This Performance Work Statement (PWS) details a roof repair project for Building 4737 at Seymour Johnson Air Force Base in North Carolina. The contractor must design, procure, and install a new Polyvinyl Chloride (PVC) fabric siding/roof membrane for a prefabricated stress tension shelter measuring 50' wide, 212' long, and 25' tall. The project requires replacing the existing membrane installed in 1995, with new white roof panels and tan side wall panels that are Berry Amendment Compliant, 28-ounce PVC coated polyester, and NFPA 701 compliant.

The project has a 90-calendar day period of performance, including design, material procurement, and construction. Key requirements include installing a temporary cover within 7 calendar days of contract award, ensuring the new membrane meets specific design parameters (including temperature range of -70°F to 130°F, wind load capabilities, and snow load specifications), and protecting an existing External Aircraft Fuel Tank Storage System (EAFTSS) located within the structure. The contractor must provide structural drawings stamped by a North Carolina professional engineer and submit various deliverables, including project schedules, color samples, and as-built drawings. Warranties include five years for materials/workmanship, 20 years for finish, and 10 years for weather tightness.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VKAG 25-1034

REPAIR ROOF, BUILDING 4737

Performance Work Statement (PWS)

Seymour Johnson Air Force Base North Carolina

8 September 2025

Revised 10 September 2025

Table of Contents

1.0 PURPOSE 3

2.0 SCOPE 3

3.0 DESCRIPTION OF WORK 3

3.1 General 3

3.2 Structure 3

3.3 Roof 4

3.4 Sides 4

3.5 Electrical 4

4.0 GENERAL REQUIREMENTS 4

4.1 Schedule 4

4.2 Warranties 4

4.3 Deliverables and Deliverable Schedule Supplement 4

4.4. AUTOCAD Requirements General 5

4.5 Applicable Documents 8

4.6 Work 8

4.7 Contractor Laydown Area 8

4.8 On-site Field Oversight 8

4.9 Safety Requirements 9

5.0 GOVERNMENT FURNISHED MATERIAL (GFM) 9

6.0 SCHEDULE 9

7.0 List of Attachments/Government Furnished Material (ALL on CD) 9

1.0 PURPOSE

The contractor shall design, procure, and install new Polyvinyl Chloride (PVC) fabric siding/roof membrane for Building 4737, a prefabricated stress tension shelter at Seymour Johnson Air Force Base, North Carolina.

2.0 SCOPE

2.1 The contractor shall provide all necessary personnel, facilities, tools, equipment and materials to complete the tasks identified in this PWS.

2.2 The contractor shall demolish and dispose of existing fabric siding/roof membrane for Building 4737.

2.3 The contractor shall design, procure, and install a new PVC fabric siding/roof member for Building 4737.

2.4 The contractor shall provide and maintain a temporary cover over the hole in the existing roof membrane until the new siding/roof membrane is on-site and the existing siding/roof membrane is removed.

3.0 DESCRIPTION OF WORK

3.1 General

3.1.1 Design, procure, and install new PVC fabric siding/roof membrane for Building 4737, a prefabricated stress tension shelter. Existing shelter is 50’ wide, 212’ long, and 25’ tall. Structural drawings must be stamped by a professional engineer licensed in North Carolina.

3.1.2 The new PVC fabric side and roof panels will be installed over an existing galvanized metal frame structure and on concrete foundation that is not to be modified without Contracting Officer approval.

3.1.3 The existing structure (frame and membrane system) was designed to meet the following parameters and these parameters shall remain the MINIMUM design criteria for the replacement membrane.

Temperature Range: -70°F to 130°F Wind Load (Sustained): 70MPH Wind Load (Gust): 100MPH Snow Load: 40 PSF Rainfall Load: 4”/Hour

3.1.4 A mechanized tank storage system called the External Aircraft Fuel Tank Storage System or EAFTSS, is housed within the structure and cannot be relocated during the membrane replacement. The stored vertical fuel tanks can be moved around and potentially relocated but the storage system cannot. The contractor shall prevent damage to the EAFTSS and any fuel tanks during installation of the temporary cover and the membrane replacement.

3.2 Structure:

The existing structure was installed in 1995 and is a prefabricated stress tension shelter with a galvanized metal frame installed on a concrete foundation.

The information plate on the shelter reads the following:

Type of Equipment – Tension Membrane

Name of Manufacturer – Rubb Building Model No – 50 x 212.5 BVE Contract No – F33600-93-D-0124 Weight – 80,000 lbs Manufacture Date, Month/Year – 4/95

3.3 Roof:

Roof panels shall be translucent “white” color to match existing and shall be custom cut to accommodate any existing penetrations.

Fabric shall be Berry Amendment Compliant, 28-ounce PVC coated polyester, and National Fire Protection Association (NFPA) 701 compliant.

3.4 Sides

Side wall panels shall be “tan” color to match existing and shall be custom cut to accommodate all existing doors, fans, and other penetrations.

Fabric shall be Berry Amendment Compliant, 28-ounce PVC coated polyester, and NFPA 701 compliant.

3.5 ELECTRICAL

Electrical service to the structure shall be disconnected and reconnected by the 4th Civil Engineer Squadron Electrical Shop. Coordinate with the Contracting Officer and/or Contracting Officer’s Representative to schedule disconnection and reconnection of electrical service.

3.5.1 Lightning Protection

Not Applicable

4.0 GENERAL REQUIREMENTS

4.1. Schedule. Contractor shall maintain a project schedule showing the major elements of work and demonstrating an efficient logical plan to complete the removal of existing fabric and installation of the new fabric in the allotted performance period.

4.2 Warranties: Unless specified otherwise, a one-year workmanship warranty shall apply to all work.

Contractor shall provide all manufacturer’s warranties for installed items. Warranties shall be, from date of acceptance:

- Five years materials/workmanship (including structural failures such as rupturing, cracking, or puncturing)

- 20 years finish (color fading, chalking, cracking)

- 10 years weather tightness

4.3 Deliverables and Deliverable Schedule Supplement. The contractor shall complete all demolition, design, and construction activities. When construction is complete, a complete set of as-built record drawings (including CADD files) and O&M manuals shall be submitted to the base.

Specific minimum submittals required with proposal package. Contractor shall provide the following submittals as a minimum for approval by the Contracting Officer:

• Project Schedule

• Color Samples

• Material Certificates of Compliance After Award, prior to commencing work:

• Structural/Tensioning/Sealing Design (Stamped by NC PE)

• Drawings (Plan View, Elevations, Tensioning/Sealing Details) After completion of onsite work:

• Operations & Maintenance (O&M) Manuals

• Warranty Documentation

• As-Built Drawings (if any variations to drawings)

4.4. AUTOCAD Requirements General. All contract drawings to be furnished shall be well prepared, complete, and accomplished in accordance with the best industry practice to show clearly and concisely type and extent of work to be performed. The term “contractor” shall mean an A&E firm, Design / Build firm, SABER, MACC, Construction firm, or contractors performing work for the U.S. Army Corps of Engineers contracted and or managed non-MILCON project for SJAFB. The contractor shall ensure drawings, specifically any shading or hatching, are reproducible on the Base Engineer’s KIP 7970 printer. All drawings shall be drawn to appropriate scales and dimensioned completely and accurately and shall be legible at when drawings are reproduced at ½ size. Contractor shall not place any company logos of any type on drawings. The engineer of record shall place contact information in the lower right corner of the cover sheet in an area not to exceed 2”x 2”. Engineer license seals shall be placed on all drawings required to be sealed by the design engineer, address and contact information for that engineer shall be placed under the engineers seal. Extensive explanatory notes on the drawings are undesirable and should be placed in the specifications. The use of fractions less than 1/8” for building dimensions will be avoided. Standard building material indications, symbols for civil items, and for electrical equipment shall be used to the greatest extent possible.

4.4.1 AUTOCAD Design Drawing Sets: The contractor shall supply all contract drawings prepared using the latest release of AutoCAD software (Release 2014 or higher), however, save all drawings in a AutoCAD 2018 format. Drawings prepared in AutoCAD LT versions or AutoCAD academic versions are not acceptable and shall be rejected. Drawings shall be managed utilizing the “Drawing Sheet Set Manager” in AutoCAD. Line quality shall not be half-toned or gray scaled below 75%. Drawings produced using another software package will be acceptable provided all drawings are converted to standard AutoCAD drawing file format prior to receipt by the Government and comply with the SJAFB CADD standard which is based on the U.S. Army Corps of Engineers CADD STD 6.1 dated August 2019. SJAFB CADD standards manual will be provided upon request by the drafting section. In addition, the contractor shall comply with the following standards:

a. Drawing files shall be delivered in the standard AutoCAD “.dwg” file format for AutoCAD 2017 version. “Model space” shall be the preferred method for drafting all drawing items such as floorplans, sections, details…. Dimensions, leaders, and notes… specific to the drafted item shall accompany the object drawn in “Model Space” and be scaled accordingly to appear in paper space at the correct text height as specified. Only general notes applicable to the entire drawing shall be in Paperspace.

b. Drawing units shall be set according to the requirements for the drawing discipline, i.e. civil drawings units shall be set to the decimal format, and architectural drawings set to the architectural format. Civil site plans shall be in North Carolina State Plane (NAD 83 and NADV88) with all site plans oriented with north at the top of the sheet. Any Reorientation of a view for drafting convenience shall be done within the viewport using the “Dview and Twist” commands, objects in model space shall not be rotated. The contractor shall supply a written explanation as to how externally referenced drawings are used, view-port scales/settings, viewport layer settings, blocks and any other relevant information necessary for the Engineering Support Section of Seymour Johnson to make changes or updates to the drawings. The contractor must also be available for phone assistance to clarify any other problems encountered by the Engineering Support Section. “Paperspace” shall be used to format the final plotted drawing sheet.

c. Standard plotted paper size shall be the “ARCH-D” size sheet unless otherwise specified.

d. All drawings shall use the standard Seymour Johnson AFB project templates to include title block. Templates are available for each engineering discipline. Title block shall not be altered by the contractor.

e. Project and drawing data shall be managed using the drawing sheet set manager. Title block template files shall not be modified as attributes within the title block are used by other drawing management tools. SJAFB Drawing templates will be made available for each discipline by SJAFB Engineering Support section.

f. All Drawings (drawing sets) shall be delivered in AutoCAD format at various stages of the project. All drawings shall be submitted on CD-ROM / DVD-ROM. Submittals made at 35%, 65%, 100%, and or AS-Built. CD-ROM / DVD-ROM shall be labeled accordingly, i.e. 65% review, 100% for construction, or AS-Built as required.

g. All External Referenced (XREF) drawings will have an “xref_” at the start of the file name (i.e.

xref_base.dwg). Xref drawings shall be located and linked correctly as to ensure the externally referenced drawing will load with referencing drawing. The contractor shall not layer / nest xref drawings. Multiple xref drawings on the same level shall be allowed, but, not nested xref’s.

Each drawing file will contain only one drawing. If a drawing has an XREF drawing, the XREF shall also be a separate drawing. Xref drawings shall not contain other xref drawings i.e. nested externally referenced drawings. The contractor shall provide complete typewritten instructions for reintegrating the drawings, and must specify which XREF goes with which drawing. Contractor shall use the “Drawing Sheet Set” function of AutoCAD to create and organize the project drawing set, and the “E-Transmit” function of AutoCAD to package all drawing sets for delivery.

h. The contractor shall utilize Arial text. Text shall be 1/8” in height for all normal text, and ¼” in height for headings such as, “DETAILS, SECTIONS, PLANS etc…”. Only text fonts / styles native to the basic AutoCAD package shall be used. No unique text styles or fonts developed by the contractor, or design firm shall be used.

i. The contractor shall be provided a copy of layer standard and drawing templates utilized by the

SJAFB Drafting Section upon request. SJAFB layer standards are based on the CADD/GIS Technology Center (U.S. Army Corps of Engineers CADD STD 6.1 dated August 2019, and on the NIBS National CADD Standard v 6.0), standards are found at their web site: https://cadbim.usace.army.mil/. Compliance to CADD layer standards are critical to the integration of project drawings to the Air Force Civil Engineering NextGen IT and GIS systems.

Any new layers created by the contractor shall have narrative descriptions easily identified (i.e., https://cadbim.usace.army.mil/ walls, elec., etc.) and shall follow the CADD standard naming convention in the description field in the drawing layer manager. All objects drawn shall be placed on the appropriate layer. Dimensions and annotations shall be placed only in model space. Due to the difficulty seeing the color yellow (color #2) against a white background (either model space, paper space, or plotted hardcopy), the color yellow shall not be used.

j. Use of third party development software is acceptable provided all final drawing files submitted are native AutoCAD format. Any features peculiar to the development software used, such as shape files, menus, blocks, etc. that are not accessible using the basic AutoCAD package are not acceptable and shall be modified to ensure the drawing files may be easily maintained, edited, or changed by government personnel using the basic AutoCAD software package.

k. Final AutoCAD drawing files should exhibit good drafting practice allowing for each change and minimal storage requirements. Drawings should make use of features to limit drawing size/complexity wherever possible. Over-detailing (drawing features that are not discernible at full or half scale reproduction) is not acceptable and must be avoided. All detail notes, leaders and dimensions shall be legible when reproduced at half scale.

l. Drawings shall have no more than one layout tab. Layout tab shall have the same name as the sheet title name.

m. SJAFB does not use unique plot styles, use only out of the box “monochrome.ctb” to plot drawings. SJAFB plots all drawings using line weights and line types as assigned for each layer in layer manager. Line weights of less than 0.15mm shall not be used.

n. Provide only “un-bound” native files. CADD files provided as “bound” files (files that contain multiple reference files copied, bound, into a single file) are unacceptable and unusable for future changes or use of drawing files by SJAFB.

o. Final drawings shall be submitted with a complete hard copy list of drawing file names, layers used, etc. Project number and list of drawings on each disk will be written on the label affixed to the disk. Drawing file name shall be in accordance with SJAFB standards and shall appear in the appropriate section of the title block as directed by the SJAFB Technical Support personnel.

SJAFB Title blocks shall not be modified by the contractor as attributes are embedded in the title blocks are extracted for use in SJAFB CADD digital vault database, contractor shall update attributes contained in the Sheet Set Manager or attributes directly in the title block if not in the properties within the Sheet Set Manager. Contractor shall use both the “Drawing Sheet Set Manager” functionality of AutoCAD and the “E-Transmit” function of AutoCAD to package all drawing sets for delivery. SJAFB drawing templates and Drawing Sheet Set Manager template contain attributes to ensure consistent title block information. The “E-Transmit” functionality within the Sheet Set Manager ensures that all blocks, externally referenced files are packaged with the drawing set and ensure all references remain intact.

p. CAD and PDF files shall be sent on CD for each design submittal to allow for Government quality control review. Final CAD and PDF format drawings shall be included with the final project CD in separate folders.

4.4.2 AS-BUILT DOCUMENTS (if any variations to drawings):

4.4.2.1 Drawings:

During the progress of the work, the contractor shall keep a careful record at the job site of all changes and deviations to the layouts shown on the drawings. The contractor shall manually enter such changes and corrections and make corrections to the field drawings promptly for incorporation into final “as-built” drawings. As-built drawings shall conform to SJAFB CADD standards. As-Built AutoCAD drawings are based on the “100% For Construction” CADD drawing set. Drawings shall be managed utilizing the “Drawing Sheet Set Manager” in AutoCAD. The final as-built drawings shall indicate, in addition to all changes and corrections, the actual location and depth of all subsurface utility lines. If the project was designed by the government, it shall be the responsibility of the contractor to submit for approval the final as-built AutoCAD drawings incorporating “red-lines”, and survey data referenced below, at the project’s conclusion. If the project was designed (design / build), the contractor shall provide the Government with a draft of the as-built drawings in AutoCAD for CADD format for CADD standards review along with standard D size drawing set for review at the project’s conclusion. Following government approval of the draft, the contractor shall submit the survey data referenced below and the final as-built drawings; one (1) copy of Standard D (24” x 36”) size drawings and a CD ROM or DVD ROM containing the AutoCAD 2013 format as-built drawings. Final as-built AutoCAD drawings delivered on CD ROM or DVD ROM shall utilizing the “E-Transmit” tool within AutoCAD.

4.4.2.2 Survey Data:

The contractor shall furnish survey data showing the horizontal/vertical location of all site improvements constructed under the Task Order to include, but not limited to, topography, buildings, pavements, utilities, and all similar construction. Contractor shall provide survey coordinates for the as constructed corners of any buildings that are new construction, or additions to existing buildings. Building corner survey data shall be in NC State Plane coordinates. Site improvements such as buried utility lines require one survey shot every 50’ of straight line, at changes in elevations along a run, at each turn or bend in the line, hydrants, fittings, valves, valve boxes, curb stops, electrical hand holes, relocations and crossings of existing utilities, structures, or other appurtenances relocated or affected by the construction. Also provide elevations for the topmost point of visible appurtenances such as fire hydrants and valve boxes, and provide rim and invert elevations for all manholes in the project area. The contractor shall use conventional surveying methods such as total stations, automatic levels, or Global Positioning System (GPS) for field data collection at an accuracy of +/-2cm. A copy of all survey data shall be a submitted as a deliverable item. All survey work shall be tie to existing grid through use of on base monuments as published by National Geodetic Survey (NGS) NAD 83, NADV 88. Benchmark data is found at the National Geodetic Survey website: https://www.ngs.noaa.gov . Site survey drawings shall show the ties to published monuments / benchmarks. Assumed elevations with temporary benchmarks are not acceptable. Survey deliverables include field notes, field book data, and/or data collector files compatible with Trimble Business Center software version 3.9 or greater. Drawing data shall delivered in an AutoCAD format (NC State Plane, units set to feet, where one AutoCAD drawing unit = 1.0’, decimal unit format for civil / site drawings). All electronic data deliverables shall be a CD-ROM in format that conforms to the latest version of both the CADD/GIS Technology Center’s Spatial Data Standards and A/E/C CAD Standards. These standards can be found at:

https://cadbimcenter.erdc.dren.mil/default.aspx?p=a&t=1&i=2

All AutoCAD drawings used for site or survey work shall conform to the SJAFB CADD standards which are based on the USACE CADD Standards v 6.0. AutoCAD survey drawings layering conventions shall conform to USACE CADD standard for the “V” survey drawings. Reference section 5.a drawings, for CADD standards.

4.5 Applicable Documents. The contractor shall comply with all applicable Federal, state, local and agency laws; building codes, statutes, ordinances, instructions, manuals, handbooks, UFCs, regulations, https://www.ngs.noaa.gov/ https://cadbimcenter/ guidance, policy letters and rules (inclusive of changes and amendments), and Presidential Executive Orders in effect on the date of issuance of the project.

4.6 Work. Work shall commence immediately following contract award. No on-site work shall commence prior the initial pre-execution conference. Pre-execution conference shall be held prior to the start of any on site work. Coordinate and schedule the pre-execution conference with the Contracting Officer and Contracting Officer’s Representative. Further details regarding management requirements, inspection and testing, facilities and temporary controls, environmental protection, quality control system, on-site quality control, and project closeout will be in accordance with the contract documents. All existing site and facility features to be removed during demolition shall be clearly annotated in the Installation variation drawings and supporting documents. Implementation of these documents will provide the basis for the refined design and other documentation required for the work.

4.7 Contractor Laydown Area If insufficient space is available adjacent to the worksite, the contractor will be given a lot in the Contractor Storage area approximately 1 mile from the site for any additional storage needs above and beyond the on-site storage.

4.8 On-Site Field Oversight. The contractor shall provide the manpower, equipment, material, services, and transportation necessary to ensure oversight services throughout accomplishment of this contract.

The Government will provide on-going surveillance and approval recommendations. The Contracting Officer’s Representative will report all findings to the Contracting Officer. It is the responsibility of the Contractor to establish and maintain open communications between salient authorities associated with accomplishment of this contract.

4.9 Safety Requirements. The Contractor shall conduct its operations in accordance with EM 385-1-1 U.S. Army Corps of Engineers Safety and Health Manual (latest edition).

5.0 GOVERNMENT FURNISHED MATERIAL (GFM)

Reference Material. Seymour Johnson AFB will make record drawings/data available for contractor research purposes to include base topographic, utility and Installation variation drawing information for the project area, a portion of which has been provided with this PWS. All documents are to be viewed and to remain in 4 CES record drawing vault within the Engineering Flight in Building 3300.

6.0 SCHEDULE

6.1 Period of Performance. The period of performance will be 90 calendar days, inclusive of design, material procurement/approval, and construction period. Contractor shall plan material submittals and work in order to meet the performance period.

6.1.1 Temporary cover over the hole in the existing roof membrane shall be installed within 7 calendar days of contract award.

6.1.2 Removal of the existing fabric membrane shall not commence until the new fabric membrane is delivered, inspected, and accepted by the Contracting Officer and/or Contracting Officer’s Representative.

6.3 Deliverables. Contractor shall submit one (1) full-size and two (2) half-size drawing sets (including 2 CD e-transmittal of Autocad files and PDFs of all installation design documents) to the Contracting Officer. Contractor is responsible to draft and provide any design meeting minutes to all Government points of contact.

7.0 List of Attachments/Government Furnished Material

7.1 VKAG 25-1034 Site Photos

7.2 SJAFB Site-Specific EMS Awareness Training for Contractors (Aug 2024)

7.3 01 00 00 General Requirements REV 20OCT23

END OF PERFORMANCE WORK STATEMENT

1.0 PURPOSE
2.0 SCOPE
3.0 DESCRIPTION OF WORK
3.1 General
3.2 Structure:
3.3 Roof:
3.4 Sides
3.5 ELECTRICAL
3.5.1 Lightning Protection
4.0 GENERAL REQUIREMENTS
5.0 GOVERNMENT FURNISHED MATERIAL (GFM)
6.0 SCHEDULE
7.0 List of Attachments/Government Furnished Material

File details come from the government source that posted it. Updated .