Utility_Information_Sheet.pdf

PDF 517 KB Posted

Attached to
Liberty Street, Douglas Street to Denton Street
Solicitation number
CT226-07
Issued by
Ada County, Idaho

About this file

This utility information document pertains to the Liberty Street project (Project #822009) involving multiple utility companies for infrastructure work between Douglas Street and Denton Street. The project requires approximately 120 working days from the Notice to Proceed (NTP) date for utility relocations, adjustments, and installations, with utilities potentially working on site throughout every project phase. The contractor must coordinate and accommodate work with various utility companies, understanding that project phasing may significantly impact utility relocation schedules.

The document lists contact information for multiple utility companies involved in the project, including Sparklight, Lumen, City of Boise departments (Parks and Rec, Public Works, Street Lights), Idaho Power, Intermountain Gas, Veolia, Zayo/Integra, Marathon, and Verizon Wireless. Each utility has specific representatives and contact details, with some having unique requirements such as Marathon's requirement for an inspector to be on-site when working around their lines and Verizon Wireless needing to move an antenna complex at Morris Hill. The Ada County Highway District (ACHD) General Conditions Section 26 applies to the project, and the ACHD Utility Supervisor, Scott Bennett, is the primary contact for questions.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Utility Information

Liberty St., Douglas St to Denton St

Project #822009

Utility Company Work Duration and Contact Information:

Utilities require approx. 120 working days from NTP date to complete their relocations, adjustments, and installations after clearing, grubbing, tree trimming, and removal. These utility windows may impact the Contractor’s critical path schedule by that amount of time, but utilities may be working on site for every phase of the project. Project phasing may have a significant effect on the schedule for utility relocations, adjustments, and installations.

Contractor must coordinate and accommodate work with utility companies and schedule required construction windows throughout the project.

ACHD General Conditions Section 26 applies. Contact ACHD Utility Supervisor, Scott Bennett, at

(208) 387-6259, with questions.

Utilities within the project:

Sparklight – Kevin Wakagawa – (208) 954-9219 – kevin.wakagawa@sparklight.biz Lumen – Vince Cook - (208) 735-5844 – vince.cook@centurylink.com or Aaron Kowal - (208)

985-4498 - aaron.kowal@lumen.com City of Boise Parks and Rec – Dan Falconer – (208) 608-7632 – dmfalconer@cityofboise.org City of Boise Public Works – Tiffany Wyer – (208) 608-7501 – twyer@cityofboise.org City of Boise Street Lights – Tom Marshall – (208) 608-7526 – tmarshall@cityofboise.org Idaho Power – Ethan Morgan – (208) 388-6510 – emorgan@idahopower.com or Dan

Hammerquist - (208) 388-2629 - dhammerquist@idahopower.com Intermountain Gas – Tony Galvan – (208) 488-5480 – Jose.Galvan@intgas.com Veolia – Al Christy - (208) 617-9433 - Alan.Christy@veolia.com replacing all main line and services and hydrants.

Zayo/Integra – Nick Kompaniet - (541) 450-2454 - nick.kompaniet@zayo.com Marathon – Midge Kline - (208) 373-2141 - makline2@marathonpetroleum.com or Brandin

Mann – (208) 954-4999 - bmann@marathonpetrolium.com inspector must be on-site when working around Marathon line.

Verizon Wireless – Donovan Waldenmyer – (208) 830-2253 – donovan.waldenmyer@verizonwireless.com has an antenna complex to move at Morris Hill.