Questions_and_Answers.docx
DOCX document 13 KB Posted
- Attached to
- Hardware Refresh of Government Furnished Equipment and Technical and Maintenance Support
- Solicitation number
- W15QKN-17-Q-0003
About this file
Questions and Answers Pertaining to Solicitation Number W15QKN-17-Q-0003- Hardware Refresh of Government Furnished Equipment and Technical and Maintenance Support
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMENDMENT_03.docx | DOCX document | |
| Amendment_02 _Questions_and_Answers.docx | DOCX document | |
| SOW_eMILPO-DTAS_HW_20Oct16.doc | DOC document | |
| CombinedSynopsisSolicitation eMILPO_and_DTAS.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers Pertaining to Solicitation Number: W15QKN-17-Q-0003- Hardware Refresh of Government Furnished Equipment and Technical and Maintenance Support
1) Question: Is the contractor installing this equipment as part of the upgrade or only procuring the equipment for delivery?
Answer: The contractor will provide the hardware for delivery. No installation is required.
2) Question: If the contractor is installing the equipment, can you clarify if you required on-site 24 X 7 contractor support per para. 1.3.
Answer: The 24 (hour) x7 (days) is maintenance support at a "premium" level, instead of a "standard" level of support, which is usually 8-5...Mon-Fri.
3) Question: Do you required on ground support for the life of this contract?
Answer: The 24x7 premium level maintenance support is required for both the Base Year and one additional year.
4) Question: Can you please provide feedback on the number of FTEs if any are needed and labor category description for each?
Answer: There are no FTEs required as there is no labor component to this contract.
5) Question: Is this a new requirement?
a. If not, can you please provide the current contract number and vendor name?
Answer: This is a new requirement, therefore there is no incumbent contractor nor previously awarded contract.