VENDOR QUESTIONS AND ANSWERS~2.docx
DOCX document 16 KB Posted
- Solicitation number
- 21-422DNR-REALT-B-22025
- Issued by
- Boone County, Illinois
About this file
This document contains vendor questions and answers related to the Scope of Work for the Aqueduct #7 tree debris removal project, which is being managed by the Illinois Department of Natural Resources (IDNR). The project involves the removal of trees and debris blocking Aqueduct #7 on the Hennepin Canal State Trail in Bureau County, Illinois. All removed trees and debris will be stacked in a pile east of the creek on IDNR property.
The document does not provide any additional details about pricing terms, set asides, incumbents, funding requirements, or other salient information beyond the scope of work and vendor questions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Matton access draft maps2.pdf | ||
| AQ7 Meeting location.PNG | PNG image | |
| Aqueduct 7 photos.docx | DOCX document | |
| Matton access draft maps.pdf | ||
| 1SMALL CONSTRUCTION BID FORM~26.docx | DOCX document | |
| Standard CertificationsV.18.1~59.doc | DOC document | |
| Revised SOW - Hennipen Canal Debris Removal.docx | DOCX document | |
| 1Standard Terms and Conditions1~4.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ILLINOIS DEPARTMENT OF NATURAL RESOURCES
SCOPE OF WORK VENDOR QUESTIONS
Date: April 30, 2021 File# 1-21-018
LOCATION: Hennepin Canal State Trail, 16006 875 East St, Sheffield, Bureau County, IL
PROJECT TITLE: Aqueduct #7 tree debris removal
QUESTIONS FROM VENDOR:
1. Is all of the down/ removed material (i.e. trees removed, tree trimmings and wash down debris) to be stacked on site?
All trees that need to be removed to provide access to Aqueduct 7 and the trees blocking the aqueduct opening will be stacked in a pile east of the creek on IDNR property.