0011155352-0001 CSS 6292
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
- Extend the response date and time from 29 June 2018,12:00 PM to 10 July 2018, 12:00 PM.
- Revise Instructions to Offerors, Paragraphs 5 - 8 and Paragraph II.2.A. and B. Basis for Aw ard/ Evaluation Criteria
- Incorporate revised Scope of Work and revised draw ings
1. CONTRACT ID CODE PAGE OF PAGES
J 1 37
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 28-Jun-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W15QKN18Q1070
X 9B. DATED (SEE ITEM 11)
24-May-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
28-Jun-2018
CODE
US ARMY CONTRACTING COMMAND
5418 S. SCOTT PLAZA
JOINT BASE MDL NJ 08640
W15QKN 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W15QKN18Q1070
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 29-Jun-2018 12:00 PM to 10-Jul-2018 12:00 PM.
SECTION 00 20 00 - INSTRUCTIONS FOR PROCUREMENT
The following have been modified:
INSTRUCT TO OFFERORS/BASIS AWD
I. INSTRUCTIONS TO OFFEROR
1. The United States Army Contracting Command – New Jersey (ACC-NJ) has a requirement in support of the 99th
Regional Support Command (RSC) Directorate of Public Work located at the at the CW2 Kerry P. Hein USARC, 200 Route 25A, Shoreham, New York. The work shall include, but not limited to, repair and replacement of fuel tanks. The contractor shall provide all plant, labor, equipment, tools, materials, technical support, supervision and transportation to accomplish all work in accordance with the Scope of Work (SOW). The North American Industry
Classification System (NAICS) code that applies to the principal nature of the acquisition is 237120, Oil and Gas
Pipeline and Related Structures Construction
2. Contractor must be registered in System for Award Management (SAM) to be considered for award. To obtain information on SAM or to register with SAM visit the web site at: https://www.sam.gov.
3. A site visit is HIGHLY ENCOURAGED. A primary site visit will be held on Wednesday, May 30, 2018 at
09:00AM EST and an alternate site visit will be held on Thursday, May 31, 2018 at 09:00AM EST. Attendees shall meet at 200 Route 25A Shoreham NY 11786 and must call Bob Bennett at 646-996-8561 for gate entry. Only one site visit is required on either one of the provided dates. The site visit shall be coordinated with the Regional
Facility Operation Specialist (RFOS), Greg Malanuk at gregory.t.malanuk.civ@mail.mil and copy Contract
Specialist, Deborah E. Terrell at deborah.e.terrell.civ@mail.mil.
4. Questions shall be emailed to the Contract Specialist, Deborah E. Terrell at deborah.e.terrell.civ@mail.mil and the Contracting Officer, Lorraine Carruba at lorraine.m.carruba.civ@mail.mil no later than 4 June 2018, 1:00PM
EST. Questions must specify the section or paragraph of the Request for Quote (RFQ) for which the clarification is desired.
5. Contractor offers shall be submitted via email to the Contract Specialist at deborah.e.terrell.civ@mail.mil and the
Contracting Officer at lorraine.m.carruba.civ@mail.mil and shall include:
- Technical: Itemized breakdown of materials (description and quantities) and labor mix (labor classification and number of hours) to determine technical acceptability. (See attached Sample
Construction Itemization Template)
- Pricing:
a. Pricing for all Contract Line Item Numbers (CLINs). A total price should also be included.
b. CAGE Code, DUNS Number, and business-size standard under the applicable NAICS of 237120.
https://www.sam.gov/ mailto:gregory.t.malanuk.civ@mail.mil mailto:deborah.e.terrell.civ@mail.mil mailto:deborah.e.terrell.civ@mail.mil mailto:lorraine.m.carruba.civ@mail.mil mailto:lorraine.m.carruba.civ@mail.mil
c. Complete blocks 14, 15, 17, 19 and 20 of the SF1442 as well as signing/acknowledging any amendments. In doing so, the offeror accedes to the contract terms and conditions as written in the Request for Quote.
d. Copy of insurance certificate meeting minimum requirements identified in Federal Acquisition
Regulation Subpart 28.307-2
6. All offers shall remain valid for 120 calendar days
7. Multiple offers will not be accepted.
8. The following paragraphs under FAR clause 52.212-1 are not applicable to this RFQ: (d) Product Samples and
(e) Multiple Offers.
II. BASIS FOR AWARD / EVALUATION CRITERIA
1. The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered.
The basis for award of any contract resulting from this solicitation will be the result of the evaluation of the Factors specified utilizing the Lowest Price Technically Acceptable Source Selection methodology. The Government intends to award a single Firm Fixed Price (FFP) contract.
2. The Government intends to award a contract without discussions with respective offerors, so offerors should submit their best offer initially. The Government, however, reserves the right to conduct discussions if deemed in its best interest.
3. Award shall be made to a single contractor. Award will be made to the lowest priced technically acceptable, responsible offeror that meets the requirements of the Scope of Work/attachments and this solicitation.
A. TECHNICAL: Ability to meet the requirements of the Scope of Work and solicitation based on the itemized breakdown of materials (description and quantities) and labor mix (labor classification and number of hours) submitted.
B. PRICE:
1. Proposals will include prices for each line item listed and a total price, in order that proposals may be properly evaluated; completed SF1442 and any amendments; insurance certificate IAW FAR Subpart 28.307-2.
2. The Government will evaluate offers for award purposes by adding the total price for all Contract Line Item
Numbers (CLIN) for the total evaluated price. In the event there is a difference between a unit price and the total
CLIN amount, the unit price will be held as the intended price multiplied by the number of units. If the offeror shows only the total amount but fails to submit a unit price, the total CLIN amount divided by the quantity will be held as the intended price.
C. The Past Performance Information Retrieval System and Federal Awardee Performance & Integrity Information
Systems as well any other Government-sponsored information available may be utilized to help make a responsibility determination in accordance with FAR Subpart 9.104.
D. Failure to provide the requested information may deem the proposal Unacceptable and may not be eligible for award.
E. The Government will begin the evaluation process with a ranking based on the Total Evaluated Price from the lowest to highest price. Following the price ranking, only the lowest priced offeror(s) will be evaluated for technical acceptability under the non-price factor(s) according to the evaluation criteria set forth in paragraph 3 of this section.
If acceptable, the evaluation will stop at that point and award will be made to the lowest priced technically acceptable offeror. If unacceptable, the Government will continue to review proposals in order of price until evaluating one that is technically acceptable and eligible for award. The Government reserves the right to conduct additional technical evaluations as deemed necessary.
SECTION 00 70 00 - CONDITIONS OF THE CONTRACT
252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)
(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.
(b) The Contractor shall--
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
(3) Promptly notify the Contracting Officer of any discrepancies;
(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and
(5) Reproduce and print contract drawings and specifications as needed.
(c) In general--
(1) Large-scale drawings shall govern small-scale drawings; and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:
Title File Drawing No.
1. NY058-DWG Typical Tank Details - Marked 6-26-2018
2. NY058-DWG - C102 Overall Site Plan - Markup 6-26-2018
3. NY058-Mechanical (tank) Details M518-Plans -Marked 6-26-2018
4. NY058-2000gAST-DWG-Apb610- Marked 6-26-2018
5. NY058-2000gAST-SPECs- Marked 6-26-2018
6. NY058-6000gAST-DWG-Apb660 - Marked 6-26-2018
7. NY058-6000gAST-SPECs- Marked 6-26-2018
8/ NY058-10000gAST-DWG-Apb680 - Marked 6-26-2018
9. NY058-10000gAST-SPECs- Marked 6-26-2018
(End of clause)
SECTION 01 00 00 - GENERAL REQUIREMENTS
SCOPE OF WORK
SCOPE OF WORK
99th Readiness Division Directorate of Public Works
Fort Dix, New Jersey 08640
June 26, 2018
Project Name: CW2 KERRY P. HEIN USARC Project Number: NY058 CSS 6292
Project Location: 200 Route 25A
Shoreham, NJ 11786-2104
Project POC: PRI: RFOS/QAR: Gregory Malanuk Wrk (718) 631-6188 Cell (347) 219-9596
Project POC/ALT: AFOS: Robert Bennett Wrk Cell (646) 996-8561
Project POC/ALT: REPS: Blayre Linker Wrk (718) 631-6186 Cell (516) 732-1821
HQ Eng Tech: Rich Heagler Wrk (609) 562-7644 Cell (732) 715-2216
1. GENERAL CONTRACTOR:
1.1. Shall furnish all plant, labor, equipment, materials, transportation, supervision and technical expertise to perform requirements in accordance with the specifications and allotted period of performance described in this Scope of Work (SOW).
1.1.1. Shall provide their own storage shed or trailer for on-site office accommodations and for storing of equipment and material. The “On-Site Government Quality Assurance
Representative” (QAR) will assign the contractor a location for placement of their shed or trailer upon request.
1.2. Is obligated to verify all measurements and specification requirements at the on-site visit prior to starting the project. No extra compensation shall be allowed for the contractor who does not attend the on-site visit and who does not appreciate the difficulty of the contract specifications. Any discrepancies, ambiguities or changes must be verified and confirmed in writing to the Contracting Officer, Contracting Officer Representative (COR), and QAR.
1.3. Shall furnish all submittals for equipment and/or materials that vary from requirements of this SOW. All submittals are required to be turned in and approved by the QAR 30 days prior to ordering any of those materials.
1.3.1. Shall provide, unless otherwise specified, new and unused materials and/or installed equipment in the original manufacturer’s packaging. All materials stored on the job site are subject to inspection by the QAR and must be protected from the elements at all times.
1.4. Shall not perform any portion of this contract without notice to proceed. Shall not commence work prior to the Government COR/QAR pre-construction meeting. Shall notify the
COR/QAR a minimum of 72 hours prior to commencing work and prior to completing work on this contract.
1.5. Shall submit, prior to commencing any work: A current Certificate of Insurance (Prime and
Subs); a letter appointing a construction superintendent; a schedule of operations. The construction schedule shall be subject to change so Contractor’s operations do not conflict or otherwise disrupt normal operations of the government in the facility involved.
1.6. Shall perform the work between the hours of 0730 and 1600 (7:30 AM – 4:00 PM), Monday through Friday (unless otherwise specified), excluding legal holidays. NO EXCEPTIONS, any work on military training/drill weekends or federal holidays must have prior written coordination and approval between the Contractor, Project POC (Primary or Alternate), and the Facility
Manager.
1.6.1. Shall submit on company letterhead to the QAR an “Entry Authorization Letter” registering all motor vehicles and driver/operators information as required to access individual installations.
1.6.2. Shall ensure all motor vehicles, drivers and operators are qualified, licensed and insured.
1.7. Shall ensure compliance with all applicable Federal, State, and Local Municipal environmental regulations concerning the protection of land, water and resources. Shall apply most stringent regulation requirements to any ambiguities, deviations must be approved in writing by the Contracting Officer or COR. The types and quantities of all hazardous materials brought to the job site shall be reported to the facility/installation environmental officer.
1.8. Shall call/coordinate, prior to any excavation, with local municipalities and the facility utilities section to identify all underground utilities.
1.8.1. Prior to any underground excavation, the contractor shall call and obtain approval from the state in which the work is being performed.
1.8.2. A copy of the approval notification letter or valid authorization number must be available for inspection at the excavation site.
1.9. Shall be responsible for any damages caused by them or their subcontractors during the performance of this contract, and shall be required to reimburse the United States Government for the cost of any repairs resulting from those damages, or the Contractor/ Subcontractor shall make the necessary repairs to the satisfaction of the United States Government.
1.9.1. The contractor shall hold the Government harmless against any liability imposed by a
Federal, State, or Local regulatory agency, resulting from the negligent acts or willful misconduct of the contractor to include assessment of a civil or administrative penalty or fine.
1.10. Shall be solely responsible for ensuring compliance with the provisions of this contract by subcontractors. Shall ensure work be performed by workmen skilled in their particular trades, and certified as required by Federal, State and Local laws and/or codes
1.11. Shall be required to leave the job site in a safe and secure condition at the end of each workday. The contractor shall provide at his/her expense a Dumpster for all construction debris, dumping shall also be at contractor expense. The Contractor shall at no time use government dumpsters.
1.12. Shall clean the job site of all construction debris at the end of each working day. The daily clean up will not alleviate the Contractor from the responsibility of the final clean up for acceptance, upon completion of this contract. All debris removed from the job site shall be disposed of properly at an off post/facility landfill of the Contractor’s own choice and at the
Contractor’s expense. Upon request by the by the Contracting Officer or QAR, the Contractor shall provide the name, address, and location of the disposal site, and copies of any manifest from such disposals.
1.13. Shall ensure all work be completed in the negotiated time frame.
2. CONTRACTOR QUALITY CONTROL
2.1. The Contractor shall provide and maintain an effective quality control program that complies with the Contract Clause (FAR 52.246-12), the below stated quality control requirements and the quality control requirements stated in the respective section of the
Technical Specifications. Quality control personnel shall also be charged with the responsibility of policing Contractor’s Safety Program.
2.2. The Contractor shall establish a quality control system to perform sufficient inspection and testing of all items of work, including that of their subcontractors. The quality control system shall ensure conformance with applicable specifications and drawings with respect to materials, workmanship, construction, finish, functional performance, and identification.
2.3. The quality control system will be established for all construction except where the technical provisions of the contract provide for specific Government control by inspections, tests, or other means. The Contractor’s quality control system will specifically include the surveillance and tests required in the technical provisions of the contract specifications. For purposes of the above description, shop manufacture or standard products are not defined as construction.
2.3.1. The Contractor’s quality control system is the means by which they assure themselves their construction complies with the requirements of the contract plans and specifications. The controls shall be adequate to cover all construction operations, including both on and off-site fabrication.
2.3.2. The Contractor shall not build up or conceal any feature of the work containing uncorrected defects, and payment on deficient items will be withheld until they are satisfactorily corrected or other action has been taken as authorized pursuant to the Contract Clause entitled
“Inspection of Construction”.
2.3.3. The Contractor’s appointed job site supervisor may be used as the Quality Representative
(QR). When supplemented by special technicians or testing facilities to perform all specified tests, balancing, adjusting and/or regulating mechanical and electrical devices, equipment and/or systems it will be done in writing. As an option, an industry recognized testing laboratory approved by the Contracting Officer or COR may be used for said testing.
2.3.4. The contractor is responsible for maintaining an effective quality control system.
Recurring deficiencies indicate the system is not adequate and the contractor’s performance is failing to meet government’s minimum acceptable standards. If, in the opinion of the
Contracting Officer, an unacceptable number of deficiencies are occurring in the contractor’s performance, the Contracting Officer may direct the contractor to revise its operations to correct the defective performance. Failure by the contractor to provide acceptable revisions and/or to improve contract performance may result in the termination of the contract for default.
2.3.5. In the event the Contractor utilizes the service of a commercial testing laboratory, the
Contracting Officer reserves the right to check laboratory equipment for compliance with the standards set forth in the contract specifications and to check the laboratory technician’s testing procedures and techniques.
3. GOVERNMENT
3.1. The Government will provide, when available, electrical power, water and existing utilities at each building required in the performance of this contract at no cost to the Contractor.
Temporary extension of power and/or water lines, if necessary, shall be installed at the
Contractor’s expense.
3.1.1. Contractor owned construction sheds, trailers, offices or other such facilities requiring utility services shall be metered for each utility involved, and all costs involved up to the point of connection to Government owned utility systems shall be at the contractor’s expense. Final connection of Contractor supplied service laterals to existing Government owned utility systems will be made at the Contractor’s expense.
3.2. Contracting Officer or COR will schedule a pre-performance conference after contract award and prior to commencement of work. The Contracting Officer will notify the contractor of the time, date, and place set for the meeting, which will be held at a location to be designated by the Contracting Officer. At this meeting, the contractor will be oriented with respect to
Government procedures and lines of authority, as well as contractual, administrative, and construction matters. The contractor is required to furnish a current Certificate of
Insurance and a letter appointing a construction superintendent at the meeting.
3.2.1. Pre-Construction Conference: Topics will cover but are not limited to the following:
3.2.1.1. Introduction of Key players: COR/QAR, General Contractor, Job-site Supervisor, Sub-
Contractors and using agencies. Other personal that may be in attendance are Environmental, Police, Fire, Safety and Health services, in addition to Distinguished Visitors.
3.2.1.2. Scope of Work (SOW): Brief description of work, modifications to SOW, customer requests for additional work, unauthorized work, facility access and authorized personnel access.
3.2.1.3. Milestones: Period of performance, start date, schedule, phasing, completion date, work hours desired, weekend work schedule, scheduled outages/interruptions (power, water, roads, alarms, fire protection, HVAC).
3.2.1.4. Materials: Submittals, equipment, construction area, storage area, Government provided utilities, dumpster locations, Barriers (construction fence, silt fence, road blocks, access points to facilities, etc)
3.2.1.5. Administrative: Lines of authority, Wage rate/certified payrolls, Daily reports, Visitor control, Environmental requirements (hazards, dust and noise control), Safety meeting/concerns, Excavation permits, Fire (burn Permits), Police support, Payments, Liquidated Damages
3.2.2. Contracting Officer, COR and/or their QAR may inspect the work at any time during the contract period, and reserves the right to stop or terminate the contract if all work does not comply with the specifications provided by the manufactures recommendation of this SOW. The presence or absence of the Contracting Officer or QAR shall not relieve the Contractor from strict compliance with these plans and specifications.
3.3. Technical surveillance of workmanship and inspection of materials for work being performed under this contract shall be the responsibility of the QAR. This provision in no way authorizes anyone other than the Contracting Officer to commit the Government to changes in the terms of the contract. In the event it is determined necessary to designate a QAR for this contract, such designation shall be by a separate letter to the individual selected with a copy furnished to the contractor.
3.4. The Government, it’s Officers and Agents will be free from liability for any negligence occasioned by the Contractor’s operations, employees or equipment. In addition, the Contractor will reimburse the Government for any damage and/or loss that occurs as a result of the
Contractor’s negligent operations, employees or equipment
3.5. The Government reserves the right to undertake performance by Government forces or other
Contractors, the same type of similar work as contracted for herein, as the Government deems necessary or desirable, and to do so will not breach or otherwise violate this contract.
3.6. Federal Holidays (New Year’s Day, Martin Luther King JR’s Birthday, Presidents’ Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving
Day, and Christmas Day), that fall within the workweek will not be considered workdays.
Whenever a holiday falls on a Saturday or Sunday, the proceeding Friday or following Monday respectively will be observed as a holiday. Prior to the contractor performing the work on days or at times other than those specified, the contractor shall submit a written request to the QAR for approval by the Contracting Officer. Requests for deviation shall be submitted no less than
24 hours prior to the time the contractor desires to work.
4. LIFE, SAFETY AND HEALTH REQUIREMENTS: To better provide life, safety and health protection to all contractor employees, on-site personnel, and Government personnel performing or in any way coming in contact with this contract the specific requirements established here-in will be adhered to at all times:
4.1. 29 CFR 1910: Comply with all pertinent provisions of 29 CFR 1910 General, and with any additional measures the Contracting Officer may determine to be reasonably necessary. Copies of this manual may be obtained from the Superintendent of Documents, U.S. Government
Printing Office, Washington, D.C., 20402.
4.2. OSHA: Comply with latest version of OSHA Handbook Rules and Regulations.
4.3. NFPA: Comply with the most current edition of the National Fire Codes (NFPA) and installation fire prevention standards. www.nfpa.org/catalog
4.3.1. All open flame/hot work or disconnection of fire protection alarms or suppression systems require prior written approval/coordination from one of the 99 th
Regional Support Command
(RSC) POC’s listed on the first page of this document.
4.3.2. Any connection, disconnection or installation of fire protection alarms or suppression systems shall require an acceptance test performed by the contractor and witnessed by the local
Fire Prevention Authority having jurisdiction over that facility. In the event the fire alarm system cannot be disconnected (i.e., child development, hospital, etc) a temporary system will be provided and certified by the local Fire Prevention Authority having jurisdiction. Work required to be performed after hours due to the nature of the facility will be at no additional cost to the government.
4.3.3. All fire alarm system components, including all smoke and heat detectors, shall be protected from dirt, dust and damage during demolition and construction.
4.4. AR 420-90: Comply with Army Regulation 420-90, http://www.usapa.army.mil.
http://www.nfpa.org/catalog http://www.usapa.army.mil/
4.5. Lockout / Tag out Procedure: The Contractor shall perform this work in accordance with 29
CFR 1910.147, The Control of Hazardous Energy and the following general requirements.
4.5.1. Preparation: Make a survey to locate and identify all isolating devices to be certain which switches, valves, or other energy isolating devices apply to the equipment to be locked or tagged out. More than one energy source such as electrical, mechanical or others may be involved.
4.5.2. Sequence Of Lockout/Tag out Procedure:
4.5.2.1. Notify all affected personnel that a lockout/tagout system is going to be used and the reason therefore. The authorized personnel shall know the type and magnitude of energy the machine or equipment uses and shall understand hazards thereof.
4.5.2.2. If the machine or equipment is operating, shut it down by the normal stopping procedure such as depressing stop button, open toggle switch, etc.
4.5.2.3. Operate the switch, valve, or other energy isolating devices so that the equipment is isolated from its energy source. Stored energy such as in charged capacitors, springs, elevated machine members, rotating flywheels, hydraulic systems and other pressurized air, gas, steam, or water systems etc. must be dissipated or restrained by methods such as repositioning, blocking, or bleeding down the stored energy.
4.5.2.4. Lockout and/or tagout the energy isolating devices with assigned individual locks, tags, or additional safety measures as may be required.
4.5.2.5. After ensuring that no personnel are exposed, and as a check on having disconnected the energy sources, operate the push button or other normal operating controls to make certain the equipment will not operate.
CAUTION: Make sure the operating controls are returned to the "NEUTRAL" or "OFF" position after the test.
4.5.2.6. The equipment is now locked out or tagged out.
4.5.3. Restoring Machines Or Equipment To Normal Production Operations:
4.5.3.1. After the servicing and/or maintenance is complete and equipment is ready for normal production operations, check the area around the machines or equipment to ensure that no one is exposed.
4.5.3.2. After all tools have been removed from the machine or equipment, guards have been reinstalled, and personnel are in the clear, remove all lockout and tagout devices. Operate the energy isolating devices to restore energy to the machine or equipment.
4.5.4. Procedure Involving More Than One Person: In the preceding steps, if more than one individual is required to lockout or tagout equipment, each shall place his/her own personal lockout or tagout device on the energy isolating devices. When an energy isolating device cannot accept multiple locks or tags, a multiple lockout or tagout hasp shall be used. If a single lock is used to lockout the machine or equipment, the single key shall be placed in a lockout box or cabinet which allows the use of multiple locks to secure it. Each employee shall then use his/her own lock to secure the box or cabinet. As each person no longer needs to maintain his/her lockout protection, only that person shall remove his/her lock from the box or cabinet.
4.6. USACE EM 385-1-1: The Contractor shall be responsible for knowing the Corps of
Engineers, Safety and Health Requirements Manual, EM 385-1-1, (use the current version at the time of task order award), and incorporate those general and additional safety requirements into daily working procedures to provide safe working conditions during performance of this contract. Copies of this manual may also be obtained from the Superintendent of Documents.
http://www.usace.army.mil/inet/usace-docs/eng-manuals/em385-1-1/toc.htm
4.7. SITE SAFETY PLAN: The Contractor shall submit in writing a Site Safety Plan and present the overall safety program via in-person conference with the Contracting Officer and/or
Primary Project POC. The Site Safety Plan shall follow the requirements of the EM 385-1-1 and include all relevant Accident Prevention and Activity Hazard Analyses. The Site Safety Plan shall include provisions to deal with hazardous materials, pursuant to the Contract Clause entitled "Hazardous Material Identification and Material Safety Data".
4.7.1. With respect to hazardous materials, the plan will consist of:
4.7.1.1. A plan for protecting personnel and property during the transport, storage, and use of the materials.
4.7.1.2. An index of hazardous materials to be introduced to the site.
4.7.1.3. Material Safety Data Sheets (MSDS) for materials listed in the index of the plan and not required in the technical section of the specification.
4.7.1.4. Procedures for spill response and disposal.
4.7.2. The Contractor shall not turn in hazardous waste generated during performance of the contract, for disposal by the government, unless such disposal is explicitly provided for in the contract. If specified in the contract, the Contractor shall provide an MSDS for each hazardous material/waste turned in to the government for disposal.
4.7.3. The contractor shall not dispose hazardous materials/waste in any dumpster, sanitary sewer, storm sewer or dispose of hazardous materials/waste by any other means on government property.
4.7.4. The contractor shall not sign any hazardous waste manifest. Signature authority for hazardous waste manifests is delegated only to certain personnel within the Environmental
Office. The contractor shall provide copies of all manifests or bills of lading for the http://www.usace.army.mil/inet/usace-docs/eng-manuals/em385-1-1/toc.htm transportation and disposal of all asbestos or asbestos containing materials to the Environmental
Office.
4.8. HAZARDOUS MATERIAL CONTACT (PCB, Asbestos or Led Material): If material is encountered which may contain PCB's, hazardous materials, asbestos and/or led and must be disturbed, DO NOT touch the material. Should the discovery of such suspected material affect the Contractor's planned work schedule, the Contractor shall redirect the work crew to other portions of the unaffected work and modify the schedule at no additional cost to the Government.
4.8.1. Contact/notify an On Site Representative/POC from page one immediately if circumstances appear unusual, unhealthy, or otherwise hazardous.
4.8.2. In writing, address circumstances and concerns to be addressed by the Contract Officer, Project POC, Environmental and/or Government Representative regarding the discovery of the suspected material and of any adverse impact the Contractor may expect to incur due to this situation.
4.8.3. On Site Representative, within 14 calendar days, will perform laboratory tests to determine if the material is a hazard. If there is not a danger, the site Representative will direct the Contractor to proceed in the identified area without change. If the material is identified as hazardous, before proceeding, the On Site Representative will determine the most cost-effective means for removal. The hazardous material will be removed, abated or rendered harmless before work commences.
4.9. ENVIRONMENTAL PROTECTION REQUIREMENTS: Provide and maintain strict compliance with all federal, state, county and local environmental protection requirements including but not limited to, water, air, soil, and noise pollution during the life of this contract.
4.9.1. In the event of a spill, initiate containment operations utilizing personnel properly trained and protected for such situations and immediately notify the Contracting Officer and/or On Site
Representative/POC from page one.
4.9.2. Plan for and provide environmental protective measures to control pollution that develops during normal construction practice.
4.9.2.1. Prevent oily or other hazardous substances from entering the ground, drainage areas, storm drainage system, or local bodies of water.
4.9.2.2. Keep dust down at all times, including during nonworking periods. Sprinkle or treat with dust suppressants, the soil at the site, and other areas disturbed by operations. Dry power brooming will not be permitted. Instead use vacuuming, wet mopping, wet sweeping, or wet power brooming. Only wet cutting will be permitted for cutting concrete, and bituminous concrete.
4.9.2.3. Handle generated hazardous waste in accordance with federal, State, county and local regulations including 40 CFR 262.
4.9.3. Plan for and provide environmental protective measures required to correct conditions that develop during the construction of permanent or temporary environmental features associated with the project. Dispose of hazardous waste in strict accordance with federal, State, county and local regulations including 40 CFR 263 and 40 CFR 264.
4.9.4. Make the maximum use of low-noise emission products, as certified by the EPA. Blasting or the use of explosives is prohibited.
4.10. OZONE DEPLETING SUBSTANCES (ODS): The Contractor shall not knowingly vent or otherwise dispose of any ODS in a manner which would permit their release into the environment. ODS's are generally found in refrigerants, fire fighting agents, and solvents.
4.10.1. The Contractor shall use only those products that are approved and listed by the EPA
Significant New Alternatives Program (SNAP).
4.10.2. The Contractor shall furnish a material safety data sheet to the Government representative prior to use of any ODS or SNAP product on station.
4.10.3. Class I ODS's: The use on installations or the removal off an installation is strictly prohibited without the prior knowledge and consent of the Contracting Officer.
4.10.4. Class II ODS’s: Shall be used only when specified by the Government.
4.10.5. When ODS's of any class are used or saved for reuse, the Contractor shall list this amount in pounds on the "Daily Report To Inspector" form and the Contractor's invoice.
4.10.6. ODS's shall be captured and recycled in conformance with all applicable Federal, State, and local regulations.
4.11. SAFETY OFFICER: The Installation Safety Officer will be responsible for monitoring the contractor in the area of safety and accident prevention. Additional information may be provided and Contractor shall comply with the safety rules of the Government installation concerning related activities not directly addressed in this contract.
4.11.1. The Contractor’s personnel, when operating motor vehicles, shall not exceed ten (10) miles per hour when passing military troops on the roadways, and abide by post speed limits otherwise.
4.12. OCCUPANCY:
4.12.1. It shall be the Contractor’s responsibility to coordinate with QAR to schedule and perform his work in such a manner as to create the least possible interference with the conduct of normal activities within the areas.
4.12.2. The Contractor shall not receive any additional compensation due to the conditions brought about by this occupancy and usage of the Government.
4.12.3. Contractors are only authorized to occupy areas in which active construction, maintenance, repair or associated work in the performance of the contract is required to be done.
4.12.4. The Contractor shall not block more than one access of the building at any time, nor shall he disrupt the existing parking arrangement at any of the building parking areas without prior coordination with the QAR.
5. CONDUCT OF EMPLOYEES
5.1. The contractor is fully responsible for the performance and conduct of his employees at all times while on post performing under the contract. The Contractor shall not allow any employee to perform work under the contract while under the influence of alcohol, drugs or any other incapacitating agent.
5.1.1. Contractor employees will abide by the DOD Smoking Policy.
5.2. Military police and other law enforcement personnel on post have the right to deny entry to post or remove from post any contractor employee for misconduct which endangers the health or safety of people or property or for reasons of security. In addition, the Post Commander may bar an individual from entering the post under the authority of 18 U.S.C. 1382.
5.3. Removal from post of a contractor employee in accordance with above shall not relieve the
Contractor from the requirement to meet all of the terms and conditions of the contract.
6. SECURITY
6.1. At all times during the performance of work within the facilities, the Contractor and their employees shall remain cognizant of security restrictions existing within the facility. The
Contractor’s employees shall ensure any doors, windows or access panels which may have been opened for them during the course of the work period are secured at the end of the day.
6.2. The Contractor shall report any incident in which no escort is provided for scheduled work within secured areas of the building or any occurrence during which an escort leaves the
Contractor’s employees while within a secure area.
6.3. The Contractor and their employees may store tools and equipment within the work area.
However, recognize they do so at their own risk even if the area can be secured.
7. INSPECTOR GENERAL’S (IG) AUTHORITY TO INSPECT CONTRACTORS
7.1. The Inspector General shall have access to the Contractor’s facilities, employees, operations, and records at the site where work is being performed at all times to conduct inspections or for other purposes. Where feasible, advance notification of an IG inspection or investigation will be provided to the Contractor by the Contracting Officer.
8. DEFINITIONS
8.1. Where the words “Special Contract Clauses” or “Special Clauses” appear in test provisions, the Technical Specifications, or on contract drawings, it shall be taken to mean “Special Contract
Requirements”.
8.2. Throughout this contract, the word “indicated”, “shown”, or “specified” shall mean indicated, shown, or specified in the drawings and/or specified in the specifications.
8.3. Throughout this contract, the words “as directed” “inspected”, “selected”, or “accepted” shall mean as directed, inspected, selected or accepted by the QAR. The words, “approved” or
“authorized” shall mean approved or authorized by the Contracting Officer. These definitions are provided as guidance for the contractor, and shall service as the governing interpretation when this language appears within the body of this contract and apparently conflicts with the above.
9. APPLICABLE PUBLICATIONS: Those applicable publications that are not listed in the
Applicable Publication paragraph of the Technical Specifications sections, but are found elsewhere in the text of those specifications, also form a part of this contract.
10. SUBMITTALS / DELIVERABLES
10.1. SUBMITTALS: Contractor shall provided submittals to the COR for submittal approval minimum 30 days prior to scheduled installation of any referenced materials substituted in the technical sections herein, unless otherwise noted.
10.1.1. Original and four (4) copies of each submittal shall be provided and signed by the contractor. Once approved, original and four copies will be stamped “Approved”, signed and dated by the COR.
10.1.2. Distribution of submittals: Approved submittals will be included in the deliverables portion as stated in paragraph 10.2 below.
10.2. DELIVERABLES: Send a minimum of 30 days prior to contract completion date original and four (4) copies of ALL final documentation; submittals, certifications, laboratory tests, descriptive data, test reports, required shop drawing, site surveys, and warranties. Send via First
Class Mail, FedEx, or UPS to:
th
Readiness Division HQ
Attn: DWP Operations: Contract# __________________
Fort Dix, NJ 08640
10.3. The Contractor shall furnish to the above address the original manufacturer’s documentation and four (4) copies demonstrating material proof of compliance requirements in regards to Technical Specifications for this contract.
10.3.1. Certificate of Compliance:
10.3.1.1. Name and address of the Contractor
10.3.1.2. Project name
10.3.1.3. Location
10.3.1.4. Quantity
10.3.1.5. Dates of shipment or delivery to which the certificates apply
10.3.1.6. Each certificate shall be signed by an authorized officer of the manufacturing company
10.3.2. Laboratory Tests: Reports submitted with the certificate shall contain:
10.3.2.1. Name and address of the testing laboratory
10.3.2.2. Date of the tests to which the report applies.
10.3.3. Samples: The Contractor shall furnish samples of materials for approval, as required by the applicable sections of the technical specifications that differ from the specification.
10.3.4. Descriptive Data: The Contractor shall furnish the manufacturer’s descriptive data, installation instructions, and maintenance instructions, for approval, as required by the applicable sections of the technical specifications.
10.3.5. Test Reports: The Contractor shall furnish copies of test reports for approval to demonstrate compliance with the applicable sections of the technical specifications that differ from the specification.
10.3.6. Shop Drawings: Consist of illustrations, schedules, performance charts, instructions, brochures, diagrams, drawings and other information to illustrate and/or demonstrate compliance to the applicable sections of the technical specifications.
10.3.6.1. The Contractor shall furnish for approval, one copy “DRAFT Shop Drawing”. Each rendition will be numerically annotated until final approval.
10.3.6.2. The Contractor shall furnish finalized drawing copies “AS BUILTS” and all applicable support data once agreed upon by the Contracting Officer/COR and/or Project POC. Each submission shall include:
10.3.6.2.1. Two (2ea) full size sets of Mylar prints, and Four (4ea) half size paper copy (provide full size paper drawing sets if half size is unreadable).
10.3.6.3.2. Two (2ea) identical copies on optical media discs to include: The drawing sets in both PDF and CAD format (CAD files to be Microstation.dgn files Geo-referenced to WGS84 coordinate system). For smaller projects AutoCAD DWG files are acceptable. An electronic copy of the specifications associated with the project. Drawing index in MS Excel listing each drawing title, sheet name, drawing number, sheet number, and electronic file name for the drawings of the project
10.4. Documentation shall not be construed as relieving the Contractor from furnishing satisfactory material, if after tests are performed on selected samples of the material is found not to meet the specific requirements.
11. TECHNICAL SPECIFICATIONS: REPAIRS TO THE TANK SYSTEM
11.1 PERIOD OF PERFORMANCE: 90 Calendar Days from the Notice to Proceed Date to complete ALL TASKS associated with the Scope of Work.
11.1.1. SECURITY:
11.1.2. AT Level I training. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT
Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 30 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil
11.1.3. Access and general protection/security policy and procedures. Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost
Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal
Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy.
In addition to the changes otherwise authorized by the changes clause of this contract, should the
Force Protection Condition (FPCON) at any individual facility or installation change, the
Government may require changes in contractor security matters or processes.
11.1.4. For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate
Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive
2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at
OCONUS locations, in accordance with status of forces agreements and other theater regulations.
11.1.5. iWATCH Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity
ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within XX calendar days of contract award and within YY calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.
11.1.6. For contracts that require OPSEC Training. Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter.
11.1.7. The COR of the project shall inform their employees (contractors) about suspicious activity reporting, iWatch procedures and Antiterrorism/OPSEC Awareness. The COR shall keep proper accountability of their personnel.