VA101-17-R-0351-00011001.pdf
PDF 293 KB Posted
- Solicitation number
- VA10117R0351
About this file
VA101-17-R-0351 00011 Jacksonville RFI VII Responses.pdf
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Information
CONTRACTOR COMPANY:
RFI REQUESTER: RFI DATE:
PROJECT NAME: Jacksonville National Cemetery DESIGN FIRM:
PROJECT NUMBER:
928CM2003
CONST. PROJECT MANAGER: RFI RESPONDER: RFI DATE RESPONDED:
Requested Information/Clarification:
C&C Contractors LLC
Fred Pearson
1. Please clarify the mitigation requirements for this contract. Will we be responsible for design and/or construction of the masterplan mitigation area (~28 ac) or just enough to mitigate for the impacts related to this current construction project? If just for this phase, have there been any plans for that portion or is that entirely up to the DB team, as it appears that the VA Environmental Consultant has prepared exhibits for submittal to these agencies?
Government Response: All Phase 2 impacted wetlands as outlined in VA101-17- R-0351-00008001 shall be mitigated under this contract. Available mitigation locations are also identified and may be refined or redesigned at the approval of the Government. The Offeror is to assume all mitigation for Phase 1 has been completed at this time.
2. Who will be responsible to obtaining SJRWMD permit modifications?
Government Response: The Offeror (D/B Contractor) with Government coordination will modify the permit. The SJRWMD permit will only need to be updated if no deviations are present from the bridging document plan which corresponds with the initial permit requirements.
2a.The permit I am looking at is actually expired so it may require a whole new one which may require new wetland delineations as well.
Government Response: Initial investigation identifies the permit will only need to be updated.
3. Is there a USACE permit and if so who will be responsible to obtaining that permit modifications?
Government Response: If deviations from bridging document plan and existing SJRWMD permit are proposed, a modification may be required. Any modifications will be the responsibility of the Offeror with Government coordination.
4. The SJRWMD requires a Conservation Easement over the mitigation area. Who is responsible for the survey and documentation of that?
Government Response: The Offeror (D/B Contractor) with Government coordination.
5. Who is responsible for the Section 106 requirements?
Government Response: The Offeror (D/B Contractor.)
6. Does the VA have a separate Environmental Consultant as indicated on page 98 of the SOW who is preparing/completing the EA and will be updating the permits related to the wetlands?
Government Response:The VA has an Environmental Consultant preparing the EA. The D/B Contractor is responsible to satisfy all permitting conditions.
February 14 2018
David "Dave" MartinoDavid "Dave" Martino
CONSTRUCTION REQUEST
FOR INFORMATION
RFI No: ___7
February 20, 2018
Blank Page
File details come from the government source that posted it.