VA245-17-B-0086-A00006001.pdf

PDF 37 KB Posted

Attached to
Facility Backup Generator Proj #581-16-101 VAMC Huntington WV
Solicitation number
VA24517B0086
Issued by

About this file

VA245-17-B-0086 A00006 00 01 10 TOC.pdf

View the file

Other files

File Type Posted
VA245-17-B-0086-A00008003.pdf PDF
VA245-17-B-0086-A00008002.docx DOCX document
VA245-17-B-0086-A00007006.docx DOCX document
VA245-17-B-0086-A00007007.pdf PDF
VA245-17-B-0086-A00006002.pdf PDF
VA245-17-B-0086-A00006000.docx DOCX document
VA245-17-B-0086-A00006004.pdf PDF
VA245-17-B-0086-A00006006.pdf PDF
VA245-17-B-0086-A00006003.pdf PDF
VA245-17-B-0086-A00006007.pdf PDF
VA245-17-B-0086-A00006005.pdf PDF
VA245-17-B-0086-A00004000.docx DOCX document
VA245-17-B-0086-A00003002.pdf PDF
VA245-17-B-0086-A00003000.docx DOCX document
VA245-17-B-0086-A00003001.pdf PDF
VA245-17-B-0086-A00002000.docx DOCX document
VA245-17-B-0086-A00001003.pdf PDF
VA245-17-B-0086-A00001000.docx DOCX document
VA245-17-B-0086-A00001001.pdf PDF
VA245-17-B-0086-A00001002.pdf PDF
VA245-17-B-0086-011.pdf PDF
VA245-17-B-0086-014.pdf PDF
VA245-17-B-0086-010.pdf PDF
VA245-17-B-0086-015.pdf PDF
VA245-17-B-0086-016.pdf PDF
VA245-17-B-0086-012.pdf PDF
VA245-17-B-0086-009.docx DOCX document
VA245-17-B-0086-013.pdf PDF
VA245-17-B-0086-000.docx DOCX document
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA Huntington March 15, 2017 Install Back-Up Generator 100% Construction Documents Huntington, WV 25704 Project No. 581-16-101

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 11-15 01 33 23 Shop Drawings, Product Data, and Samples 07-15 01 35 26 Safety Requirements 10-14 01 45 29 Testing Laboratory Services 06-15 01 57 19 Temporary Environmental Controls 01-11 01 91 00 General Commissioning Requirements 10-15

DIVISION 02 – EXISTING CONDITIONS

02 21 00 Site Surveys 08-16 02 41 00 Demolition 02-15

DIVISION 03 – CONCRETE

03 30 00 Cast-in-Place Concrete 12-15

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 02-16 05 36 00 Composite Metal Decking 10-15 05 50 00 Metal Fabrications 07-14

DIVISION 09 – FINISHES

09 91 00 Painting 01-16

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 07-16 22 05 23 General-Duty Valves for Plumbing Piping 09-15 22 05 33 Heat Tracing for Plumbing Piping 09-15 22 07 11 Plumbing Insulation 09-15 22 14 00 Facility Storm Drainage 09-15

DIVISION 23 – MECHANICAL

23 05 11 Common Work Results for HVAC 02-15 23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment 02-15

23 05 13 Common Work Results for Facility Fuel Systems 02-17 23 05 41 Noise and Vibration Control for HVAC Piping and

Equipment 02-15

00 01 10-2

23 07 11 HVAC and Boiler Plant Insulation 02-15 23 08 00 Commissioning of HVAC Systems 06-13 23 09 23 Direct Digital Control for HVAC System 09-11 23 10 00 Facility Fuel Systems 02-15 23 10 01 Facility Fuel Systems Piping 02-15

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16 26 05 13 Medium-Voltage Cables 12-12 26 05 19 Low-Voltage Electrical Power Conductors and Cables 07-13 26 05 26 Grounding and Bonding for Electrical Systems 12-12 26 05 33 Raceway and Boxes for Electrical Systems 05-14 26 05 41 Underground Electrical Construction 12-12 26 05 73 Overcurrent Protective Device Coordination Study 12-15 26 08 00 Commissioning of Electrical Systems 06-13 26 13 13 Medium-Voltage Circuit Breaker Switchgear 12-12 26 22 00 Low-Voltage Transformers 12-15 26 23 13 Generator Paralleling Controls 12-12 26 24 16 Panelboards 05-14 26 32 13 Engine Generators 07-15 26 36 23 Automatic Transfer Switches 12-12 26 56 00 Exterior Lighting 05-14

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 06-15 27 05 26 Grounding and Bonding for Communications Systems 06-15 27 05 33 Raceways and Boxes for Communication Equipment &

Systems 06-15

27 11 00 Telecommunications Room Fittings 06-15 27 15 00 Communications Structured Cabling 01-16

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 09-11 28 05 13 Conductors and Cables for Electronic Safety and

Security 09-11

28 05 28.33 Conduits and Backboxes for Electronic Safety and Security

09-11

28 23 00 Video Surveillance 09-11

DIVISION 31 – EARTHWORK

31 20 00 Earthwork 10-12 31 63 26 Drilled Caissons

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 05-13 32 12 16 Asphalt Paving 09-15 32 31 13 Chain Link Fences and Gates 05-13

00 01 10-3

32 31 40 High Security Fences and Gates 08-16 32 90 00 Planting 10-11

DIVISION 33 – UTILITIES

33 40 00 Storm Sewer Utilities 10-11