This document is an Emergency Purchase Extension Approval from the State of Illinois Chief Procurement Office for General Services. The requesting agency is the Illinois Department of Corrections (DOC) for the Vienna Correctional Center. The scope of the initial emergency contract was to rent a 600 HP boiler to temporarily replace the facility's current boiler that is in need of replacement and inspection. The original emergency term ran from February 26, 2024 to May 26, 2024. This extension will run from May 27, 2024 to December 30, 2024 to allow time for the replacement of the permanent boiler by the Capital Development Board. The total estimated cost of the extension is $298,093.50.
The original emergency procurement was necessary due to the critical need for continued operation of the boiler system at the Vienna Correctional Center, which provides essential services like hot water, cooling/heating, and meal preparation. A competitive procurement process could not be used to meet this emergency need. There is no Businesses Enterprise Program (BEP) participation on this contract, as the agency was only able to identify one vendor, Heartland Mechanical, in the local area that could provide the required temporary boiler.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Vienna CC Temp Boiler emergency-purchase-extension 51024 APO Wet Signed~1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EMERGENCY PURCHASE EXTENSION APPROVAL
State of Illinois Chief Procurement Office for General Services Emergency Purchase Extension Approval v.24.1 Page 1 of 3
Section 20-30(a) of the Procurement Code provides that a contract for an emergency may be extended beyond 90 calendar days with the approval of the chief procurement officer (CPO). Prior to execution of the extension, the CPO shall receive this completed form justifying the extension. The duration of the extension shall be limited to the scope of the emergency.
Zip: 62966State: ILCity: MurphysboroAddress: 511 Health Department Rd.
Vendor: Heartland Mechanical
Zip: 62995State: ILCity: ViennaAddress: 6695 State Route 146 East
Requesting Agency DOC - Corrections Division: Vienna Correctional Center
Extension Justification BidBuy Reference #: 24-426DOC-VIENN-P-63232
Amount of original contract: $ 177,593.5
Actual or Estimated: Estimated
Original BidBuy Reference #: 24-426DOC-VIENN-B-41858
Original Emergency Term Start Date: 2/26/2024 Original Emergency Term End Date: 05/26/2024
Expected Extension Start Date: 05/27/2024 Expected Extension End Date: 12/30/2024
Amount of extension contract: $298,093.5 Actual or Estimated: Estimated
Is there BEP participation on this contract? If no, explain why
Approved 0% BEP Goal Setting Review Form attached. Vienna CC looked for Vendors to meet this type of emergency and was only able to find Heartland Mechanical in the area.
Has this emergency contract been extended before? Please detail in the space below:
BidBuy Reference # Amount Start Date End Date
$0.00
$0.00
$0.00
1. Provide detail about the events that led the agency to conduct an emergency procurement:
Vienna CC boilers produce steam for facility hot water, cooling/heating and meal preparation for the facility. This emergency procurement will be a one-time procurement. The existing boiler is being replaced by CDB.
2. What is the scope of work of the initial emergency contract? Please detail below:
Rental of 1 600 HP boiler to temporarily replace current facility boiler that is in need of replacement and inspection.
3. Does this extension change the scope of work? Yes No If yes, please detail below:
Emergency Purchase Extension Approval v.24.1 Page 2 of 3
Section 20-30(a) of the Procurement Code provides that a contract for an emergency may be extended beyond 90 calendar days with the approval of the chief procurement officer (CPO). Prior to execution of the extension, the CPO shall receive this completed form justifying the extension. The duration of the extension shall be limited to the scope of the emergency.
Zip: 62966State: ILCity: MurphysboroAddress: 511 Health Department Rd.
Vendor: Heartland Mechanical
Zip: 62995State: ILCity: ViennaAddress: 6695 State Route 146 East
Requesting Agency DOC - Corrections Division: Vienna Correctional Center
4. Provide justification for extending the original emergency contract:
Extending the original emergency contract for temporary boiler for Vienna Correctional Center is crucial to maintaining the daily operational needs for the facility. Vienna CC boilers produces steam for facility hot water, cooling/heating and meal preparation for the facility. This emergency procurement will be a one-time procurement. The existing boiler is being replaced by CDB and inspected to become operational again.
5. Does this emergency contract correct or eliminate the emergency condition?
Yes No Please detail:
The emergency extension of the temporary boiler is needed until the new, permanent boiler becomes operational.
6. Explain why the need cannot be met through a competitive procurement process.
Emergency procurement, needing extension until new boiler becomes operational.
7. Is a competitive procurement in process to replace this emergency contract?
Yes No Status: other, please explain below
Vienna's new boiler is being replaced for full operation by CDB and is expected to be complete by the end of 2024.
8. What is the effect of a denial of this extension request?
The denial of an extension request for the emergency temporary boiler could have several significant effects:
Disruption of Services: Without access to a boiler house, Vienna Correctional Center would be unable to operate leading to disruptions in essential services such as hot water, cooling/heating and meal preparation for the facility.
Emergency Purchase Extension Approval v.24.1 Page 3 of 3
Section 20-30(a) of the Procurement Code provides that a contract for an emergency may be extended beyond 90 calendar days with the approval of the chief procurement officer (CPO). Prior to execution of the extension, the CPO shall receive this completed form justifying the extension. The duration of the extension shall be limited to the scope of the emergency.
Zip: 62966State: ILCity: MurphysboroAddress: 511 Health Department Rd.
Vendor: Heartland Mechanical
Zip: 62995State: ILCity: ViennaAddress: 6695 State Route 146 East
Requesting Agency DOC - Corrections Division: Vienna Correctional Center
BidBuy Reference #: 24-426DOC-VIENN-R-217504
Signatures below cannot be delegated.
APO Signature
I am requesting an extension of the requested emergency contract. I believe all statements herein are true and correct to the best of my knowledge.
APO Signature: Date:
SPO Signature
SPO Signature: Date: May 15, 2024
CPO Signature Based on my review, I approve the Agency to proceed in accordance with the emergency contract extension detailed in this document.
Based upon my review, I approve the Agency to proceed with the following changes:
CPO Signature: Date:
Page of
Section 20-30(a) of the Procurement Code provides that a contract for an emergency may be extended beyond 90 calendar days with the approval of the chief procurement officer (CPO). Prior to execution of the extension, the CPO shall receive this completed form justifying the extension. The duration of the extension shall be limited to the scope of the emergency.
State of Illinois Chief Procurement Office for General Services Emergency Purchase Extension Approval v. 24.1
EMERGENCY PURCHASE EXTENSION APPROVAL
State of Illinois Chief Procurement Office for General Services Emergency Purchase Extension Approval v.24.1 Page of Section 20-30(a) of the Procurement Code provides that a contract for an emergency may be extended beyond 90 calendar days with the approval of the chief procurement officer (CPO). Prior to execution of the extension, the CPO shall receive this completed form justifying the extension. The duration of the extension shall be limited to the scope of the emergency.
Extension Justification Actual or Estimated:
Has this emergency contract been extended before? Please detail in the space below:
BidBuy Reference # Amount Start Date End Date
1. Provide detail about the events that led the agency to conduct an emergency procurement:
2. What is the scope of work of the initial emergency contract? Please detail below:
3. Does this extension change the scope of work?
If yes, please detail below:
4. Provide justification for extending the original emergency contract:
5. Does this emergency contract correct or eliminate the emergency condition?
Please detail:
6. Explain why the need cannot be met through a competitive procurement process.
7. Is a competitive procurement in process to replace this emergency contract?
8. What is the effect of a denial of this extension request?
Signatures below cannot be delegated.
APO Signature I am requesting an extension of the requested emergency contract. I believe all statements herein are true and correct to the best of my knowledge.
SPO Signature CPO Signature 11.0.0.20130303.1.892433.887364
| DropDownList1: If no, explain why |
| DropDownList1: DOC - Corrections |
| DropDownList1: DOC - Corrections |
| DropDownList1: DOC - Corrections |
| CurrentPage: |
| PageCount: |
| VendorZip: 62966 |
| VendorState: IL |
| VendorCity: Murphysboro |
| VendorAddress: 511 Health Department Rd. |
| Vendor: Heartland Mechanical |
| AgencyZip: 62995 |
| AgencyState: IL |
| AgencyCity: Vienna |
| AgencyAddress: 6695 State Route 146 East |
| AgencyDivision: Vienna Correctional Center |
| ReferenceNumber: 24-426DOC-VIENN-P-63232 |
| AmountOfOriginal: 177593.50000000 |
| ActualOrEstimated2: Estimated |
| TextField15: 24-426DOC-VIENN-B-41858 |
| Start: 2/26/2024 |
| End: 05/26/2024 |
| ExpectedExtensionStartDate: 05/27/2024 |
| ExpectedExtensionEnd: 12/30/2024 |
| AmtExtensionExpenditure: 298093.50000000 |
| ActualOrEstimated3: Estimated |
| TextField5: Approved 0% BEP Goal Setting Review Form attached. Vienna CC looked for Vendors to meet this type of emergency and was only |
able to find Heartland Mechanical in the area.
| TextField7: |
| NumericField4: 0 |
| DateField3: |
| DateField4: |
| TextField8: |
| NumericField2: 0 |
| DateField5: |
| DateField6: |
| TextField9: |
| NumericField3: 0 |
| DateField7: |
| DateField8: |
| TextField6: Vienna CC boilers produce steam for facility hot water, cooling/heating and meal preparation for the facility. This emergency procurement will be a one-time procurement. The existing boiler is being replaced by CDB. |
| TextField13: Rental of 1 600 HP boiler to temporarily replace current facility boiler that is in need of replacement and inspection. |
| CheckBox7: 0 |
| CheckBox8: 1 |
| TextField1: |
| TextField2: Extending the original emergency contract for temporary boiler for Vienna Correctional Center is crucial to maintaining the daily operational needs for the facility. Vienna CC boilers produces steam for facility hot water, cooling/heating and meal preparation for the facility. This emergency procurement will be a one-time procurement. The existing boiler is being replaced by CDB and inspected to become operational again. |
| WhoAuthorizedWork: |
| CheckBox3: 0 |
| CheckBox4: 1 |
| TextField10: The emergency extension of the temporary boiler is needed until the new, permanent boiler becomes operational. |
| TextField12: Emergency procurement, needing extension until new boiler becomes operational. |
| CheckBox6: 0 |
| CheckBox5: 1 |
| DropDownList2: other, please explain below |
| TextField11: Vienna's new boiler is being replaced for full operation by CDB and is expected to be complete by the end of 2024. |
| TextField14: The denial of an extension request for the emergency temporary boiler could have several significant effects: |
Disruption of Services: Without access to a boiler house, Vienna Correctional Center would be unable to operate leading to disruptions in essential services such as hot water, cooling/heating and meal preparation for the facility.
| TextField3: 24-426DOC-VIENN-R-217504 |
| AuthorizedSignature: |
| TitleField: |
| SignatureField2: |
| DateField2: 2024-05-15 |
| CheckBox1: 1 |
| CheckBox2: 0 |
| TextField4: |
| SignatureField1: |
| DateField1: |
File details come from the government source that posted it. Updated .