Questions & Answers
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment_02_Wage_Determination.pdf | ||
| Amendment_0003.pdf | ||
| Question_and_Answers.pdf | ||
| Amendment_0002.pdf | ||
| Amendment_0001.pdf | ||
| Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Comment / Question Technical Answer/Remarks
The SF1442 nor Amendment 0001 provide a bid due date/time. Can you provide?
The response date for this solicitation is 16 Apr 2018 @ 2:00PM EST. You can find this information in section 13 of solicitation or by searching for W25G1V-18-R-0007 on fbo.gov and looking on the right side of the notice under General Information.
The SF1442 states that a bid bond is required; however, the solicitation docs do not provide specifics as to how much the bid bond should be for (i.e. 20% of price, etc.). Can you clarify?
Section 13 B. of the solicitation stated that an offer guarantee was required. Amendment 0002 corrects this error to read that an offer guarantee is not required.
3 What is the Manufacturer, Material, Color, Model and Gauge of the Metal Panels on: a. Roof Panels? b. Mansard panels? c. Gabel Ends?
The Depot has various panels, styles and manufacturers installed on its buildings. The standard color is Dark Bronze, .040 Aluminum in a 12” width. Price quote using Petersen Aluminum Corporation, Snap-Clad Panel with stiffener beads.
Pricing for this item is #49 on Price Schedule.
TPO Roof on Barracks: Do we need to provide repair material unit priced for TPO? Not listed in RFP.
The Barracks roof is an EPDM roof which has been coated with Acrymax coating. As of present, there are no TPO roofs on the Depot.
5 Are Agricultural Roof Panels on storage garages/sheds in need of quotation? Not listed on RFP.
No
What is security protocol for getting on roofs in an emergency situation? Is it possible that emergency call will be dispatched and techs will not be allowed on roof?
All workers will need a background check done before they will be permitted on the Depot. The check is good for 2 years. In the event of an emergency, we will make every effort to get in touch with Security to allow the contractors access to the building with the Emergency. If you are called, we probably already alerted Security of the situation.
7 What size retrofit drains need to be quoted? Item #19 4"
8 Do we need to provide quote for metal panel fasteners?
Not at this time. If fasteners are needed, a quote from the supplier will be necessary to verify and agree on the cost.
9 Do we need to provide quote for gutter hangers?
Not at this time. If gutter hangers are needed, a quote from the supplier will be necessary to verify and agree on the cost.
Noticed some lifting 3-tab shingles. Is this item required to be priced separately from architectural shingles? Not at this time. If 3 tab shingles are needed, a quote from the supplier will be necessary to verify and agree on the cost difference.
11 Gauge Required for Stainless Cap? Item #21 26 ga
Technical Comments and Questions for Solicitation W25G1V-18-R-0007
12 Gauge Required for Aluminum 12” Flashing? Is this for standard coil stock? Item #27 .019 Painted
Gauge Required for Galvanized Gutters and Downspouts? (Warehouses) Item #33 CHANGE 6" Painted Galvanized Gutter to 6"x6" Commercial Box Aluminum Gutter .050 Item #34 CHANGE 3"x5" Galvanized Downspout to 3"x5" Aluminum Downspout .040
Gauge Required for Aluminum Gutters and Downspouts? (Residential Areas) Item
#31 Gutters .032 Item #32 Downspouts .019
Do we need to provide sky track and scissor lift as needed? What is protocol for getting lift delivered on site?
Yes. The contractor, COR or supplier should notify Security that a lift will be delivered. It may require being searched at the main entrance area before being allowed on the Depot.
16 What size scissor lift? Most buildings are under 30' from ground level to gutter.
17 4” PVC for Downspouts. Is this Schedule 40? Yes
18 Are rates Prevailing Wage? Yes, rates are prevailing wage per Wage Determination incorporated into this solicitation on page 35 of the solicitation.
19 What is the procedure for obtaining vehicle pass? Are we able to have multiple vehicles on site?
See solicitation, page 11, 4. Security Requirements Multiple vehicles are allowed on site.
060 EPDM – Is the EPDM mechanically fastened or fully adhered? Both methods are utilized on the Depot and will be determined at the time of repair on which would work best. Any materials not on price schedule will require a quote from the supplier to verify and agree on the cost.
21 Edging 24 Gauge Kynar – Please provide profile style, size of face and manufacturer.
Item #11 Gravel stop edging with 5" face, Carlisle
22 12” Aluminum Flashing – Is this standard color? Please provide gauge? Item #27 Yes, standard colors. .019
23 Aluminum K-gutter – Please provide gauge? Item #31 .032
24 2’ x 3’ Aluminum Downspout – Please provide gauge? Item #32 .019
25 Skytrack/Scissor Lift- - Who is providing the lift equipment for the 4 year contract term, Contractor or TYAD?
Items #43 & 44 The contractor supplies all lifts.
As this is an “on-call” project, it may require either one or both lifts, at any time, any size, for an undetermined amount of time. How is the contractor to provide and bill for an hourly rate?
Items #43 & 44 The Government will make every effort to schedule repair work to all areas requiring the use of a lift so the lift can be rented for an extended period of time.
The Government will attempt to provide work to utilize the rental in 1 month increments.
27 If contractor is to provide equipment, will TYAD provide on-site storage for entire contract term?
The Government will supply an on-site area for storage of material.
The contractor must supply their own trailer.
We have recently received price increase announcements from our suppliers, who will be implementing significant price increases across all roofing materials, accessories, and all steel and aluminum products. These increases range from 5 to 25 %. Due to the volatility of material pricing, please explain if and how the 4 year firm fixed-price, can be adjusted to compensate the contractor for these additional costs? How do we address this? Is there a chance for economic adjustments?
As with any contract, it is impossible to predict future increases in material pricing. Every Firm Fixed Price contract comes with a degree of liability on the Contractor's behalf. Costs can increase or decrease over a projects period of performance. As stated in the pricing schedule, price will be forecasted for the base and each option period. It is the Contractor's duty to price these periods as practically as possible based on market knowledge and expectations. There will be no economic adjustments based on market conditions.
29 #21 Please provide profile style, size of face and gauge.
See ITEM # 21 (Description change) Total dimensions of the stainless steel Coping Cap is 20" girth with a thickness similar to 26 Ga
Page 58 of 73 of the Solicitation under section"K" incorporates FAR Clause 52.222-33 Notice of Requirement for Project Labor Agreement, by reference.
Please confirm that FAR Clause 52.222-33is indeed incorporated into this solicitation.
FAR Clause 52.222-33 has been removed from this solicitation
I don't see a unit price for standing seam/metal roof panels. At the pre-bid it was evident that there are damaged metal roof panels but there is not unit price to fix them.
See item #49 & Question #3 (above).
For the "Net Amount" under Item #1 on page 4of the Solicitation - is this simply just the sum of all of the unit prices? Or are we to make assumptions on expected quantities of each unit price for the year?
The "Net AMT" sections on pages 4-6 of the solicitation are not to be completed by prospective bidders. Bidders will complete the "Roof Repair Price Schedule" beginning on page 7. Each item must be priced for base & option years. The cumulative totals for each item will be added together to determine lowest cost to the Government.
This, along with responsibility determinations, will determine the successful awardee. All costs associated with this contract must be included in the price schedule. No other costs shall be invoiced.
Any metal products will likely increase 15-25% in the near future due to tariff increases. Is there any relief available either in the content of the contract, or by future negotiation?
See #28 above
34 I am a Vietnam veteran. Is there a veteran set-aside available?
The Contracting Officer has determined this to be a Small Business Set Aside. Also, there are no set asides in Department of Defense (DoD) for Veteran Owned Small Business. For more information regarding set asides, please contact David Kern @ 570-615-8733.
35 Should these material prices include sales tax? Yes, material prices must include sales tax.