This document provides an amendment to a solicitation for repair and replacement of fire suppression systems at two buildings on an Air National Guard base in Alabama.

The amendment decreases the period of performance from 635 to 585 days to align with revised schedule logic. It also provides responses to requests for information. The solicitation seeks services to replace aging aqueous film-forming foam systems with new high-expansion foam systems at Buildings 135 and 138, including removal and disposal of existing equipment. A pre-bid conference and site visit were held in June 2020. The solicitation is set aside for small businesses and is subject to Davis-Bacon wage rates. The award will be a firm-fixed-price contract for services to be completed in accordance with specifications dated January 2020.

View the file

Other files

Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

1. Amendment is to reduce the Period of Preformance from: 635 Days To: 585 Days

2. The revised B3 specifications that w ere issued in addendum no. 1 included a change in the schedule logic that shortened the period of performance to 585 days.

3. This Amendment w ill furthermore, provide request for information responses

4. All other terms and conditions w ill remain the same.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 7

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 14-Jul-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W50S6M20B0001

X 9B. DATED (SEE ITEM 11)

09-Jun-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Jul-2020

CODE

NGAL-PFO-PC

117TH AIR REFUELING WING -MSG,

5401 EAST LAKE BLVD

BIRMINGHAM AL 35217

W912JA 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W50S6M20B0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The contractor period of performance end date has decreased by 50 days from 635 days to 585 days.

The following have been modified:

NOTES

Begin Section 00010

1. All information relating to this IFB, including pertinent changes/amendments and information will be posted on web site: https://beta.sam.gov.

2. Facsimile transmission of bid is not authorized. Electronic submission of bids will NOT be accepted.

3. All information relating to this IFB, including pertinent changes/amendments and information will be posted on web site: https://beta.sam.gov. For security reasons, all potential offerors, plan rooms and printing companies are required to be registered in the GSA System for Award Management (SAM) database. Firms can register via the SAM internet site at https://www.sam.gov/portal/public/SAM/. Interested bidders are required to submit their representations and certifications at the same site.

4. Reserved.

5. A complete bid package must contain the following:

(a) Offer, Standard Form (SF) 1442 front and back signed

(b) Section 00010 Line Items- all items must be priced

(c) An Original Bid Bond and original Power of Attorney is required along with the bid on the due date

(d) Section 00600, Representations and Certifications, completed and return only additional certifications found in this section In addition, the offeror must have entered current and complete data within the past year in Online Representations and Certifications at www.sam.gov.

(e) When completing the “Offeror” portion of the SF 1442 (Blocks 14 – 20), an official having the authority to contractually bind the company must sign the SF 1442 in accordance with FAR 4.102.

One copy of the SF1442 is required to have an original signature.

(f) All amendments to the solicitation must be acknowledged.

(g) Mark the front of the envelope with the following: “BID No.W50S6M-20-B-0001”, and the Name and Address of Bidder. See Block 13A of SF 1442 for required number of copies

6. Joint Venture Requirements - Parties wishing to propose as a joint venture must submit, with the Pro Forma documents, an executed copy of the joint venture agreement. The joint venture agreement shall be executed in accordance with FAR 4.102(d). Each joint venture partner shall submit evidence satisfactory to the Contracting Officer that its Board of Directors has approved its participation in the joint venture or by an instrument of similarly binding character in the case of an unincorporated entity. Offerors are reminded that to obtain an award the awardee, to include a joint venture, must be registered in the System for Award Management (SAM) database.

Applicable to set-aside solicitations: Joint Ventures must meet applicable size standards (See FAR Subpart 19.1).

Submit with the proposal any size determination for the Joint Venture entity received from the Small Business Administration. A Joint Venture where-in one party is not a small business may be referred to the Small Business Administration ( IAW FAR 19.302 (b)) to determine eligibility. All questions regarding Joint Ventures must be directed to the Small Business Administration (SBA) and not the Contracting Officer.

NOTE: An Original Bid bond and Original Power of Attorney is required with submission of the bid. The bid bond is due on the date as stated on the SF1442 block 13. The bid bond must be on a SF24 form. Rejection of a bid bond shall be in accordance with FAR 28.101-4 Noncompliance with bid guarantee requirements.

End Section 00010

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

SECTION 00100

SECTION 00100

INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

1. Description of the Project:

Repair and Replace Fire Suppression System in Building 135 and 138 in accordance with the Specifications and Drawings dated 20 January 2020 for Project Numbers BRKR162323 and BRKR162322. The work site is at the 117th ARW, Birmingham IAP, Birmingham, Al. The project scope includes the following:

Provide all labor, tools, parts transportation, tools, equipment, materials, supplies, services, permits, insurance, supervision necessary to replace fire suppression system – as per Specifications and Drawings, dated 20 January, 2020. Project Number: BRKR162323 at the 117th ARW, Birmingham IAP, Birmingham, Al.

The project scope includes the following:

1. Replace existing Aqueous Film Forming Foam fire suppression system with a High Expansion Foam system.

2. Properly dispose of all AFFF prodcuts and equipment in accordance with codes.

3. Replace all necessary valves, pumps and control systems. Upgrade water supply.

Provide all labor, tools, parts transportation, tools, equipment, materials, supplies, services, permits, insurance, supervision necessary to replace fire suppression system – as per Specifications and Drawings, dated 20 January, 2020. Project Number: BRKR162322 at the 117th ARW, Birmingham IAP, Birmingham, Al.The project scope includes the following:

1. Replace existing Aqueous Film Forming Foam fire suppression system with a High Expansion Foam system.

2. Properly dispose of all AFFF prodcuts and equipment in accordance with codes.

3. Replace all necessary valves, pumps and control systems. Upgrade water supply.

2. Instructions to Bidders:

2.1. You are invited to submit a Bid in response to our Invitation for Bid (IFB) W50S6M-20-B-0001, Repair and Replace Fire Suppression System in Building 135 and 138, Project Number # BRKR162323 and BRKR162322.

2.2. As a result of this solicitation, the Government intends to award a Firm Fixed Price (FFP) contract resulting from this solicitation to the responsible bidder whose bid, conforming to the invitation for bids, will be most advantageous to the Government, considering only price.

2.3. This solicitation is set-aside 100% for Small Businesses.

3. Reserved:

4. Notice of Pre-Bid Conference and Site Visit:

4.1. A pre-bid conference will be conducted on Friday 19 June 2020 at 10:00 Central Time, for the purposes of briefing on the proposal requirements and answering questions regarding this solicitation. This conference will be held at Building 700 – Civil Engineering Building 5401 East Lake Blvd, Birmingham Al. THIS IS THE ONLY TIME A SITE VISIT WILL BE held, All Interested contractors are encouraged to attend. All attendees, will be required to have their temperature taken, wear a mask, and comply with all social distancing guidelines.

4.2. Due to security conditions, all offeror must register to attend this conference and site visit. Email the following information for all attendees to 117th Base Contracting Office at the following addresses: william.k.hall14.mil@mail.mil and jeffrey.a.farmer4.mil@mail.mil

Firm Name and Telephone Number Visitor’s Name and Social Security No.

Driver’s License Citizenship

4.3 This information must be provided in advance, not later than 3 business days prior to the meeting, in order to ensure access to the military base and conference site and ensure adequate seating for the conference attendees. Even if you have access to the base you must register to ensure adequate seating. The furnishing of the above information is voluntary; however, your failure to furnish all or part of the requested information may result in the Government’s denial of your access to the pre-proposal conference. This information will be provided to the Base Security Forces who will authorize your entrance to the site.

4.4 Visitors must pick up their passes at the Installation’s Main Entry Gate prior to arrival. You will be required to present the following information upon arrival: (1) Vehicle Registration, (2) Valid Driver’s License. Any of the above information furnished by you is protected under the Privacy Act and shall not be released unless permitted by law and/or you have consented to such.

4.5 Information provided at this conference or site visit shall not qualify the terms and conditions of the solicitation and specifications. Terms of the solicitation and specifications remain unchanged unless the solicitation is amended in writing. If an amendment is issued, normal procedures relating to the acknowledgment and receipt of solicitation amendments shall apply.

4.6. A record of the conference shall be made and furnished to all prospective offeror via posting to https://beta.sam.gov/. The record will include minutes of the meeting, including questions (on a non-attribution basis) and answers.

5. Formal Communication, Offeror Explanations:

5.1 Submit all questions on the by email to the contracting office at the address shown below. Do NOT contact AE or Engineering personnel directly. Doing so will only delay your answer All question must come throught the Contracting Office.

Subject Line: Reference No. W50S6M-20-B-0001 Email: william.k.hall14.mil@mail.mil and jeffrey.a.farmer4.mil@mail.mil

INQUIRIES SHALL BE SUBMITTED VIA EMAIL AND INCLUDE THE FOLLOWING

INFORMATION.

Date of Proposal Inquiry: _______________ From: ______________________________ Company Name: ______________________________

Phone Number: _____________________________ Fax Number:__________________________ Email address: ________________________________________________________________ Proposal Inquiry: Be specific as to part of solicitation you are questioning.

5.2. Any explanation desired by an offeror regarding the meaning or interpretation of the solicitation, or proposals, drawings, specifications, etc. must be requested in writing and with sufficient time allowed for a reply to reach offeror before the submission of their offer.

5.3. The Contracting Officer reserves the right to address questions received after the fifth day prior to solicitation closing with those offers deemed compliant and/or in the competitive range after closing. All questions and requests for information (RFI) must be received NOT LATER THAN the fifth working day prior to closing and will be posted not later than two working days prior to closing. OFFERORS ARE STRONGLY ENCOURAGED TO SUBMIT QUESTIONS EARLY IN THIS

PROCESS.

5.4. Any changes to the drawings, specifications, etc. will be issued in the form of an amendment.

However, any answers that clarify or provide an interpretation to the drawings, specifications, etc. will NOT be posted via amendment but rather as a response to the RFI on FBO at https://beta.sam.gov/

5.5. Receipt by the offeror must be acknowledged in the space provided on the SF 1442 or by returning a signed copy of the amendment by the time set for receipt of proposals. Explanations or instructions given in a form other than an amendment to the solicitation shall not be binding.

Questions (on a non-attribution basis) and answers shall be furnished to all prospective offeror via the web site.

5.6. For security reasons, all technical and engineering data related to this solicitation will be distributed using the https://beta.sam.gov/ Contract Opportunities. Plans and specifications are locked on https://beta.sam.gov/ and require Contractors to request explicit access from the Contracting Officer OR export controlled access through DLA.

5.7. Amendments, if/when issued will be posted to https://beta.sam.gov/ for electronic downloading.

This will normally be the only method of distributing amendments prior to closing; therefore, it is the offerors responsibility to check the website periodically for any amendments to the solicitation. Websites are occasionally inaccessible due to various reasons.

6. Bid Repository and Bid Opening

6.1. A bid repository is provided for hand carried proposals and is located at Building 700 Base Civil Engineering, 5401 East Lake Boulevard, Birmingham, Alabama 35217-3545. Hand carried proposals must be deposited in the repository prior to the time established for receipt of proposals. Bidders are cautioned that they will be required to sign-in and obtain a visitor’s pass to enter the facility and should allow time to accomplish this. See instructions for obtain access to the base in the Site Visit instruction. Follow the same instruction for obtaining entry to hand carry bid. Late receipt of bids due to entry delays may not be deemed excusable and the Contracting Officer may declare the bid “late” in accordance with FAR 14.304.

6.2..The bid opening will occur at the time and date specified in Block 13 of the SF1442 at Building 700 – Civil Engineering Building 5401 East Lake Blvd, Birmingham Al All interested offerors and their major subcontractors are encouraged to attend the bid opening.

7. Wage Determination:

7.1. Davis Bacon Wage Rates are applicable to this project. Current prevailing wage determination(s) at time of issuance of solicitation are AL20200087 01/03/2020.

7.2. In the event the current prevailing Wage Determination is changed by the Department of Labor prior to the closing date of this solicitation, it is the offerors’ responsibility to insure the most recent determination is used in preparing the proposal. An Amendment will not be issued prior to closing to change Wage Determination dates and/or numbers. Should the wage rate change after closing, but prior to award, the updated Wage Determination will be incorporated by amendment and issued to all offerors’ that have not been eliminated from the competition. If applicable, these offerors’/contractors will be given a reasonable opportunity to provide revised proposals solely to amend proposals due to Wage Determination changes. If the wage determination modification does not change any affected wage rates, then the provisions of FAR 22.404-5(c) (4) will apply.

7.3. Applicable wage rates can be found at https://wdolhome.sam.gov/

8. Bid Preparation Expenses and Pre-Contract Costs:

This IFB does not commit the Government to pay costs incurred in preparation and submission of initial and subsequent proposals or for other costs incurred prior to award of a formal contract.

9. Clauses:

9.1. Clauses and provisions from the Federal Acquisition Regulation (FAR) and supplements thereto are incorporated in this document by reference and in full text. Those incorporated by reference have the same force and effect as if they were given in full text.

10. Disposition of Unsuccessful Bids: In compliance with FAR Subpart 4.8, the Government will retain one copy of all unsuccessful proposals including the bid bond.

11. Offerors Qualifications: To establish its responsibility, the apparent low bidder may be requested by the Government prior to award, to submit a statement regarding previous experience in performing comparable work, business and technical organization, financial and bonding resources and plant available to be used in performing the work. This action may be requested to determine if the contractor is responsible.

12. Reserved

13. Reserved

END SECTION 00100

SECTION 00700 - CONTRACT CLAUSES

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 30 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 585 days from the Notice to Proceed. The time stated for completion shall include final cleanup of the premises.

(End of clause)

(End of Summary of Changes)