Questions_and_Answers.docx

DOCX document 14 KB Posted

Attached to
Well Repairs at Fort Devens Federal contract opportunity
Solicitation number
W15QKN17R1054
Issued by
Department of the Army Materiel Command Contracting Command Picatinny Arsenal

About this file

Questions and Answers

View the file

Other files for this federal contract opportunity

Other files attached to Well Repairs at Fort Devens, newest first.
File Type Posted
7701-3351_Observed_Fire_Trainer_Facility_-_Building_4322.pdf PDF
Q&A4.docx DOCX document
amendment_0006.pdf PDF
Q&A_3.docx DOCX document
Drawings_1.pdf PDF
Updated_SOW.pdf PDF
Drawings_2.pdf PDF
Layout.pdf PDF
Floor_Plan.pdf PDF
Amendment_0005_.pdf PDF
amendment_0004.docx DOCX document
amendment_0003.pdf PDF
Q&A.docx DOCX document
W15QKN-17-R-1054_0002.pdf PDF
W15QKN-17-R-1054_0001.pdf PDF
04_DEP_Corrective_20161230_SOW_Attach_01_South_Post_Map_for_MA_DEP.pdf PDF
04_DEP_Corrective_20161230_SOW_Attach_03_NON-CE-14-5D566.pdf PDF
04_DEP_Corrective_20161230_SOW_Attach_02_NON-CE-14-5D024_Sanitary_Survey.pdf PDF
SOW.pdf PDF
W15QKN-17-R-1054.pdf PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Do you have plans?

a. Yes, will be provided as part of an updated SOW package.

2. Are there drawings available that depict the existing conditions of the mechanical and electrical systems at each location requiring work to be performed?

a. Yes, will be provided as part of an updated SOW package.

3. Are there drawings available that indicate the proposed mechanical and electrical modifications being made at each location that requires work to be performed?

a. Yes, will be provided as part of an updated SOW package.

4. Reference the Scope of Work, PART 3 - OTHER REQUIREMENTS and advice if the scope of the Contractor is intended to include a system operation, data collection, and DEP compliance reporting requirement, or is this function intended to be performed by the current Licensed Ft Devens SWSS Operator?

a. This is an error in the SOW. It will be modified as part of an updated SOW package.

5. In Part 3 Other Requirements Section 3.1 Submittals it states the successful contractor is required to identify a laboratory, operator’s current registrations, and providing/reporting documents to the MADEP. Please confirm if this is a carryover from a previous SOW and that there are no reporting requirements to the MADEP for this project.

a. This is an error in the SOW. It will be modified as part of an updated SOW package.

6. We are also requesting drawings that are referenced in the Scope of Work (SOW) accompanying the solicitation. The SOW mentions “provided prints” and “note II9,” for items such as redistribution of piping interior and exterior. We only see a site overview map.

a. This will be provided as part of an updated SOW package.

7. Is this a sole source/8(a)/SDVOSB Set-Aside?

a. No, this is a competitive small business set-aside.

8. Please confirm the number of amendments issued to date is 4?

a. There were four amendments previously, this is amendment 5. They can all be found on FBO.

9. Is there an advertised Government Estimate for this solicitation?

a. No, the Government will not be releasing an estimate for this requirement.