This document contains industry questions and government responses regarding Solicitation Number W15QKN18R0004 for Armor Hardware, Turret Systems, and Platform Integration Kits. The solicitation requests proposals for hardware kits to support integration of crew served weapons on vehicle platforms, including Gunner Protection Panels and Kits, turret systems, and Platform Integration Kits. The government intends to make up to three awards for ordering periods of five years each. Technical Data Packages are provided for Objective Gunner Protection Kits, Combat Vehicle Turret Assembly, and Vehicle Integration Kits. Production rates required are up to 50 kits per month for each configuration, with the ability to ramp up to 300 kits per month within six months. Questions from industry are addressed relating to missing drawings, specifications, and eligibility requirements.

Attachment 0013 INDUSTRY QUESTIONS AND GOVERNMENT RESPONSES #2

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 0013: Industry Questions and Government Responses #2 Solicitation W15QKN-18-R-0004 Armor Hardware, Turret Systems, and Platform Integration Kits 12/18/17

1) Please advise if the print “RIA 154809 – cover, access gasket” is available.

It is already provided with the TDP. RIA 154909.

2) Requesting the missing drawings and information to be provided to for Solicitation W15QKN-18-R-0004.

ITEM
DESCRIPTION
QUESTION
13054025
PLATE, SHIELD
Drawing Note 2 states “MATERIAL - STEEL AIW ASTM B555” ASTM-B555 is a coating spec.

What material specifications are required for this part?

13064366
INSTALLATION DOCUMENT ITDS READY
Will document be provided?
57K3214
PARTS KIT, MIRROR ASSEMBLY, REARVIEW
Kit number is supplied, no drawings or parts list
12342130
MIRROR ASSEMBLY, RIGHT HAND
Drawing not in drawing package (listed on drawing 57K3214)
12343061
MIRROR ASSEMBLY, LEFT HAND
Drawing not in drawing package (listed on drawing 57K3214)
12446871-1
INSERT
Drawing not in drawing package (listed on drawing 57K3214)
12460113
INSTALLATION DRAWING
Drawing not in drawing package (listed on drawing 57K3214)
12460114
INSTALLATION INSTRUCTIONS
Drawing not in drawing package (listed on drawing 57K3214)

See Attachment 0010 responses posted. This question was covered under that previous amendment.

3) For the purposes of the proposal what should be used as the shipping destination for kit delivery? Section B does not include this information and nor does Section J Exhibit B.

See Answer 57 on Attachment 0010 responses posted.

4) We are interested in supporting this opportunity and we have reviewed the latest information. I have a couple questions pertaining to our prior government contracts that may support this contract but they are beyond the 3 year threshold. We do have a couple current contracts as a subcontractor. Am I able to briefly discuss this requirement with you or the contracts officer so we can determine our eligibility? We are interested in supporting this opportunity and we have reviewed the latest information. We have a very long history in supporting large, multi-year defense contracts; however prior to sequester we opted to take a tactical pause in defense contracting to focus our commercial partners and wait out the turbulent sequester storm. Currently we are back in the government business and have secured a couple contracts as a subcontractor and we have current commercial products in production that are equivalent regarding complexity etc. Our concern is, given the gap (3yrs plus) between our government contracts, are we still eligible to compete in this opportunity?

As instructed in Section L.4.2.2 of the Solicitation, “Offerors shall submit a list of all recent Government contracts (prime and major subcontracts) in performance or awarded to the Offeror and any of its major subcontractors within the past three(3) years, or awarded earlier than three (3) years ago, but for which deliveries/performance occurred or were scheduled to occur within the past three (3) years, which are relevant to the effort required by the solicitation.” Submit Past Performance information for Government contracts in which your company was a prime or subcontractor for contracts awarded within the past three (3) years or for contracts in which deliveries/performance occurred or were scheduled to occur within the past three (3) years. Past Performance information for major subcontractors can also be submitted for contracts awarded within the past three (3) years or for contracts in which deliveries/performance occurred or were scheduled to occur within the past three (3) years.

5) Any word on an extension on this RFQ?

Amendment 0001 to Solicitation W15QKN-18-R-0004 posted 07 DEC 2017 on Fed Biz Opps amends the Proposal Due Date from 03 January 2018 to 19 January 2018.

6) We still need 13043109 which is a color table for paint specification that is not listed below.

See Attachment 0010 responses posted. 13043109 is already included in the TDP provided.

7) We were informed we needed to resubmit the attached documentation in order to receive some of the missing prints from the TDPs on solicitation W15QKN-18-R-0004. Please let me know if you require any further documents.

The AMSTA-AR Form 1350 Technical Data Request Questionnaire, DD 2345 - Militarily Critical Technical Data Agreement, and Non-Disclosure and Non-Use Agreement submitted for the OBJECTIVE GUNNER PROTECTION KITS, COMBAT VEHICLE TURRET ASSEMBLY, and VEHICLE INTEGRATION KITS Technical Data Packages is sufficient. New forms are not required to be submitted for the AHTS PIKs missing drawings.

8) I’m following up on the missing drawings (Attachment 11). Per the amendment, it asks we submit the DD2345, Form 1350, and NDA again. Do we need to do this again even if we’ve already submitted them previously? Thanks!

The AMSTA-AR Form 1350 Technical Data Request Questionnaire, DD 2345 - Militarily Critical Technical Data Agreement, and Non-Disclosure and Non-Use Agreement submitted for the OBJECTIVE GUNNER PROTECTION KITS, COMBAT VEHICLE TURRET ASSEMBLY, and VEHICLE INTEGRATION KITS Technical Data Packages is sufficient. New forms are not required to be submitted for the AHTS PIKs missing drawings.

9) On the below solicitation, I was wondering if it is possible to bid just the transparent armor??

Proposals are requested of all items in the solicitation.

10) We had no questions and were on track to submit a compliant proposal by 1/3/18. I'm curious as to why an extension was granted. In our view there was sufficient information provided in the solicitation and TDPs to complete pricing and submit a complaint proposal.

The proposal due date was extended to allow industry time to review the AHTS PIKs drawings that were missing from the Technical Data Packages when the Solicitation was issued.

11) We also found the following drawings are missing from the O-GPK technical data package (13063370):

DocumentNomenclatureDrawings Used On
12369857ZINC-NICKEL COAT12367450
12465333ITEM IDENTIFICATION13064348 thru 13064354
12512498CONTROL BOX ASSEMBLY13064367
13039369ADHESIVE13063370 and 13042522

The following drawing was missing from the TURRET technical data package

(RIA154925)

Document Nomenclature Drawings Used On

RIA155939 (OR 6505597) ADHESIVE BACKED CLOSED CELL FOAM RIA154920,

RIA154904,

RIA154921

There no additional drawings available on the TDPs. Please use appropriate commercial standards or specifications for coatings, adhesives or foams when specified drawing is not available.