Special_Provisions.pdf

PDF 2 MB Posted

Attached to
Liberty Street, Douglas Street to Denton Street
Solicitation number
CT226-07
Issued by
Ada County, Idaho

About this file

This document is a Special Provisions document for a roadway construction project by the Ada County Highway District (ACHD) for Liberty Street, spanning from Douglas Street to Denton Street, with the project number 822009. The project involves comprehensive street improvements, including excavation, aggregate base preparation, pavement installation, concrete work, irrigation improvements, landscaping, traffic control, pedestrian accessibility modifications, and various infrastructure enhancements. The project is scheduled for implementation in 2025, with specific construction requirements outlined for different phases and elements of the work, including detailed specifications for materials, installation methods, quality control, and measurement standards.

The project will be conducted under the 2017 Idaho Standards for Public Works Construction (ISPWC) and ACHD supplemental specifications, with Keller Associates serving as the project preparation consultant. Payment for the project will be made through various line items with specific measurement criteria, such as per cubic yard, per ton, per square yard, and per each, depending on the specific construction element. The contractor will be responsible for comprehensive site management, including stormwater control, pedestrian traffic management, surveying, and ensuring Americans with Disabilities Act (ADA) compliance throughout the construction process. The project includes specific provisions for utility coordination, Marathon Pipeline protection, and detailed quality control and testing requirements to ensure construction standards are met.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIAL PROVISIONS

LIBERTY STREET, DOUGLAS ST TO DENTON ST

PROJECT NO. 822009

Special Provisions to Modify the 2017 Idaho Standards for

Public Works Construction (ISPWC) & Ada County Highway

District Supplemental Specifications to the ISPWC

Prepared by

August 2025

This stamp certifies the attached modifications to the ISPWC and ACHD supplemental provisions. It does not certify the ISPWC or ACHD supplemental provisions.

9/5/2025

Docusign Envelope ID: BF88322B-7912-4D67-BCFA-9D5F67E5290C

Liberty St, Douglas St to Denton St | Project No. 822009 Page 1 of 39

GENERAL SPECIAL PROVISIONS

ACHD PROJECT NO. 822009, GIS No: CGSP205-16

Liberty St, Douglas St to Denton St

GENERAL NOTES

1. ACHD OWNED CONDUIT IMPACTS

ACHD-owned conduit may be shallow and located directly behind the curb or under the sidewalk. The Contractor’s method of sidewalk and/or curb removal shall be done in a manner to avoid damage to conduit and fiber. Any damage shall be repaired at the

Contractor’s expense.

2. AMERICANS WITH DISABILITY ACCESS (ADA) DURING CONSTRUCTION

The needs and control of all road users (motorists, bicyclists, and pedestrians within the highway and/or public right-of-way, including persons with disabilities in accordance with the

Americans with Disabilities Act of 1990 (ADA), Title II, Paragraph 35.130) through a temporary traffic control “TTC” zone shall be an essential part of highway construction, utility work, maintenance operations, and the management of traffic incidents. The primary function of TTC is to provide for the reasonably safe and efficient movement of road users through or around TTC zones while reasonably protecting workers, responders to traffic incidents, and equipment.

Temporary facilities, including reasonably safe pedestrian routes around work sites, are also covered by the accessibility requirements of the Americans with Disabilities Act of 1990

(ADA) (Public Law 101-336, 104 Stat.327, July 26, 1990. 42 USC 12101-12213 (as amended)).

Implementation of TTC plans and installation and maintenance of devices shall be the responsibility of the contractor performing the construction, alteration and/or maintenance of the highway or public right-of-way. Temporary traffic control for pedestrians shall meet the accessibility requirements (Standards) set forth in Part 6 of the MUTCD. When an existing continuous sidewalk or street crossing route cannot be maintained for pedestrians because of construction, either temporary walkways with curb ramps are to be provided, or the construction shall be phased to maintain access to the affected addresses. Contractors shall be allowed flexibility as long as the requirements are met.

The location of the construction project and whether or not accessible facilities are present shall also determine the extent of the needed temporary facilities. The contractor is only required to maintain practical continuity where accessible facilities already exist. On low speed rural roads that do not have sidewalks and are used by bicyclists, no additional measures are needed as the bicycles can share the available travel lanes with other traffic.

On moderate to higher speed rural roads, if a bike lane exists then it should be properly

Liberty St, Douglas St to Denton St | Project No. 822009 Page 2 of 39 detoured, complete with signage, to provide a safe route through or around the work area.

If a road or bridge project affects vehicular traffic to a business, residence, school or any other type of pedestrian generating location with existing accessible facilities, then pedestrian and handicapped access must be maintained.

A continuous route for all pedestrians, including the disabled and bicyclists, shall be maintained at all times. When existing pedestrian facilities are disrupted, closed, or relocated in a TTC zone, the temporary facilities shall be detectable and include accessibility features consistent with the features present in the existing pedestrian facility. The temporary route should enable pedestrians to bypass the construction site while minimizing the retracing of their steps or going significantly out of their way. Additional consideration must be given to the disabled since they may not have the physical or cognitive ability to improvise (e.g. balancing along the curb or a very narrow path) or use unofficial alternatives

(e.g. using an adjacent grass surface). Temporary routes must meet the accessibility guidelines of the ADA for permanent facilities and shall be marked with the proper signage.

Should existing crosswalks at signalized intersections be closed or made inaccessible, temporary crosswalks should be painted in an accessible location. Temporary signals should include pedestrian phases.

Contractors shall not block temporary walkways with contractor parking, materials piles, signs, rubble or rubbish. Construction equipment and equipment operation must be separated from the temporary walkways. At work zones where higher volumes of pedestrian traffic or school children exist, pedestrian fences or other protective barriers may be needed to prevent access into the construction area.

Detour and diversion routes, when used for pedestrians and bicyclists, should be evaluated for the following items:

• Direct conflicts between pedestrians and vehicular traffic, work vehicles, and other work activities must be reduced with protective barriers or continuous high contrast fencing (min 36” high with a 6” high toe board). See MUTCD 6F.68 and 6D.02

• Temporary pedestrian facilities should provide safe, accessible routes that replicate as nearly as practical the most desirable characteristics of the existing facility, and parallel the disrupted route whenever possible. A smooth, continuous hard surface should be provided throughout the entire length of the temporary pedestrian facility. There should be no curbs or abrupt changes in grade or terrain that could cause tripping or be a barrier to wheelchair use. The geometry and alignment of the facility should meet the applicable requirements of the Americans with Disabilities Act Accessibility

Guidelines (ADAAG) for Buildings and Facilities. See MUTCD 6D.01 and 6D.02

• Advance information placed at appropriate distances before the work zone allowing pedestrians to make timely decisions about routes through or around the work zone.

See MUTCD 6F.14

• Transition information allowing pedestrians to find a safe path through and around work zones, which is critical when the pathway is restricted, diverted or detoured. See

MUTCD 6F.14

Liberty St, Douglas St to Denton St | Project No. 822009 Page 3 of 39

• Work area information assisting in safe passage of pedestrians through the work zone.

This information is needed on all pedestrian routes except detours. See MUTCD 6F.14

• Exit information directing pedestrians back to the original route. See MUTCD 6F.14

• Crosswalk placement at intersections may need additional signage, temporary striping, traffic signal modification, pedestrian signals with audible alarms if justified, proper push button height, and ramps. See MUTCD 6H.29, 6F.80, and 4E.06

• Accommodations for other transit forms (busses, trains etc.) are made. See MUTCD

6D.02

• Requirements of the ADAAG and MUTCD are adhered to.

• Access is maintained to the affected businesses and residences.

3. WORK AROUND MARATHON PIPELINE

Retain and protect existing Marathon Pipeline (MPL). No vibratory compaction is allowed over the MPL. Contractor must always provide a minimum 24-inches of cover over the pipe during construction. Must have a representative from Marathon Pipeline when any work is to be done within 50’ of the pipeline. Coordinate work with Field Tech Brandin Mann 208-954-4999 or

Brian Sexton 217-994-4176.

4. ASPHALT AND CONCRETE CUTTING

Asphalt pavement and concrete cutting shall be incidental to other items of this contract.

Contractor shall ensure that cuts made in asphalt and concrete for trenches are parallel and do not wander or diverge from the intended line.

Dust produced by asphalt or concrete saw cuts shall be collected using a high-powered vacuum dust control system, eliminating the dust from entering the atmosphere. The suction device shall be attached to the cutting equipment or positioned to a assure a maximum amount of dust will be collected before it can be released into the atmosphere. The cost to ensure dust is collected during asphalt and concrete cutting shall be considered incidental to the cost of the project and no additional compensation will be made.

5. BASIS OF PAYMENT

Except as modified herein, the various roadway work called for on the Bid Schedule shall be performed, measured, and paid for as indicated on said Bid Schedules and as provided in the

2020 IDAHO STANDARDS FOR PUBLIC WORKS CONSTRUCTION (ISPWC) and the latest supplements. The Contractor is required to have the current edition of the ISPWC standards to perform this work. Unless otherwise specified herein, all plan quantities are based upon in-place, completed and accepted units.

Liberty St, Douglas St to Denton St | Project No. 822009 Page 4 of 39

6. CONFLICTING PAVEMENT MARKINGS

All conflicting pavement markings shall be completely obliterated using an ACHD approved method prior to applying permanent pavement markings. The cost of performing all obliteration shall be considered incidental to other items and no separate pay item will be included for obliteration of pavement markings.

7. CONNECTING PIPES

Connecting new pipes, manholes, irrigation structures\ditches and catch basins to existing pipes, manholes, irrigation structures\ditches and catch basins is incidental to other work and no additional compensation will be made.

8. CONSTRUCTION STAGING

The Contractor shall furnish ACHD with a detailed construction staging plan based on their anticipated approach to construction activities. This plan and implementation will be the responsibility of the contractor. Final approval of the staging plans and revisions thereof must be granted by ACHD prior to implementation.

Staging plans that may be contained within the project plans are primarily for bidding purposes only. The contractor may utilize any staging plans contained within the bid documents as a basis for staging but the final staging plan will be provided by the contractor prior to construction activities.

The cost associated with providing the necessary staging plans will be considered incidental to

9. DAMAGED AREAS BEYOND SPECIFIED CONSTRUCTION LIMITS

Damage to any areas or items not specifically identified for removal, including the existing pavement, sod, sprinklers, and landscaping in the contract documents shall be promptly repaired by the contractor. The cost to complete such repairs shall be considered incidental to the cost of the project and no additional compensation will be made.

The Contractor shall take special care when removing material and working near existing trees to retain and protect all existing trees and vegetation not specifically called out for removal. This includes but is not limited to tree trunks, branches, and root systems.

10. EXCESS SITE MATERIAL

The Contractor shall be responsible for providing a site for the disposal of excess or unsuitable materials. If bituminous material is to be disposed of, the site shall meet the requirements of the Idaho Department of Environmental Quality. All excess material sites shall be approved by ACHD. No separate payment will be made for the acquisition or operation of the sites, or for loading, hauling or unloading the materials at the site.

Liberty St, Douglas St to Denton St | Project No. 822009 Page 5 of 39

11. INFORMATION GIVEN PRIOR TO AWARD

Oral explanations, instructions and interpretations given to bidders prior to award of contract will not be binding. It is the ACHD’s intent to provide all bidders equal opportunity to access and acquire all available pertinent information necessary to formulate a responsive bid. Any information, specifications, plans, data, or interpretations that ACHD discovers is lacking and may be important to all bidders will be furnished in the form of an addenda, the receipt of which shall be acknowledged by the bidder.

12. PROPERTY OWNER COORDINATION

Contractor shall coordinate items of work affecting adjacent property owners, including but not limited to landscape removal and replacement, sprinklers, irrigation facilities, fencing, sod care, and trees. Property access coordination shall be conducted according to General

Condition 49 – PROPERTY ACCESS POINTS.

13. PAY QUANTITIES

By the 25th of each month the Contractor shall supply quantities that are to be paid for that month. Each bid item shall be accompanied with the appropriate backup documentation on how the pay quantity was calculated. This shall include such documentation as, but not limited to; stationing, location, tallied weight tickets, sketch of calculated areas, and/or any other appropriate documentation to verify the pay quantity request. ACHD will verify quantities prior to remitting payment. Items failing to have the appropriate backup supporting documentation will not be paid until the information is supplied. The cost associated with providing the above outlined documentation shall be considered incidental to the project and no additional compensation will be granted.

All Pay quantities shall also adhere to the criteria outlined in General Condition 41 – MANNER

OF PAYMENT.

14. POWER SUPPLY

If indicated on the plans or directed by ACHD, the contractor shall install a three-wire electrical service to be used at 120/240 volts, single phase, 60 hertz AC between the power supply and the service cabinet. The contractor shall install a junction box a maximum of two

(2) feet from the power supply. The distance from the power source to the service cabinet shall not exceed 300’ without approval from the ACHD Signal Coordinator. The contractor shall coordinate with Idaho Power for the power connection location. The District shall be responsible for all Idaho Power fees related to power supply and connection. The contractor shall have Idaho Power submit paperwork to the ACHD Utility Coordinator for the connection a minimum of sixty (60) working days prior to activating the new power supply. The contractor shall be responsible for all electrical permit fees.

15. SHOP DRAWING REVIEW

Plans show details of all structures, lines, grades, typical cross sections of the roadway, location and design of all structures and a summary of items appearing on the proposal. The

Liberty St, Douglas St to Denton St | Project No. 822009 Page 6 of 39

Contractor shall keep one set of plans available on the work site at all times.

The Contractor will supplement the plans by such working drawings necessary to adequately control the work. Working drawings shall be submitted to the Engineer for review in advance of the start of the proposed work. The Contractor shall allow sufficient Engineer review time and corrections resubmitted by the Contractor without impacting the approved construction schedule. The drawings shall be on sheets measuring 22 in. x 34 in. Unless otherwise stated in the contract, the Engineer will require up to 15 business days from the date the submittals or re-submittals are received until they are returned to the Contractor. No extension to contract time will be given due to re-submittals or the failure of the Contractor to provide any information necessary in a timely fashion. If necessary, drawings will be signed and sealed by a Professional Engineer licensed to practice in the State of Idaho.

This review time will increase if the drawings submitted do not meet the contract requirements or contain sufficient details.

For structures, six sets of working drawings shall be furnished and shall include stress sheets, shop drawings, erection plans, coffer dam plans, bending diagrams for reinforcing steel, or any other supplementary plans or similar data required of the Contractor. All structural drawings provided shall be sealed by a Professional Engineer licensed to practice in the State of Idaho.

Working drawings shall be approved before beginning the work covered by the submitted drawings. Such approval is only for general conformance with the information given in the contract documents and does not relieve the Contractor of responsibility for correctness of the details and dimensions, nor does it waive any requirements of the specifications.

The contract price shall include the cost of furnishing all submitted shop and/or working drawings.

16. STORMWATER FLOWS

The Contractor is responsible for transmitting existing stormwater and irrigation flows during construction. All costs associated with transmitting existing flows, including flows from the temporary water quality best management practices on the project, shall be considered incidental to other items of work and no additional compensation will be made.

17. STORM WATER MANAGEMENT

Contractor shall implement Best Management Practices (BMPs) controls to protect storm sewer systems and Waters of the United States located on or near project limits. Contractor shall follow the requirements of the Idaho Pollutant Discharge Elimination System (IPDES)

Construction General Permit (CGP) and/or ACHD’s Construction Site Discharge Control (CSDC)

Program as required. The contractor is required to implement and maintain BMPs through life of contract. The removal of all temporary construction BMPs after completion of all required work to final stabilization is considered incidental to this project.

The ACHD CSDC Plan shall meet the CSDC Program requirements listed in Sections 8305 to

Liberty St, Douglas St to Denton St | Project No. 822009 Page 7 of 39

8306 of the ACHD Policy Manual https://www.achdidaho.org/Documents/ACHDpolicyManual/7000to9000/Section8300_Cons tructionSiteDischargeControlProgram.pdf.

The CSDC Plan shall include measures to protect the existing ACHD storm drain systems inside and outside the project boundaries from mud, dust, debris, and other pollutants generated or transported due to this project. All measures will also be implemented to protect any “Waters of the United States” inside or outside of the project boundaries. “Pollutants” are defined in

Section 8302 of the ACHD Policy Manual.

The IPDES CGP Stormwater Pollution Prevention Plan (SWPPP) shall meet the CGP requirements. The CGP can be found on the Idaho Department of Environmental Quality

(IDEQ) website at:

https://www2.deq.idaho.gov/admin/LEIA/api/document/download/16509.

BMPs for controlling pollutant transport from the construction site and activities can be found in a number of publications and locations including, but not limited to:

• Idaho Department of Environmental Quality, Idaho Catalog of Storm Water Best

Management Practices at: https://www.deq.idaho.gov/water-quality/wastewater/storm-water/ or Phone: (208) 373-0502

• United States Environmental Protection Agency – Region 10, Resources and Tools at:

https://www.epa.gov/npdes/construction-general-permit-resources-tools-and-templates or Phone: (800) 424-4372

• Idaho Transportation Department, Best Management Practices (BMP) Manual at:

https://itd.idaho.gov/env/?target=resources or Phone: (208) 334-8476

Payment for this item will be made under the appropriate bid item numbers.

18. SUBGRADE

It shall be the Contractor’s responsibility to maintain the integrity for the exposed subgrade.

Degradation due to his operations or weather shall be remedied under the guidance of a geotechnical engineer.

All costs to maintain and repair including, geotechnical engineering, etc. shall be incidental to

19. TRAFFIC CONTROL

Contractor shall furnish ACHD with a detailed traffic control plan based on their anticipated approach to construction activities. This plan and implementation will be the responsibility of the contractor. Final approval of the traffic control plan and revisions thereof must be granted by ACHD prior to implementation. It will be the sole discretion of the ACHD Resident Engineer, Liberty St, Douglas St to Denton St | Project No. 822009 Page 8 of 39 or designated representative, to determine if the advanced construction signing plan contained in the contract documents shall be approved as a traffic control plan.

Traffic control plans and/or advanced construction signing plans that may be contained within the project plans are primarily for bidding purposes only.

Local and emergency vehicle access shall be maintained at all times, unless otherwise indicated in the contract documents. All traffic control items not specifically listed in the bid schedule shall be incidental to this contract, and no additional compensation will be made. Short term lane closures shall be only as approved by the Resident Engineer.

20. TRENCHING

All excavation and trenching shall meet OSHA requirements. Trenches shall be backfilled and properly compacted, closed at the end of each day, and barricaded, as needed.

21. WARNING AND REGULATORY SIGNS

Existing warning and regulatory signing shall be retained and protected throughout the project limits unless otherwise noted. This may require multiple relocations, which will be incidental to other bid items. Existing warning and regulatory signs that are designated for removal and replacement and do not conflict with construction traffic control signs shall be maintained during construction and, if necessary, relocated to locations where the signs are visible to traffic and serve their original purpose.

22. CONSTRUCTION OF IRRIGATION IMPROVEMENTS

All irrigation improvements shall be constructed during the irrigation off-season, generally

October 15th to March 15th. All irrigation improvements shall be completed prior to March 15th, 2026. Contractor shall meet all requirements stated in License Agreements obtained from

Irrigation Districts and/or Irrigation users.

23. WORKING HOURS

Unless otherwise specified here the Regular working hours for this contract shall adhere to the criteria outlined in General Condition 40 – WORK HOURS/TIME OF COMPLETION.

24. QUALITY CONTROL/QUALITY ASSURANCE

SECTION 100 – General Conditions

Add the following:

Ada County Highway District Quality Control and Quality Assurance Procedure

Definitions

Quality Assurance (QA) is defined as the process or set of processes used to measure and

Liberty St, Douglas St to Denton St | Project No. 822009 Page 9 of 39 assure the quality of a product and/or workmanship. This encompasses ACHD’s oversight of the Developer’s/Contractor’s processes and materials. This includes review of the inspector, sampler, tester and laboratory qualifications (per ACHD Independent Assurance Program defined below); verifying the results of the quality control and process control testing; and inspecting for conformance to plans and specifications.

Quality Control (QC) is defined as the actions necessary to produce quality workmanship and materials. QC includes, but should not be limited to, inspection of the production and placement operations, quality control and process control testing and inspection of the finished product. QC is the responsibility of the Developer/Contractor. No separate payment will be made for this work. If quality control testing is not being performed at the required frequency, ACHD may stop production of work until the tests are supplied, or ACHD determines the work can proceed.

Quality Control Testing and Process Control Testing are defined as the testing and inspections conducted by the Developer/Contractor to determine if the construction materials have been produced and placed in compliance with the project specifications and applicable standards. Process control testing is conducted to demonstrate that the construction materials being produced and used continue to meet the requirements for the product.

Independent Assurance Program (IAP) is the process provided by ACHD, through trained and certified staff, to ensure that all testing is performed correctly and testing equipment is functioning and calibrated properly.

Acceptance is determined by the QA test results, in combination with the assurance that the

Developer/Contractor has satisfied the specification requirements for materials quality and workmanship, with the exception of Superpave Hot Mix, as specified below. In addition to the specified testing results, visual inspection of the end product is also taken into consideration in determining acceptance. Acceptance will be determined by ACHD. All samples required for QA testing will be supplied by the Developer/Contractor to ACHD. Prior to obtaining a sample for QA testing, ACHD shall be notified of when and where the sample will be taken from. ACHD will determine if it needs to witness the obtaining of the QA sample. Superpave Hot Mix acceptance shall be based on ACHD’s supplement to the ISPWC

Section 814 under Part 4.2.

Construction Testing and Inspection Responsibilities

Quality Control

A. The Developer/Contractor shall be responsible for the Quality Control of all construction processes and materials quality. The Developer/Contractor will be responsible for quality throughout the construction process. Therefore, the Developer/Contractor must ensure that the materials and workmanship provided by themselves, Subcontractors, Suppliers, and

Producers meet all pertinent specifications. All tests listed under Quality Control in the

Minimum Testing Frequency Table are required for quality control, however only tests listed as Acceptance shall be used in determining pay.

Liberty St, Douglas St to Denton St | Project No. 822009 Page 10 of 39

B. The Quality Control laboratory must be approved by the Idaho Transportation Department.

All testing personnel and facilities used by the Developer/Contractor must be currently certified by the Western Alliance for Quality Transportation Construction (WAQTC) and by the ACHD Independent Assurance Program. All test results must be supplied to ACHD the next working day after the test was performed. All Quality Control tests will be supplied to

ACHD directly from the lab performing the tests. Tests results shall have the ACHD project/permit number listed and be sequential.

C. Quality Control Testing must occur in a random frequency and at a minimum, at the intervals specified in the table provided in the corresponding ISPWC sections. The

Developer/Contractor shall determine the random locations. Upon request, documentation must be supplied showing how the random numbers/locations were determined by the

Developer/Contractor. All random sampling for ACHD will be done by the

Developer/Contractor and witnessed by an ACHD representative.

D. For gradation testing by the Developer/Contractor during production, each sample size shall be taken per AASHTO T2, except the sample size shall be doubled. The sample obtained shall be split in accordance with AASHTO T248, and half of it shall be marked with an ID number and tested by the Developer/Contractor. The other half of the sample shall be sealed in a canvas sack or plastic bucket, and marked with the ID number, stored in a weather protected container, and reserved for use in retesting if needed. Material shall be retained until written notification is given by ACHD that it can be discarded.

E. Acceptance, gradation, binder content and volumetrics for plant mix pavement and/or

Superpave Hot Mix asphalt shall be performed on the loose mix sampled from the roadway, haul unit, or an approved sampling method at the Hot Plant. At the start of each project the location for sampling shall be determined by ACHD and all samples for the project shall be obtained from that determined location. The hot mix sample used for asphalt binder content, gradation and volumetric testing shall be doubled in size. The sample shall be split in accordance with AASHTO R47 and half of the sample shall be used for the appropriate testing. The other half of the sample shall be sealed in a box, marked with the sample ID number, stored in a weather protected enclosure, and reserved for use in retesting if needed. Material shall be retained until written notification is given by ACHD that it can be discarded.

Quality Assurance

A. ACHD shall oversee the Developer’s/Contractor’s fulfillment of the QC requirements, and independently verify that the QC test results being submitted by the Developer/Contractor are representative of the workmanship and product quality. ACHD will also be responsible for determining general project acceptance based on conformance to the approved plan and specifications.

Liberty St, Douglas St to Denton St | Project No. 822009 Page 11 of 39

B. ACHD will perform random Quality Assurance testing at the intervals specified in Minimum

Testing Frequency table.

C. Acceptance of material will be based on the Quality Assurance test performed by ACHD. If no QA test is performed, acceptance will be based on the QC tests results and inspections as determined by ACHD.

D. ACHD will perform random inspections of material storage and handling practices.

Dispute Resolution

A. The dispute resolution process is to resolve differences between the Developer/Contractor and ACHD when a disagreement regarding the test results occurs.

B. When a failing QA test occurs, production may be suspended until the differences are resolved and ACHD is satisfied.

C. ACHD may run one or more tests of the split material from the QC process to help resolve differences.

D. When ACHD and the Developer/Contractor are unable to resolve the differences, a Third

Party prequalified independent lab shall be brought in to verify testing.

E. ACHD will hire the Third Party independent lab. If ACHD tests are found to coincide with the independent lab, ACHD will not grant additional contract time due to any delays in production and the Developer/Contractor shall bear the costs associated with the Third Party resolution. Likewise, if the Developers/Contractors tests are found to coincide with the independent lab, ACHD will bear the costs associated with Third Party resolution and will grant additional time for any delay caused by this additional testing.

F. For hot mix density dispute testing, cores shall be obtained by the Third Party from the same locations as the nuclear gauge tests.

Independent Assurance Program

A. ACHD practices the standards of the Western Alliance for Quality Transportation

Construction (WAQTC).

B. ACHD Independent Assurance personnel may observe testers and verify that the equipment and techniques used for the required testing are calibrated and performing accurately, per

WAQTC. During construction, it may be necessary for an IAP representative to verify the reliability of the tester by witnessing sampling and testing, and by splitting samples and comparing results.

C. All independent testing laboratories to be used shall be pre-qualified by ACHD prior to construction. To request an inspection and certification, contact the ACHD Lab Coordinator at 387-6310 to schedule. Laboratories that are currently certified by the Idaho

Liberty St, Douglas St to Denton St | Project No. 822009 Page 12 of 39

Transportation Department (ITD) can provide ACHD with their current certification as confirmation of qualification. In the event that the lab is ITD certified; a facility inspection by

ACHD IAP personnel may still be required.

Price Adjustment for Non- Compliant Materials or Products

A. When material fails to meet the required specifications, they will be subject to a price adjustment or rejection. ACHD may also request a lengthened warranty period.

B. ACHD will, in its sole, discretion determine the price adjustment or rejection.

C. The determined price adjustment or rejection of material shall be applied to the quantity of material that is represented by the non-compliant test results, as outlined in the Minimum

Testing Frequency table.

Minimum Testing Requirements

A. The requirements outlined herein are the established minimum acceptance requirements for materials used in standard applications and paid for under standard bid items. For special provision items, material used in non-standard, non-roadway, temporary applications, or small quantities of materials, alternative materials acceptance requirements will be determined as discussed herein or as specified in the contract documents, or as otherwise approved by ACHD. Material placed without appropriate testing shall be subject to a price deduction or rejected as determined by ACHD.

B. Minimum testing frequencies are included in the Minimum Testing Frequency table. The

Developer/Contractor frequencies may only be altered by Change Order approved by ACHD.

ACHD may elect to increase its own testing frequency at any time. Testing frequency should be increased when accepting material from newly developed sources or those with varying results.

C. Material source approval requirements are not listed in this document. All fill and aggregate material imported to the project must be obtained from ACHD or ITD approved materials sources.

D. Based on inspection and without regard for testing frequency, ACHD may isolate and reject obviously defective material.

E. When the material is not listed in the Minimum Testing Frequency table and not identified in the ISPWC, acceptance shall be determined by ACHD.

F. When the material is required by the Contract to meet a given specification, such as ASTM or

AASHTO, acceptance of material will, at a minimum, require a manufacturer’s certification. A partial list of such material is outlined in the List of Miscellaneous Material Accepted on the

Basis of Manufacturer’s Fabricator’s Certification.

Liberty St, Douglas St to Denton St | Project No. 822009 Page 13 of 39

Small Quantities

A. ACHD may accept small quantities of certain materials without sampling and testing. The determination to accept materials using this provision rest solely with ACHD.

B. The following are not eligible for small quantity acceptance:

i. Concrete with a specified strength of greater than 3000 psi.

ii. Paving on the roadway with quantities above 100 ton.

C. Materials may be accepted as a small quantity if the estimated quantity is less than the minimum QC testing frequency. The small quantity exception may be used on pavement items such as; small patches, utility repairs, pavement placed outside the traveled way

(driveways, approaches, mailbox turnouts, asphalt sidewalk and curb), and temporary pavement.

D. The minimum requirements that must be met for small quantities includes; approved sources, mix design, material certifications, inspection, and a core for density acceptance of mainline and intersection paving less than 100 tons.

Liberty St, Douglas St to Denton St | Project No. 822009 Page 14 of 39

Liberty St, Douglas St to Denton St | Project No. 822009 Page 15 of 39

Liberty St, Douglas St to Denton St | Project No. 822009 Page 16 of 39

Liberty St, Douglas St to Denton St | Project No. 822009 Page 17 of 39

Liberty St, Douglas St to Denton St | Project No. 822009 Page 18 of 39

ROADWAY SPECIAL PROVISIONS

1. 202.4.1.A.1 – EXCAVATION (PLAN QUANTITY)

ON PAGE 14 OF SECTION 202 OF THE ISPWC, PART 4.1.A, replace the entire section with the following:

This item shall be paid for by the cubic yard on a plan quantity basis with no final measurement, for which the price and payment shall constitute full compensation for excavating, loading, hauling, spreading, blending, shaping, drying, watering and compacting excavated material that is acceptable for the use as on-site borrow for embankment fill, and for all tools, labor, equipment, materials and incidentals necessary to complete the work and all appurtenances not itemized on the Bid Schedule.

Payment for this item will be made under:

202.4.1.A.1 – Excavation (Plan Quantity) ....................... Per Cubic Yard

2. 202.4.5.A.1 – UNSUITABLE MATERIAL EXCAVATION (PLAN QUANTITY)

ON PAGE 17 OF SECTION 202 OF THE ISPWC, PART 4.5.A, add the following:

ITEM 29, “VARIATIONS IN QUANTITIES”, ON PAGE GC15 OF THE ACHD GENERAL

CONDITIONS, SECOND PARAGRAPH, shall not apply to the 202.4.5.A.1 bid item.

Payment for this item will be made under:

202.4.5.A.1 – Unsuitable Material Excavation (Plan Quantity)……………….. Per Cubic Yard

3. 602.4.1.K.1.12B – 12” DIA. GRAVITY IRRIGATION SLIDE & GATE TYPE C-8

ON PAGE 11 OF SECTION 602 OF THE ISPWC, PART 4.1.K, add the following:

This item shall include all costs associated with furnishing and installing canal gate in the irrigation boxes at the locations shown on the construction plans. The slide gates shall be waterman C-8 style or approved equal.

Payment for this item will be made under:

602.4.1.K.1.12B – 12” Dia. Gravity Irrigation Slide & Gate, Type C-8 ………….... Per Each

4. 602.4.1.L.1 – 6” DIA. GRAVITY IRRIGATION VALVE TYPE OVERFLOW RISER

ON PAGE 11 OF SECTION 602 OF THE ISPWC, PART 4.1.L, add the following:

This item shall include all costs associated with furnishing and installing an overflow riser at the end of pipes at the locations shown on the construction plans. The overflow riser valve shall be Waterman Overflow Riser Valve style or approved equal.

Payment for this item will be made under:

602.4.1.L.1 – 6” Dia. Gravity Irrigation Valve, Type Overflow Riser ………………… Per Each

Liberty St, Douglas St to Denton St | Project No. 822009 Page 19 of 39

5. 706.4.1.F.1 – CONCRETE DRIVEWAY APPROACH

ON PAGE 7 OF SECTION 706 OF THE ISPWC, PART 4.1.F, add the following:

This item includes all labor, equipment and materials necessary to construct a 6” thick concrete driveway approach as shown on project plans. The contractor shall limit any driveway closures to 3-days without prior approval from ACHD and the Property Owner.

Excavation & gravel base shall be paid separately.

Payment for this item will be made under:

706.4.1.F.1 – Concrete Driveway Approach .................... Per Square Yard

6. 706.4.1.G.1 – CONCRETE REPAIR

ON PAGE 7 OF SECTION 706 OF THE ISPWC, PART 4.1.F, add the following:

This item includes all labor, equipment and materials necessary to construct a 6” thick concrete repair slab over 4” of ¾” Crushed Aggregate Base behind driveway approaches at the locations identified in the plans. Concrete shall be class 4000 psi. The contractor shall limit any driveway closures to 3-days without prior approval from ACHD and the Property

Owner.

Excavation & gravel base shall be paid separately.

Payment for this item will be made under:

706.4.1.G.1 – Concrete Repair ........................................ Per Square Yard

7. 706.4.1.H.1 – PEDESTRIAN RAMP W/ DETECTABLE WARNING DOMES

ON PAGE 7 OF SECTION 706 OF THE ISPWC, PART 4.1.H, add the following:

This item shall include all costs associated with completion of the required concrete pedestrian ramps. All pedestrian ramps shall have a four (4) foot wide throat. All pedestrian ramps shall include full width prefabricated truncated domes as shown on the project plan sheets. Refer to ISPWC standard drawings SD-712*, ACHD Supplementals, and project plans for additional details. All pedestrian ramps shall be constructed in full compliance with current requirements of the Americans with Disabilities Act (ADA). Truncated domes are considered incidental to this bid item and no additional compensation will be granted.

Payment for this item will be made under:

706.4.1.H.1.A.A – Pedestrian Ramp w/ Detectable Warning Domes, Type SD-712A……………….Per Each

706.4.1.H.1.D.C1– Pedestrian Ramp w/ Detectable Warning Domes, Type SD-712D, C1………………Per Each

706.4.1.H.1.E.G1– Pedestrian Ramp w/ Detectable Warning Domes, Type SD-712E, G1………………Per Each

Liberty St, Douglas St to Denton St | Project No. 822009 Page 20 of 39

8. 801.4.1.A.1.3 – 3” MINUS UNCRUSHED AGGREGATE BASE

ON PAGE 2 OF SECTION 801 OF THE ISPWC, PART 2.1 – DESCRIPTION, add the following:

E. The material shall have a minimum R-value of 70.

ON PAGE 6 OF SECTION 801 OF THE ISPWC, PART 4.1.B, add the following:

The pay quantity for this item was calculated using a unit weight of 135 pcf at a moisture content of 7 percent.

Payment for this item will be made under:

801.4.1.B.1.3 – 3” Minus Uncrushed Aggregate Base ..... Per Ton

9. 802.4.1.A.1 – CRUSHED AGGREGATE FOR BASE - TYPE I (PLAN QUANTITY)

ON PAGE 7 OF SECTION 802 OF THE ISPWC, PART 4.1, add the following:

Material will be calculated using plan quantity.

Payment for this item will be made under:

802.4.1.A.1 – Crushed Aggregate Base - Type I (Plan Quantity)…. Per Cubic Yard

10. 814.4.1.A.1 – PLANT MIX PAVEMENT – SUPERPAVE SP-3

REFERENCE 2020 ACHD SUPPLEMENT TO THE 2020 ISPWC

SP-3 plant mix asphalt pavement shall utilize PG 64-28 liquid asphalt with 0.5% anti-strip. The aggregate shall have a nominal maximum aggregate side of 1/2” (inch).

814.4.1.A.1 – Plant Mix Pavement – Superpave SP-3 ................... Per Ton

11. 1003.4.1.B.1 – BIOFILTER BAG (FIBER WATTLE)

ON PAGE 3 OF SECTION 1003 OF THE ISPWC, PART 4.1.B, add the following:

ITEM 29, “VARIATIONS IN QUANTITIES”, ON PAGE GC15 OF THE ACHD GENERAL CONDITIONS, SECOND PARAGRAPH, shall not apply to the 1003.4.1.B.1 bid item.

1003.4.1.B.1 – Biofilter Bag (Fiber Wattle) .................................... Per Each

12. 1006.4.1.C.1 – INLET PROTECTION

ON PAGE 3 OF SECTION 1006 OF THE ISPWC, PART 2.1, add the following:

B. Inlet protection shall be Stormguard Sediment Catch Basin Inserts installed according to manufacturer’s recommendations or approved equal.

Payment will be made under:

1006.4.1.C.1 – Inlet Protection ...................................................... Per Each

Liberty St, Douglas St to Denton St | Project No. 822009 Page 21 of 39

13. 1103.4.1.B.1 – TRAFFIC CONTROL SIGNS

ON PAGE 7 OF SECTION 1103 OF THE ISPWC, PART 4.1.B, add the following:

Provide and install Class “A” construction signing to direct vehicular traffic in and around the project site, including informational signage, per the MANUAL ON UNIFORM TRAFFIC

CONTROL DEVICES, most current edition. Signs that will be in place longer than 3 days shall be permanent sign installations. Contractor shall bag or cover signs when not in use.

Contractor shall refer to the ATSSA pamphlet called Quality Standards for Work Zone Traffic

Control Devices.

Payment will be made by the square foot of sign acceptably installed, initial installation only.

1103.4.1.B.1 – Traffic Control Signs .............................................. Per Square Foot

14. SSP 06013 – STORMWATER MANAGEMENT PLAN PREPARATION AND IMPLEMENTATION

Description: This item shall consist of all work associated with contractor plan preparation and approvals to meet the requirements of the Idaho Pollutant Discharge Elimination System

(IPDES) Construction General Permit (CGP) and/or ACHD’s Construction Site Discharge Control

(CSDC) Program as required. The contractor is considered an operator having day-to-day control as defined in the CGP; therefore, the contractor is a co-permittee with ACHD in the implementation of the CGP requirements. A Stormwater Pollution Prevention Plan (SWPPP) will be accepted by ACHD in lieu of the CSDC Plan provided that the SWPPP meets the CSDC

Program requirements listed in 8305 and 8306 of the ACHD Policy Manual.

https://www.achdidaho.org/Documents/ACHDpolicyManual/7000to9000/Section8300_Cons tructionSiteDischargeControlProgram.pdf .

Workmanship: The contractor is responsible for the completion, submittal, and implementation of the ACHD provided SWPPP drawing and narrative, filing of the Notice of

Intent (NOI), and filing of the Notice of Termination (NOT). Access for completing an electronic NOI and NOT can be found on the Idaho Department of Environmental Quality

(IDEQ) IPDES E-Permitting website: https://www2.deq.idaho.gov/water/IPDES.

The CGP can be found on the Idaho Department of Environmental Quality (IDEQ) website at:

https://www2.deq.idaho.gov/admin/LEIA/api/document/download/16509. The SWPPP shall have been prepared and submitted to ACHD for acceptance prior to the filing of the NOI.

Prior to filing the NOT, the conditions listed in Part 8.2 (Conditions for Terminating CGP

Coverage) of the CGP shall be met.

Once a SWPPP has been prepared, the Contractor and ACHD shall both submit an electronic

NOI on the website listed above. There is a fourteen-calendar day wait after the acknowledgement of receipt has been posted on the IDEQ website for the SWPPP to be considered approved and construction allowed to commence.

Liberty St, Douglas St to Denton St | Project No. 822009 Page 22 of 39

Prior to starting construction, the ACHD accepted SWPPP/CSDC Plan must be implemented.

No Construction Activity or Land Disturbing Activity will be allowed to commence until the

Contractor has fully implemented the accepted SWPPP/CSDC Plan as required by the District and set forth in the ACHD Policy Manual.

Additionally, the contractor is responsible for installing, maintaining, and removing all Best

Management Practices (BMPs) and for all documentation required to keep the SWPPP current.

For compliance with the District’s CSDC Program, the SWPPP/CSDC Plan should address all potential pollutants outlined in the ACHD Policy Manual.

A Rainfall Erosivity Waiver (Waiver) is available and defined in Appendix B Part B.1 of the CGP.

If the Waiver is utilized the Waiver shall have been prepared and submitted to ACHD for acceptance prior to the filing of the Waiver through the IPDES E-Permitting website. If the conditions on which the Waiver is based change, the Contractor is responsible for updating the Waiver and/or development, including filing for NOI and NOT, and implementation of a

SWPPP.

BMPs for controlling pollutant transport from the construction site can be found in a few publications including, but not limited to:

a) Idaho Department of Environmental Quality, Idaho Catalog of Storm Water Best

Management Practices at: https://www.deq.idaho.gov/water-quality/wastewater/storm-water/ or Phone: (208) 373-0502

b) United States Environmental Protection Agency – Region 10, Resources and Tools at:

https://www.epa.gov/npdes/construction-general-permit-resources-tools-and-templates , or phone: (800) 424-4372

c) Idaho Transportation Department, Best Management Practices (BMP) Manual at:

https://itd.idaho.gov/env/?target=resources, phone: (208) 334-8476

Measurement and Payment: Payment for work items to implement the SWPPP or CSDC shall be per other specific bid items noted in this contract.

Payment for this plan preparation and approval item will be made under:

SSP 06013 – Stormwater Management Plan Preparation & Approval……………..…Per Lump Sum

15. SSP 07013 – PATTERNED CONCRETE

Description: This item shall consist of constructing patterned concrete at the location and grades detailed in the plans and detail sheets.

Materials: Concrete shall be Class 3000 and shall meet all applicable requirements of Division 700 of the

ISPWC. Baes Material shall be ¾” Crushed Aggregate for Base Type I. The texture shall be a running bond or basket weave brick pattern finish. The color shall be red-brown colored concrete that matches

AMS Standard 595A: AMS-STD 10076. The Contractor shall submit pattern and color samples for approval prior to construction.

Liberty St, Douglas St to Denton St | Project No. 822009 Page 23 of 39

Workmanship: The pattern shall be Brick Basket Weave or approved equal. When the concrete is still in the plastic stage of set, imprinting tools shall be applied to make the approved patterned surface. The pattern shall be formed with 3/8-inch maximum depth grooves and be placed simultaneously with the adjacent concrete sidewalk. No cold joints are allowed for the placement of the patterned concrete between the patterned concrete and the smooth section of sidewalk.

Measurement and Payment: All costs associated with construction of the patterned sidewalk, including concrete, imprinting tools, curing, and sealing, and aggregate base material and installation shall be included in the unit price bid for this item. Payment shall be per square yard, complete, in place.

SSP 07013 Patterned Concrete ........................................................................ Per Square Yard

16. SSP 08125 – ASPHALT REPAIR - OTHER

Description: This item shall include all work and costs associated with the repair of existing local roads, asphalt driveways, parking lots, and sidewalks abutting the project to match the grade of curbs, sidewalks, driveway approaches, and existing asphalt. This provision applies to all roadways that are not functionally classified as a Principal or Minor Arterial.

Materials: This item shall include placement of a 4” (inch) thickness of 3/4” (inch) aggregate base course, on a compacted sub-grade, and a 3” (inch) thickness of 1/2“ (inch) SP-3 Plant

Mix Asphalt in accordance with Section 814 of the 2015 ACHD Supplement to the ISPWC.

The asphalt cement performance grade shall be PG 64-28 and shall contain ½% of heat-stable anti-stripping agent per ton of asphalt cement added at the asphalt batch plant. Asphalt tack material shall be a SS-1 emulsified asphalt diluted as specified in accordance with ISPWC

Division 800 – “Aggregate and Asphalt.”

Workmanship: This item shall include all excavation, labor and equipment necessary to complete the repair of the existing asphalt roadway to match the grade of curbs, sidewalks, driveway approaches and existing asphalt. The asphalt mat shall be placed in accordance with the direction provided by ACHD’s designated representative.

Measurement and Payment: Material costs associated with the furnishing and placement of an asphalt tack coat on the lip of the gutter and on the edges of previously placed asphalt are considered incidental to this item.

SSP 08125 – Asphalt Repair - Other ......................... Per Square Yard

17. SSP 25050 – 4” TOPSOIL

Description: This item shall include all work and costs associated with installing 4” of compacted topsoil in the areas as shown on the construction plans or as directed by the Engineer.

Liberty St, Douglas St to Denton St | Project No. 822009 Page 24 of 39

Materials: Topsoil shall be friable, fertile, agricultural soil, containing normal amounts of macro and micro nutrients capable of sustaining vigorous plant growth. It shall be of uniform composition throughout, without admixture of subsoil. It shall be free of stones 1” (one inch) or larger, lumps, sticks, live plants and their root, and other extraneous matter.