This document contains a question and answer regarding inspection requirements for a federal solicitation. The solicitation seeks production of Standoff Activated Volcano Obstacle plastic parts for experiment and test purposes. The solicitation number is W15QKN20Q0031 and has been 100% set aside for small businesses under NAICS code 333511 with a size standard of 500 employees. The government will evaluate deliverables based on the Quality Assurance Plan issued in Amendment 0001, which specifies inspection of all deliverables. Additionally, the government will inspect two quantities per part for specific dimensions and tolerances listed in the provided technical drawings. Notification of First Article Inspection by the contractor shall be no less than 14 days prior. The required plastic parts will be manufactured, inspected, and delivered in accordance with government Technical Data Packages and contract requirements.

View the file

Other files for this federal contract opportunity

Other files attached to Standoff Activated Volcano Obstacle, newest first.
File Type Posted
W15QKN20Q0031_0003.pdf PDF
Question and Answer dated 05-11-2020.docx DOCX document
W15QKN20Q0031_0002.pdf PDF
Questions and Answers dated 04 May 2020.docx DOCX document
W15QKN20Q0031 Amendment 0001.pdf PDF
Past Performance Questionnaire.docx DOCX document
DD_2345_FORM.pdf PDF
Attachment 0002 CDRL_A002- CERTIFICATION_DATA REPORT.pdf PDF
Attachment 0005 - US_Government_NDA.doc DOC document
W15QKN20Q0031.pdf PDF
Attachment 0004 - CERTIFICATE_OF_DESTRUCTION.DOC DOC document
Attachment 0001 CDRL_A001- PARTS_MATERIALS AND PROCESS SELECTION LIST.pdf PDF
Attachment 0003 Section J Attachment - Contract Quality Requirements.docx DOCX document
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question: There seems to be an inconsistency regarding inspection requirements from last Q&A:

"This contact does not include a Physical Configuration Audit (PCA) clause. That would be our process where a small sample of parts would be 100% inspected against all features of the drawing. What we did call out are the characteristics listed in the QAP. These callouts are attached to MIL-STD-1916 Verification Levels which dictate that 1 in every X parts will have this feature examined. Because we are buying such a small quantity of parts this factor becomes 1 in every 1 part will have this feature examined. This means that we have 100% of parts for this order being examined for each major and minor characteristic. We are examining every part, but not every feature of every drawing."

Solicitation:

9. First Article Inspection: CCDC Armament will be inspecting 2 quantity per part for the dimensions and tolerances listed in drawing 19200_13095276, 19200_13095280, 19200_13095283, and 19200_13095293. Notification of FAI date by the contractor shall be no less than 14 days prior.

Answer: Government will evaluate based on the QAP issued with the amendment 0001 which is the inspection for all deliverables. Paragraph 9. First Article Inspection is only pertaining to First Article testing.