QtAs - W15QKN-24-R-5017.docx

DOCX document 17 KB Posted

Attached to
CONSTRUCTION - Multiple Projects - Londonderry, NH & Keene, NH Federal contract opportunity
Solicitation number
W15QKN-24-R-5017
Issued by
Department of the Army Materiel Command Contracting Command Picatinny Arsenal

About this file

This document contains a federal contract solicitation and related questions and answers file. The solicitation seeks fixed-price construction services for three small business set-aside projects located in Londonderry and Keene, New Hampshire. The projects include repairing a parking lot and road at the Londonderry Armed Forces Reserve Center, repairing fencing and removing trees at the Keene Armed Forces Reserve Center, and repairing bay doors at facilities in Londonderry, New Hampshire and Auburn, Maine. Site visits are scheduled and questions must be submitted by March 4th, 2024. The period of performance will be staggered based on award date. The United States Army Contracting Command - New Jersey Warfighter Support Division is acting on behalf of the 99th Readiness Division.

View the file

Other files for this federal contract opportunity

Other files attached to CONSTRUCTION - Multiple Projects - Londonderry, NH & Keene, NH, newest first.
File Type Posted
W15QKN-24-R-5017_0004.pdf PDF
QtAs (Rev. 1) - W15QKN-24-R-5017.docx DOCX document
QtAs - W15QKN-24-R-5017.docx DOCX document
W15QKN-24-R-5017_0003.pdf PDF
NH004-Keene-A3-CSS-92935-SOW-Repair Fence-Remove Trees.docx DOCX document
ME001 DOOR PLAN.pdf PDF
W15QKN-24-R-5017_0002.pdf PDF
NH014-Londonderry-A3-CSS-94632- OA6.2 OMS Door Det AB -Repair AMSA Bay Doors (1).PDF PDF
NH014 OA6.1 OMS Door Sch AB all door size.PDF PDF
W15QKN-24-R-5017_0001.pdf PDF
SF1413 Statement of Acknowledgement.pdf PDF
Contractor Cost Breakdown Form (NOV 2022).xlsx XLSX spreadsheet
NH014-Londonderry-A3-CSS-94632-SOW-Repair AMSA Bay Doors V5.docx DOCX document
NH004-Keene-A3-CSS-92935 Picture-Repair Fence- Remove Trees.jpg JPG image
DBA NH20240022 (Mod. 0) 1-5-2024.pdf PDF
NH004 09-017 Keen-Boundary Survey_May2009 Annotated.pdf PDF
DBA NH20240020 (Mod. 0) 1-5-2024.pdf PDF
DBA ME20240015 (Mod. 0) 1-5-2024.pdf PDF
NH004-Keene-A3-CSS-92935-SOW-Repair Fence-Remove Trees.docx DOCX document
NH014-Londonderry_A3_CSS-88245-ARM GATE PICTURES.pdf PDF
NH014-Londonderry-A3-CSS-88245- SOW-Repair Parking lots and Roads.docx DOCX document
W15QKN-24-R-5017.pdf PDF
Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions & Answers

W15QKN-24-R-5017

March 5, 2024

CSS 92935

Q1: Can you please let us know the Wage rate of Tree cutting laborer/Landscaper ?

A1: All Wage Rates are within the applicable Wage Determinations. Wage Determinations are the three (3) attachments starting with the title “DBA…”.

Q2: Can you please let us know the height of the black vinyl coated fabric to install of 135ft ?

A2: The fence is 6 feet tall with a 1 foot barbed wire topper. Fence fabric is only to be replaced if damaged during tree removal. 9 gauge vinyl coated wire tires are required along the entire fence line, at rails and posts, not replacing fabric.

Q3: Can you please send us the picture for Overhead doors and Door C & D?

A3: This exhibit is already attached to the Solicitation, entitled “ME001 DOOR PLAN”.

CSS 94632

Q4: Are they ¼” steel guides or ½” guides?

A5: ¼” steel.

Q5: Will the seals be required on the inside or outside or both?

A5: Outside.

Q6: Is there an aluminum retainer needed for the seals or all in one standard seal?

A6: Standard all in one.

Q7: Is it a brush seal or rubber flap and what color.

A7: Brush seal (black)

Q8: Is the bottom just a bulb rubber or is it a sensing edge or pneumatic edge?

A8: They are pneumatic sensing edges for safety.

Q9: On page 5 of the solicitation, paragraph (e), It states, “Bid Guarantee IAW FAR 52.228-1, must be submitted with your proposal submission to be eligible for award. Failure to provide a bid guarantee will render your proposal unacceptable.”

How do you want the bid bonds for the 3 separate tasks. Do you want a bid guarantee for each individual task or all three added together?

A9: Please provide separate bonds for each individual project.