Attachment 0002 - Quality Assurance Surveillance Plan (QASP)

View the file

Other files

File Type Posted
EWI_-_Redacted_JA_(5-4-16).pdf PDF
W15QKN16R0022-0001.pdf PDF
Exhibit_A_-_CDRLs.pdf PDF
Attachment_0001_-_Labor_Categories.xlsx XLSX spreadsheet
W15QKN-16-R-0022.pdf PDF
Attachment_0002_-_Quality_Assurance_Surveillance_Plan_(QASP).pdf PDF
Exhibit_A_-_CDRLs.pdf PDF
W15QKN-16-R-0022.pdf PDF
Attachment_0001_-_Labor_Categories.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE REQUIREMENTS SUMMARY/QUALITY ASSURANCE SURVEILLANCE

PLAN (PRS/QASP)

Performance Requirement IAW Section

Performance Measure

Performance Standard

Acceptable Performance

Level

(APL)

Method of

Surveillance

Compliance (Exceeded, Met or Partially

Met The contractor shall provide field support during pre-campaign and campaign operations

Completeness

Quality

Timeliness

The installations/ reinstallations will be performed expeditiously.

The Engineers and technical staff will ensure that the calibrations, repairs maintenance, troubleshooting, modifications, installations/reinstallations are complete

*TBD on a Task Order Basis

COR/COTR

Review

Repair service calls

Timeliness Repairs are made in a timely manner; customers are informed of expected repair time of within 24 hours of repair time.

*TBD on a Task Order Basis

The contractor shall provide process support

Quality

Timeliness

Completeness

Process and Mechanical Engineering support during operations will be performed expeditiously to minimize downtime. The engineers and technical staff will ensure that maintenance, repair, troubleshooting/diagnosis, redesign, and software modification are complete.

*TBD on a Task Order Basis shall provide permitting support

Quality

Completeness

The Engineers and technical staff will ensure that modification and upgrade of the incinerator compliance program is complete. Complete permitting reports prepared and submitted as required by NJDEP

*TBD on a Task Order Basis

Supply critical parts and materials

The critical parts and material must be supplied in a timely manner so as to

*TBD on a Task Order Basis not interfere with the current operations

Submit maintenance, installation, support, and repair reports

Completeness

Upon satisfactory completion of maintenance, installation, repair and support efforts the contractor will supply monthly invoice detailing the work done, hours expended and equipment purchased; this will also include the balance of remaining monies left on the contract.

Report shall be submitted electronically and contain no errors.

*TBD on a Task Order Basis will submit safety reports as required

The contractor will submit safety incident/accident reports immediately after any major accident or incident as describe in Section 7.3

Report shall be submitted electronically and contain no errors.

*TBD on a Task Order Basis

*TBD on a Task Order Basis