM OF .25" HIGH, NORMAL BLOCK STYLE. FASTEN NAMEPLATES WITH A MINIMUM OF TWO SHEET-METAL SCREWS OR TWO RIVETS, PER NAMEPLATE
NEW FIRE ALARM/MASS NOTIFICATION CONTROL PANEL "FACU"
EXISTING FINISHED FLOOR
3/4" EMT WITH WIRING AS REQUIRED
CONDUIT AND WIRING TO DEVICES AS REQUIRED
2 # 12, 1 # 12 GND., 1/2" EMT
TEXT SIGN CONTROLLER
CONDUIT AND WIRING TO TEXT SIGNS AS REQUIRED
HAZARDOUS LOCATION NOTES: 1. THE AREA WITHIN 5 FT HORIZONTALLY FROM AIRCRAFT THE AREA WITHIN 5 FT HORIZONTALLY FROM AIRCRAFT POWER PLANTS OR AIRCRAFT FUEL TANKS SHALL BE CLASSIFIED AS CLASS 1, DIVISION 2 THAT SHALL EXTEND UPWARD FROM THE FLOOR TO A LEVEL 5 FT ABOVE THE UPPER SURFACE OF WINGS AND OF ENGINE ENCLOSURES 2. THE DIAGRAM SHOWN IS TAKEN FROM NFPA 70 AND THE DIAGRAM SHOWN IS TAKEN FROM NFPA 70 AND REPRESENTS AN EXAMPLE OF THE CODE REQUIREMENT WITH A GENERAL AIRPLANE. THE AIRPLANE IN THIS HANGAR WILL BE A KC-135. SHEET FA-200 SHOWS THE AIRPLANE OUTLINE. 3. ALL WORK IN THE HANGAR SHALL BE COMPLIANT WITH ALL WORK IN THE HANGAR SHALL BE COMPLIANT WITH NFPA 70 ARTICLE 513. 4. REFER TO SHEET LS1.0 FOR HAZARDOUS LOCATION REFER TO SHEET LS1.0 FOR HAZARDOUS LOCATION DESIGNATION OF SPACE. NOTE THAT THE ENTIRE AREA OF THE HANGAR AND OTHER ASSOCIATED ROOMS SHOWN AS CLASS 1 DIVISION 2 SPACES SHALL BE CLASSIFIED UP TO A LEVEL 18" ABOVE THE FLOOR.
Sheets and Views
FA-003
Repair Fire Suppression, Hangar Building 138 17070/BRKR162323 117th Air Refueling Wing - Birmingham, AL Type B-3 (100%) Submittal 20 January 2020
Revised 30 June 2020
TEMPORARY FACILITIES AND CONTROLS 01 5000 - 1
SECTION 01 5000 - TEMPORARY FACILITIES AND CONTROLS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Temporary telecommunications services.
B. Temporary sanitary facilities.
C. Temporary Controls: Barriers, enclosures, and fencing.
D. Waste removal facilities and services.
E. Field offices.
1.02 RELATED REQUIREMENTS
A. Section 01 5100 - Temporary Utilities.
B. Section 01 5500 - Vehicular Access and Parking.
1.03 TELECOMMUNICATIONS SERVICES (MODIFIED BY ADDENDUM NO. 2)
A. Provide, maintain, and pay for telecommunications services to field office at time of project mobilization.
A. The Contractor shall provide, maintain, and pay for telecommunications services to field office at time of project mobilization.
B. Telecommunications services shall include:
1. Windows-based personal computer dedicated to project telecommunications, with necessary software and laser printer.
2. Telephone Land Lines: One line, minimum; one handset per line.
3. Internet Connections: Minimum of one; DSL modem or faster.
2. Telephone Service: Cellular telephone, one for both the project superintendent and on-site quality control manager. Each line shall have cellular service plans to include unlimited minutes, unlimited long-distance calling, and unlimited data. Cellular device shall be capable of reviewing and responding to project email correspondence.
3. Internet Connections: High speed wireless connection. Contractor’s option.
Wireless stick, wireless phone hot-spot, etc... are acceptable internet service options.
TEMPORARY FACILITIES AND CONTROLS 01 5000 - 2
1.04 TEMPORARY SANITARY FACILITIES
A. Provide and maintain required facilities and enclosures. Provide at time of project mobilization.
B. Use of existing facilities is not permitted.
C. Maintain daily in clean and sanitary condition.
1.05 BARRIERS
A. Provide barriers to prevent unauthorized entry to construction areas, to prevent access to areas that could be hazardous to workers or the public, to allow for owner's use of site and to protect existing facilities and adjacent properties from damage from construction operations and demolition.
B. Provide barricades and covered walkways required by governing authorities for public rights-of-way and for public access to existing building.
C. Provide protection for plants designated to remain. Replace damaged plants.
D. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.
1.06 FENCING (MODIFIED BY ADDENDUM NO. 2)
A. Provide minimum of 6 foot (1.8 m) high fence around construction site; equip with vehicular and pedestrian gates with locks. Contractor is responsible for site safety.
Fencing requirement listed above is a minimum only. Contractor to provide all fencing/site protection measures to ensure the safety of the site and public.
A. The Contractor is solely responsible for site safety and security. Contractor shall erect and maintain fencing as deemed necessary by the Contractor around construction equipment, construction material storage areas, and active construction areas as deemed necessary to protect materials, work in place, and the public while allowing for continued occupancy and operations of the Government throughout the duration of the project.
1.07 EXTERIOR ENCLOSURES
A. Provide temporary insulated weather tight closure of exterior openings to accommodate acceptable working conditions and protection for Products, to allow for temporary heating and maintenance of required ambient temperatures identified in individual specification sections, and to prevent entry of unauthorized persons. Provide access doors with self-closing hardware and locks.
TEMPORARY FACILITIES AND CONTROLS 01 5000 - 3
1.08 INTERIOR ENCLOSURES
A. Provide temporary partitions and ceilings as may be required to adequately separate work areas from Owner-occupied areas, to prevent penetration of dust and moisture into Owner-occupied areas, and to prevent damage to existing materials and equipment.
B. Submit phasing and dustproofing plan to Owner and Architect prior to beginning selective demolition activities.
1.09 VEHICULAR ACCESS AND PARKING - See Section 01 5500
1.10 WASTE REMOVAL
A. See Section 01 7419 - Construction Waste Management and Disposal, for additional requirements.
B. Provide waste removal facilities and services as required to maintain the site in clean and orderly condition.
C. Provide containers with lids. Remove trash from site periodically.
D. If materials to be recycled or re-used on the project must be stored on-site, provide suitable non-combustible containers; locate containers holding flammable material outside the structure unless otherwise approved by the authorities having jurisdiction.
E. Open free-fall chutes are not permitted. Terminate closed chutes into appropriate containers with lids.
1.11 FIELD OFFICES
A. Office: Weathertight, with lighting, electrical outlets, heating, cooling equipment, and equipped with sturdy furniture, drawing rack, and drawing display table.
B. Provide space for Project meetings, with table and chairs to accommodate 10 persons.
C. Locate offices a minimum distance of 30 feet (10 m) from existing and new structures.
D. Field office to remain in place during entire construction schedule including as day project on site shut period.
1.12 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS
A. Remove temporary utilities, equipment, facilities, materials, prior to Date of Substantial Completion inspection.
B. Clean and repair damage caused by installation or use of temporary work.
C. No underground installations for temporary utilities are permitted on the site without written approval by the Contracting Officer.
TEMPORARY FACILITIES AND CONTROLS 01 5000 - 4
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
END OF SECTION
TEMPORARY UTILITIES 01 5100 - 1
SECTION 01 5100 - TEMPORARY UTILITIES
A. Temporary Utilities: Provision of electricity, lighting, heat, ventilation, and water.
A. Section 01 5000 - Temporary Facilities and Controls:
1. Temporary telecommunications services for administrative purposes.
2. Temporary sanitary facilities required by law.
1.03 TEMPORARY ELECTRICITY
A. Cost: By Owner.
B. Connect to Owner's existing power service.
1. Do not disrupt Owner's need for continuous service.
2. Exercise measures to conserve energy.
C. Complement existing power service capacity and characteristics as required.
D. Provide power outlets for construction operations, with branch wiring and distribution boxes located at each floor. Provide flexible power cords as required.
E. Provide main service disconnect and over-current protection at convenient location and meter.
F. Permanent convenience receptacles may not be utilized during construction.
G. Provide adequate distribution equipment, wiring, and outlets to provide single phase branch circuits for power and lighting.
1.04 TEMPORARY LIGHTING FOR CONSTRUCTION PURPOSES
A. Provide and maintain 1 watt/sq ft (10.8 watt/sq m) lighting to exterior staging and storage areas after dark for security purposes.
B. Provide branch wiring from power source to distribution boxes with lighting conductors, pigtails, and lamps as required.
C. Maintain lighting and provide routine repairs.
D. Permanent building lighting may be utilized during construction.
TEMPORARY UTILITIES 01 5100 - 2
1.05 TEMPORARY HEATING
A. Cost of Energy: By Owner.
B. Provide heating devices and heat as needed to maintain specified conditions for construction operations.
C. Owner's existing heat plant may be used.
1. Exercise measures to conserve energy.
D. Prior to operation of permanent equipment for temporary heating purposes, verify that installation is approved for operation, equipment is lubricated and filters are in place.
Provide and pay for operation, maintenance, and regular replacement of filters and worn or consumed parts.
1.06 TEMPORARY COOLING
A. Cost of Energy: By Owner.
B. Provide cooling devices and cooling as needed to maintain specified conditions for
C. Owner's existing cooling plant may be used.
1. Exercise measures to conserve energy.
D. Prior to operation of permanent equipment for temporary cooling purposes, verify that installation is approved for operation, equipment is lubricated and filters are in place.
Provide and pay for operation, maintenance, and regular replacement of filters and worn or consumed parts.
1.07 TEMPORARY VENTILATION (MODIFIED BY ADDENDUM NO. 2)
A. Utilize existing ventilation equipment. Extend and supplement equipment with temporary fan units as required to maintain clean air for construction operations.
A. Use of existing HVAC systems for construction ventilation is not allowed. Contractor shall provide temporary ventilation units as required to:
1. Meeting applicable material/system installation ventilation requirements.
2. Meet and exceed OSHA requirements for health and safety of construction personnel
3. Create negative pressure within work areas to prevent dust and construction debris from leaving the work area and migrating into adjacent areas being occupied by the Government while work is ongoing.
1.08 TEMPORARY WATER SERVICE
A. Cost of Water Used: By Owner.
TEMPORARY UTILITIES 01 5100 - 3
B. Provide and maintain suitable quality water service for construction operations at time of project mobilization.
C. Connect to existing water source.
1. Exercise measures to conserve water.
D. Extend branch piping with outlets located so water is available by hoses with threaded connections. Provide temporary pipe insulation to prevent freezing.
VOLATILE ORGANIC COMPOUND (VOC) CONTENT RESTRICTIONS 01 6116 - 1
SECTION 01 6116 - VOLATILE ORGANIC COMPOUND (VOC) CONTENT
RESTRICTIONS
A. VOC restrictions for product categories listed below under "DEFINITIONS."
B. All products of each category that are installed in the project must comply; Owner's project goals do not allow for partial compliance.
A. Section 01 3000 - Administrative Requirements
B. Section 01 4000 - Quality Requirements
C. Section 01 5721 - Indoor Air Quality Controls
D. Section 01 6000 - Product Requirements
1.03 DEFINITIONS
A. VOC-Restricted Products: All products of each of the following categories when installed or applied on-site in the building interior:
1. Adhesives, sealants, and sealer coatings.
2. Carpet.
3. Carpet cushion.
4. Carpet tile.
5. Resilient floor coverings.
6. Wood flooring.
7. Paints and coatings.
8. Insulation.
9. Gypsum board.
10. Acoustical ceilings and panels.
11. Cabinet work.
12. Wall coverings.
13. Composite wood and agrifiber products used either alone or as part of another product.
14. Other products when specifically stated in the specifications.
B. Interior of Building: Anywhere inside the exterior weather barrier.
VOLATILE ORGANIC COMPOUND (VOC) CONTENT RESTRICTIONS 01 6116 - 2
C. Adhesives: All gunnable, trowelable, liquid-applied, and aerosol adhesives, whether specified or not; including flooring adhesives, resilient base adhesives, and pipe jointing adhesives.
D. Sealants: All gunnable, trowelable, and liquid-applied joint sealants and sealant primers, whether specified or not; including firestopping sealants and duct joint sealers.
1.04 REFERENCE STANDARDS
A. CAL (CHPS LEM) - Low-Emitting Materials Product List; California Collaborative for High Performance Schools (CHPS); current edition at www.chps.net/.
B. CAL (CDPH SM) - Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions From Indoor Sources Using Environmental Chambers;
California Department of Public Health; v1.1, 2010.
C. CRI (GLCC) - Green Label Testing Program - Approved Product Categories for Carpet Cushion; Carpet and Rug Institute; Current Edition.
D. CRI (GLP) - Green Label Plus Testing Program - Certified Products; www.carpet-rug.org; current edition.
E. GEI (SCH) - GREENGUARD "Children and Schools" Certified Products;
GREENGUARD Environmental Institute; current listings at www.greenguard.org.
F. GreenSeal GC-03 - Anti-Corrosive Paints; Green Seal, Inc.; 2007
G. GreenSeal GS-11 - Paints; Green Seal, Inc.; 1993.
H. GreenSeal GS-36 - Commercial Adhesives; 2011.
I. SCAQMD 1113 - South Coast Air Quality Management District Rule No.1113; current edition.
J. SCAQMD 1168 - South Coast Air Quality Management District Rule No.1168; current edition.
K. SCS (CPD) - SCS Certified Products; current listings at www.scscertified.com.
1.05 SUBMITTALS
A. See Section 01 3001 - Submittals
B. Evidence of Compliance: Submit for each different product in each applicable category.
1. Identify evidence submittals with the words "LEED Report".
C. Product Data: For each VOC-restricted product used in the project, submit evidence of compliance.
VOLATILE ORGANIC COMPOUND (VOC) CONTENT RESTRICTIONS 01 6116 - 3
1.06 QUALITY ASSURANCE (REQUIREMENT REMOVED BY ADDENDUM NO. 2)
A. Testing Agency Qualifications: Independent firm specializing in performing testing and inspections of the type specified in this section.
PART 2 PRODUCTS
2.01 MATERIALS
A. All VOC-Restricted Products: Provide products having VOC content of types and volume not greater than those specified in State of California Department of Health Services Standard Practice for the Testing of Volatile Organic Emissions From Various Sources Using Small-Scale Environmental Chambers.
1. Evidence of Compliance: Acceptable types of evidence are:
a. Current GREENGUARD Children & Schools certification;
www.greenguard.org.
b. Current Carpet and Rug Institute Green Label Plus certification; www.carpet-rug.org.
c. Current SCS Floorscore certification; www.scscertified.com.
d. Current SCS Indoor Advantage Gold certification; www.scscertified.com.
e. Product listing in the CHPS Low-Emitting Materials Product List at www.chps.net/manual/lem_table.htm.
f. Current certification by any other agencies acceptable to CHPS.
g. Report of laboratory testing performed in accordance with CHPS requirements for getting a product listed in the Low-Emitting Materials Product List; report must include laboratory's statement that the product meets the specified criteria.
B. Adhesives and Joint Sealants: Provide only products having volatile organic compound (VOC) content not greater than required by South Coast Air Quality Management District Rule No.1168.
a. Report of laboratory testing performed in accordance with requirements.
b. Published product data showing compliance with requirements.
c. Certification by manufacturer that product complies with requirements.
C. Aerosol Adhesives: Provide only products having volatile organic compound (VOC) content not greater than required by GreenSeal GS-36.
a. Current GreenSeal Certification.
b. Report of laboratory testing performed in accordance with GreenSeal GS-36
c. Published product data showing compliance with requirements.
D. Paints and Coatings:
VOLATILE ORGANIC COMPOUND (VOC) CONTENT RESTRICTIONS 01 6116 - 4
1. Provide coatings that comply with the most stringent requirements specified in the following:
a. 40 CFR 59, Subpart D--National Volatile Organic Compound Emission
Standards for Architectural Coatings.
b. Ozone Transport Commission (OTC) Model Rule, Architectural, Industrial, and Maintenance Coatings; www.otcair.org; specifically:
1) Opaque, Flat: 50 g/L, maximum.
2) Opaque, Nonflat: 150 g/L, maximum.
3) Opaque, High Gloss: 250 g/L, maximum.
4) Varnishes: 350 g/L, maximum.
c. USGBC LEED Rating System, edition as stated in Section 01 3515; for interior wall and ceiling finish (all coats), anti-corrosive paints on interior ferrous metal, clear wood stains and finishes, sanding sealers, other sealers, shellac, and floor coatings.
1) Architectural Paints and Coatings: Do not exceed VOC content limits established in GreenSeal GS-11.
2) Anti-Corrosive and Anti-Rust Paints: Do not exceed VOC content limits established in GreenSeal GC-03.
3) Clear Wood Finishes, Floor Coatings, Stains, Primers and Shellacs: Do not exceed the VOC content limits established in SCAQMD Rule No.
1113.
2. Determination of VOC Content: Testing and calculation in accordance with 40 CFR 59, Subpart D (EPA Method 24), exclusive of colorants added to a tint base and water added at project site; or other method acceptable to authorities having jurisdiction.
3. Evidence of Compliance: Acceptable types of evidence are:
a. Report of laboratory testing performed in accordance with requirements.
E. Carpet and Adhesive: Provide products having VOC content not greater than that required for CRI Green Label Plus certification.
a. Current Green Label Plus Certification.
b. Report of laboratory testing performed in accordance with requirements.
F. Carpet Cushion: Provide products having VOC content not greater than that required for CRI Green Label certification.
a. Current Green Label Certification.
G. Carpet Tile and Adhesive: Provide products having VOC content not greater than that required for CRI Green Label Plus certification.
VOLATILE ORGANIC COMPOUND (VOC) CONTENT RESTRICTIONS 01 6116 - 5
a. Current Green Label Plus Certification.
H. Composite Wood and Agrifiber Products and Adhesives Used for Laminating Them:
Provide products having no added urea-formaldehyde resins.
a. Current SCS "No Added Urea Formaldehyde" certification;
www.scscertified.com.
I. Other Product Categories: Comply with limitations specified elsewhere.
PART 3 EXECUTION
3.01 FIELD QUALITY CONTROL
A. Owner reserves the right to reject non-compliant products, whether installed or not, and require their removal and replacement with compliant products at no extra cost to Owner.
B. Additional costs to restore indoor air quality due to installation of non-compliant products will be borne by Contractor.
EXECUTION AND CLOSEOUT REQUIREMENTS 01 7000 - 1
SECTION 01 7000 - EXECUTION AND CLOSEOUT REQUIREMENTS
A. Examination, preparation, and general installation procedures.
B. Pre-installation meetings.
C. Cutting and patching.
D. Surveying for laying out the work.
E. Cleaning and protection.
F. Starting of systems and equipment.
G. Demonstration and instruction of Owner personnel.
H. Closeout procedures, including Contractor's Correction Punch List, except payment procedures.
I. General requirements for maintenance service.
A. Section 01 1000 - Summary
B. Section 01 3000 - Administrative Requirements
C. Section 01 4000 - Quality Requirements
D. Section 01 7800 - Closeout Submittals
1.03 REFERENCE STANDARDS
A. NFPA 241 - Standard for Safeguarding Construction, Alteration, and Demolition Operations; 2013.
1.04 SUBMITTALS
A. See Section 01 3001 - Submittals
B. Survey work: Submit name, address, and telephone number of Surveyor before starting survey work.
1. On request, submit documentation verifying accuracy of survey work.
2. Submit a copy of site drawing and certificate signed by the Engineer, that the elevations and locations of the work are in conformance with Contract Documents.
EXECUTION AND CLOSEOUT REQUIREMENTS 01 7000 - 2
3. Submit surveys and survey logs for the project record.
C. Cutting and Patching: Submit written request in advance of cutting or alteration that affects:
1. Structural integrity of any element of Project.
2. Integrity of weather exposed or moisture resistant element.
3. Efficiency, maintenance, or safety of any operational element.
4. Visual qualities of sight exposed elements.
5. Include in request:
a. Identification of Project.
b. Location and description of affected work.
c. Necessity for cutting or alteration.
d. Description of proposed work and products to be used.
e. Alternatives to cutting and patching.
f. Date and time work will be executed.
D. Project Record Documents: Accurately record actual locations of capped and active utilities.
1.05 QUALIFICATIONS
A. For surveying work, employ a land surveyor registered in the State in which the Project is located and acceptable to Architect. Submit evidence of surveyor's Errors and Omissions insurance coverage in the form of an Insurance Certificate. Employ only individual(s) trained and experienced in collecting and recording accurate data relevant to ongoing construction activities, B. For field engineering, employ a professional engineer of the discipline required for specific service on Project, licensed in the State in which the Project is located.
Employ only individual(s) trained and experienced in establishing and maintaining horizontal and vertical control points necessary for laying out construction work on project of similar size, scope and/or complexity.
1.06 PROJECT CONDITIONS
A. Use of explosives is not permitted.
B. Grade site to drain. Maintain excavations free of water. Provide, operate, and maintain pumping equipment.
C. Ventilate enclosed areas to assist cure of materials, to dissipate humidity, and to prevent accumulation of dust, fumes, vapors, or gases.
D. Erosion and Sediment Control: Plan and execute work by methods to control surface drainage from cuts and fills, from borrow and waste disposal areas. Prevent erosion and sedimentation.
1. Minimize amount of bare soil exposed at one time.
EXECUTION AND CLOSEOUT REQUIREMENTS 01 7000 - 3
2. Provide temporary measures such as berms, dikes, and drains, to prevent water flow.
3. Periodically inspect earthwork to detect evidence of erosion and sedimentation;
promptly apply corrective measures.
4. Refer to applicable division 31 specifications for additional requirements.
E. Noise Control: Provide methods, means, and facilities to minimize noise produced by
F. Pollution Control: Provide methods, means, and facilities to prevent contamination of soil, water, and atmosphere from discharge of noxious, toxic substances, and pollutants produced by construction operations. Comply with federal, state, and local regulations.
1.07 COORDINATION
A. Coordinate scheduling, submittals, and work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements.
B. Notify affected utility companies and comply with their requirements.
C. Verify that utility requirements and characteristics of new operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, such equipment.
D. Coordinate space requirements, supports, and installation of mechanical and electrical work that are indicated diagrammatically on drawings. Follow routing indicated for pipes, ducts, and conduit, as closely as practicable; place runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.
E. In finished areas except as otherwise indicated, conceal pipes, ducts, and wiring within the construction. Coordinate locations of fixtures and outlets with finish elements.
F. Coordinate completion and clean-up of work of separate sections.
G. After Owner occupancy of premises, coordinate access to site for correction of defective work and work not in accordance with Contract Documents, to minimize disruption of Owner's activities.
2.01 PATCHING MATERIALS
A. New Materials: As specified in product sections; match existing products and work for patching and extending work.
EXECUTION AND CLOSEOUT REQUIREMENTS 01 7000 - 4
B. Type and Quality of Existing Products: Determine by inspecting and testing products where necessary, referring to existing work as a standard.
C. Product Substitution: For any proposed change in materials, submit request for substitution described in Section 01 6000 - Product Requirements.
3.01 EXAMINATION
A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent work. Start of work means acceptance of existing conditions.
B. Verify that existing substrate is capable of structural support or attachment of new work being applied or attached.
C. Examine and verify specific conditions described in individual specification sections.
D. Take field measurements before confirming product orders or beginning fabrication, to minimize waste due to over-ordering or misfabrication.
E. Verify that utility services are available, of the correct characteristics, and in the correct locations.
F. Prior to Cutting: Examine existing conditions prior to commencing work, including elements subject to damage or movement during cutting and patching. After uncovering existing work, assess conditions affecting performance of work. Beginning of cutting or patching means acceptance of existing conditions.
3.02 PREPARATION
A. Clean substrate surfaces prior to applying next material or substance.
B. Seal cracks or openings of substrate prior to applying next material or substance.
C. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond.
3.03 PREINSTALLATION MEETINGS
A. When required in individual specification sections, convene a preinstallation meeting at the site prior to commencing work of the section.
B. Require attendance of parties directly affecting, or affected by, work of the specific section.
C. Notify Architect and Contracting Officer four days in advance of meeting date.
D. Prepare agenda and preside at meeting:
1. Review conditions of examination, preparation and installation procedures.
2. Review coordination with related work.
EXECUTION AND CLOSEOUT REQUIREMENTS 01 7000 - 5
E. Record minutes and distribute copies within two days after meeting to participants, with electronic copies to Architect, Owner, participants, and those affected by decisions made.
3.04 LAYING OUT THE WORK
A. Verify locations of survey control points prior to starting work.
B. Promptly notify Architect of any discrepancies discovered.
C. Contractor shall locate and protect survey control and reference points.
D. Protect survey control points prior to starting site work; preserve permanent reference points during construction.
E. Promptly report to Contracting Officer the loss or destruction of any reference point or relocation required because of changes in grades or other reasons.
F. Replace dislocated survey control points based on original survey control. Make no changes without prior written notice to Contracting Officer.
G. Utilize recognized engineering survey practices.
H. Establish a minimum of two permanent bench marks on site, referenced to established control points. Record locations, with horizontal and vertical data, on project record documents.
I. Establish elevations, lines and levels. Locate and lay out by instrumentation and similar appropriate means:
1. Site improvements including pavements; stakes for grading, fill and topsoil placement; utility locations, slopes, and invert elevations.
2. Grid or axis for structures.
3. Building foundation, column locations, ground floor elevations.
J. Periodically verify layouts by same means.
K. Maintain a complete and accurate log of control and survey work as it progresses.
L. Building Lines and Levels: Locate and lay out batter boards for structures, building foundations, column grids and locations, floor levels and control lines and levels required for mechanical and electrical Work.
M. Site Improvements: Locate and lay out site improvements, including pavements, stakes for grading, fill and topsoil placement, utility slopes and invert elevations by instrumentation and similar appropriate means.
N. Existing utilities and equipment: The existence and location of underground and other utilities and construction indicated as existing are not guaranteed. Before beginning sitework, investigate and verify the existence and location of underground utilities and other construction. Furnish information necessary to adjust, move or relocate existing structures, utility poles, lines, services or other appurtenances located in, or affected by construction. Coordinate with local authorities having jurisdiction with construction.
EXECUTION AND CLOSEOUT REQUIREMENTS 01 7000 - 6
O. On completion of foundation walls and major site improvements, prepare a certified survey illustrating dimensions, locations, angles, and elevations of construction and site work.
3.05 GENERAL INSTALLATION REQUIREMENTS
A. Install products as specified in individual sections, in accordance with manufacturer's instructions and recommendations, and so as to avoid waste due to necessity for replacement.
B. Make vertical elements plumb and horizontal elements level, unless otherwise indicated.
C. Install equipment and fittings plumb and level, neatly aligned with adjacent vertical and horizontal lines, unless otherwise indicated.
D. Make consistent texture on surfaces, with seamless transitions, unless otherwise indicated.
E. Make neat transitions between different surfaces, maintaining texture and appearance.
3.06 ALTERATIONS
A. Drawings showing existing construction and utilities are based on casual field observation and existing record documents only.
1. Verify that construction and utility arrangements are as indicated.
2. Report discrepancies to Contracting Officer before disturbing existing installation.
3. Beginning of alterations work constitutes acceptance of existing conditions.
B. Maintain weatherproof exterior building enclosure except for interruptions required for replacement or modifications; take care to prevent water and humidity damage.
1. Where openings in exterior enclosure exist, provide construction to make exterior enclosure weatherproof.
C. Remove existing work as indicated and as required to accomplish new work.
1. Remove rotted wood, corroded metals, and deteriorated masonry and concrete;
replace with new construction specified.
2. Remove items indicated on drawings.
3. Relocate items indicated on drawings.
4. Where new surface finishes are to be applied to existing work, perform removals, patch, and prepare existing surfaces as required to receive new finish; remove existing finish if necessary for successful application of new finish.
5. Where new surface finishes are not specified or indicated, patch holes and damaged surfaces to match adjacent finished surfaces as closely as possible.
D. Services (Including but not limited to HVAC, Plumbing, Fire Protection, Electrical, and Telecommunications): Remove, relocate, and extend existing systems to accommodate new construction.
EXECUTION AND CLOSEOUT REQUIREMENTS 01 7000 - 7
1. Maintain existing active systems that are to remain in operation; maintain access to equipment and operational components; if necessary, modify installation to allow access or provide access panel.
2. Verify that abandoned services serve only abandoned facilities.
3. Remove abandoned pipe, ducts, conduits, and equipment, including those above accessible ceilings; remove back to source of supply where possible, otherwise cap stub and tag with identification; patch holes left by removal using materials specified for new construction.
E. Protect existing work to remain.
1. Prevent movement of structure; provide shoring and bracing if necessary.
2. Perform cutting to accomplish removals neatly and as specified for cutting new work.
3. Repair adjacent construction and finishes damaged during removal work.
F. Adapt existing work to fit new work: Make as neat and smooth transition as possible.
1. When existing finished surfaces are cut so that a smooth transition with new work is not possible, terminate existing surface along a straight line at a natural line of division and make recommendation to Architect.
2. Where removal of partitions or walls results in adjacent spaces becoming one, rework floors, walls, and ceilings to a smooth plane without breaks, steps, or bulkheads.
3. Where a change of plane of 1/4 inch (6 mm) or more occurs in existing work, submit recommendation for providing a smooth transition for Architect review and request instructions.
4. Trim existing wood doors as necessary to clear new floor finish. Refinish trim as required.
G. Patching: Where the existing surface is not indicated to be refinished, patch to match the surface finish that existed prior to cutting. Where the surface is indicated to be refinished, patch so that the substrate is ready for the new finish.
H. Refinish existing surfaces as indicated:
1. Where rooms or spaces are indicated to be refinished, refinish all visible existing surfaces to remain to the specified condition for each material, with a neat transition to adjacent finishes.
2. If mechanical or electrical work is exposed accidentally during the work, re-cover and refinish to match.
I. Clean existing systems and equipment.
J. Remove demolition debris and abandoned items from alterations areas and dispose of off-site; do not burn or bury.
K. Do not begin new construction in alterations areas before demolition is complete.
L. Comply with all other applicable requirements of this section.
EXECUTION AND CLOSEOUT REQUIREMENTS 01 7000 - 8
3.07 CUTTING AND PATCHING
A. Whenever possible, execute the work by methods that avoid cutting or patching.
B. See Alterations article above for additional requirements.
C. Perform whatever cutting and patching is necessary to:
1. Complete the work.
2. Fit products together to integrate with other work.
3. Provide openings for penetration of mechanical, electrical, and other services.
4. Match work that has been cut to adjacent work.
5. Repair areas adjacent to cuts to required condition.
6. Repair new work damaged by subsequent work.
7. Remove samples of installed work for testing when requested.
8. Remove and replace defective and non-conforming work.
D. Do not cut and patch structural elements in a manner that would reduce their load-carrying capacity or load-deflection ratio.
E. Obtain approval of the cutting and patching proposal before cutting and patching the following structural elements:
1. Foundation construction.
2. Bearing and retaining walls.
3. Structural concrete.
4. Structural steel.
5. Lintels.
6. Timber and primary wood framing.
7. Structural decking.
8. Stair systems.
9. Miscellaneous structural metals.
10. Exterior curtain wall construction.
11. Equipment supports.
12. Piping, ductwork, vessels and equipment.
13. Structural systems of special construction in Division-13.
F. Contractor to provide insect control and weahter tight at structure. All openings or penetrations made to be well-sealed from insect or rodents with plaster, “play” sand, copper gauze - contractor to adhere to all applicable fire ratings.
G. Operational and Safety Limitations: Do not cut and patch operating elements or safety related components in a manner that would result in reducing their capacity to perform as intended, or result in increased maintenance, or decreased operational life or safety.
H. Obtain approval of the cutting and patching proposal before cutting and patching the following operating elements or safety related systems:
1. Primary operational systems and equipment.
2. Membranes and flashings.
3. Fire protection systems.
4. Communication systems.
EXECUTION AND CLOSEOUT REQUIREMENTS 01 7000 - 9
5. Electrical wiring systems.
I. Execute work by methods that avoid damage to other work and that will provide appropriate surfaces to receive patching and finishing.
J. Employ skilled and experienced installer to perform cutting for weather exposed and moisture resistant elements, and sight exposed surfaces.
K. Cut rigid materials using masonry saw or core drill. Pneumatic tools not allowed without prior approval.
L. Restore work with new products in accordance with requirements of Contract Documents.
M. Fit work tight to pipes, sleeves, ducts, conduit, and other penetrations through surfaces.
N. At penetrations of fire rated walls, partitions, ceiling, or floor construction, completely seal voids with fire rated material in accordance with Section 07 8400, to full thickness of the penetrated element.
O. To avoid marring existing finished surfaces, cut or drill from the exposed or finished side into concealed surfaces.
P. Patching:
1. Finish patched surfaces to match finish that existed prior to patching. On continuous surfaces, refinish to nearest intersection or natural break. For an assembly, refinish entire unit.
2. Match color, texture, and appearance.
3. Repair patched surfaces that are damaged, lifted, discolored, or showing other imperfections due to patching work. If defects are due to condition of substrate, repair substrate prior to repairing finish.
3.08 PROGRESS CLEANING
A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in a clean and orderly condition.
B. Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces, and other closed or remote spaces, prior to enclosing the space.
C. Broom and vacuum clean interior areas prior to start of surface finishing, and continue cleaning to eliminate dust.
D. Collect and remove waste materials, debris, and trash/rubbish from site periodically and dispose off-site; do not burn or bury.
3.09 PROTECTION OF INSTALLED WORK
A. Protect installed work from damage by construction operations.
B. Provide special protection where specified in individual specification sections.
EXECUTION AND CLOSEOUT REQUIREMENTS 01 7000 - 10
C. Provide temporary and removable protection for installed products. Control activity in immediate work area to prevent damage.
D. Provide protective coverings at walls, projections, jambs, sills, and soffits of openings.
E. Protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects, by protecting with durable sheet materials.
F. Prohibit traffic or storage upon waterproofed or roofed surfaces. If traffic or activity is necessary, obtain recommendations for protection from waterproofing or roofing material manufacturer.
G. Remove protective coverings when no longer needed; reuse or recycle coverings if possible.
3.10 SYSTEM STARTUP
A. Coordinate schedule for start-up of various equipment and systems.
B. Verify that each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, and for conditions that may cause damage.
C. Verify tests, meter readings, and specified electrical characteristics agree with those required by the equipment or system manufacturer.
D. Verify that wiring and support components for equipment are complete and tested.
E. Execute start-up under supervision of applicable Contractor personnel and manufacturer's representative in accordance with manufacturers' instructions.
F. When specified in individual specification Sections, require manufacturer to provide authorized representative to be present at site to inspect, check, and approve equipment or system installation prior to start-up, and to supervise placing equipment or system in operation.
G. Submit a written report that equipment or system has been properly installed and is functioning correctly.
3.11 DEMONSTRATION AND INSTRUCTION
A. Demonstrate start-up, operation, control, adjustment, trouble-shooting, servicing, maintenance, and shutdown of each item of equipment at scheduled time, at equipment location.
B. For equipment or systems requiring seasonal operation, perform demonstration for other season within six months.
C. Provide a qualified person who is knowledgeable about the Project to perform demonstration and instruction of Owner's personnel.
EXECUTION AND CLOSEOUT REQUIREMENTS 01 7000 - 11
D. Utilize operation and maintenance manuals as basis for instruction. Review contents of manual with Owner's personnel in detail to explain all aspects of operation and maintenance.
E. Prepare and insert additional data in operations and maintenance manuals when need for additional data becomes apparent during instruction.
F. Demonstration to include identification of air filter locations and filter replacement procedures.
3.12 ADJUSTING
A. Adjust operating products and equipment to ensure smooth and unhindered operation.
3.13 FINAL CLEANING
A. Execute final cleaning prior to Beneficial Occupancy.
B. Use cleaning materials that are nonhazardous.
C. Clean interior and exterior glass, surfaces exposed to view; remove temporary labels, stains and foreign substances, polish transparent and glossy surfaces, vacuum carpeted and soft surfaces.
D. Remove all labels that are not permanent. Do not paint or otherwise cover fire test labels or nameplates on mechanical and electrical equipment.
E. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned.
F. Replace filters of operating equipment.
G. Clean debris from roofs, gutters, downspouts, scuppers, overflow drains, area drains, and drainage systems.
H. Clean site; sweep paved areas, rake clean landscaped surfaces.
I. Remove waste, surplus materials, trash/rubbish, and construction facilities from the site; dispose of in legal manner; do not burn or bury.
3.14 CLOSEOUT PROCEDURES
A. Accompany Project Coordinator on preliminary inspection to determine items to be listed for completion or correction in the Contractor's Correction Punch List for Contractor's Notice of Substantial Completion.
B. Refer to requirements of General Conditions of the Contract for Construction.
C. Beneficial Occupancy
1. Notify Contracting Officer when work is considered ready for Substantial
Completion.
EXECUTION AND CLOSEOUT REQUIREMENTS 01 7000 - 12
2. Submit written certification that Contract Documents have been reviewed, work has been inspected, and that work is complete in accordance with Contract Documents and ready for Architect's review.
3. Notify Contracting Officer of intended date of Beneficial Occupancy as early as is feasbily possible. Contracting Officer will schedule Final Inspection of the work with Owner, and Architect's Consultants. Contractor shall coordinate attendance of the Final Inspection by local Fire Department and other code officials requiring attendance.
4. Upon completion of the Final Inspection, if the work is deemed substantially complete, the Contracting Officer will distribute a Certificate of Substantial Completion with "Punch List" of items required to be corrected by the Contractor prior to Final Acceptance of the Work.
D. Final Acceptance
1. Correct items of work listed in executed Certificate of Beneficial Occupancy.
2. Notify Contracting Officer when work is considered finally complete.
3. Submit a certified copy of the Architect's final inspection list of items to be completed or corrected, stating that each item has been completed or otherwise resolved for acceptance, and the list has been endorsed and dated by the Architect.
4. Upon completion of reinspection, the Contracting Officer will prepare a certificate of final acceptance, or advise the Contractor of Work that is incomplete or of obligations that have not been fulfilled but are required for final acceptance.
5. If necessary, reinspection will be…