Attachment 0018 Questions and Answer regarding inspection.docx
DOCX document 12 KB Posted
- Attached to
- Standoff Activated Volcano Obstacle Federal contract opportunity
- Solicitation number
- W15QKN20Q0031
About this file
This document contains a question and answer regarding inspection requirements for a federal solicitation. The solicitation seeks production of Standoff Activated Volcano Obstacle plastic parts for experiment and test purposes. The solicitation number is W15QKN20Q0031 and has been 100% set aside for small businesses under NAICS code 333511 with a size standard of 500 employees. The government will evaluate deliverables based on the Quality Assurance Plan issued in Amendment 0001, which specifies inspection of all deliverables. Additionally, the government will inspect two quantities per part for specific dimensions and tolerances listed in the provided technical drawings. Notification of First Article Inspection by the contractor shall be no less than 14 days prior. The required plastic parts will be manufactured, inspected, and delivered in accordance with government Technical Data Packages and contract requirements.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W15QKN20Q0031_0003.pdf | ||
| Question and Answer dated 05-11-2020.docx | DOCX document | |
| W15QKN20Q0031_0002.pdf | ||
| Questions and Answers dated 04 May 2020.docx | DOCX document | |
| W15QKN20Q0031 Amendment 0001.pdf | ||
| Past Performance Questionnaire.docx | DOCX document | |
| DD_2345_FORM.pdf | ||
| Attachment 0002 CDRL_A002- CERTIFICATION_DATA REPORT.pdf | ||
| Attachment 0005 - US_Government_NDA.doc | DOC document | |
| W15QKN20Q0031.pdf | ||
| Attachment 0004 - CERTIFICATE_OF_DESTRUCTION.DOC | DOC document | |
| Attachment 0001 CDRL_A001- PARTS_MATERIALS AND PROCESS SELECTION LIST.pdf | ||
| Attachment 0003 Section J Attachment - Contract Quality Requirements.docx | DOCX document |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question: There seems to be an inconsistency regarding inspection requirements from last Q&A:
"This contact does not include a Physical Configuration Audit (PCA) clause. That would be our process where a small sample of parts would be 100% inspected against all features of the drawing. What we did call out are the characteristics listed in the QAP. These callouts are attached to MIL-STD-1916 Verification Levels which dictate that 1 in every X parts will have this feature examined. Because we are buying such a small quantity of parts this factor becomes 1 in every 1 part will have this feature examined. This means that we have 100% of parts for this order being examined for each major and minor characteristic. We are examining every part, but not every feature of every drawing."
Solicitation:
9. First Article Inspection: CCDC Armament will be inspecting 2 quantity per part for the dimensions and tolerances listed in drawing 19200_13095276, 19200_13095280, 19200_13095283, and 19200_13095293. Notification of FAI date by the contractor shall be no less than 14 days prior.
Answer: Government will evaluate based on the QAP issued with the amendment 0001 which is the inspection for all deliverables. Paragraph 9. First Article Inspection is only pertaining to First Article testing.