Utility_Information_Sheet.pdf
PDF 54 KB Posted
- Attached to
- Munger Road Bridges #1005 and #2001
- Solicitation number
- CT226-08
- Issued by
- Boise County, Idaho
About this file
This is a Utility Information document for the Munger Rd Bridges #1005 and #2001 Project (#224008), involving the Ada County Highway District (ACHD). The document outlines utility company work requirements for relocating, adjusting, and installing utility infrastructure, which will require approximately 20 working days from the Notice to Proceed (NTP) date. The utility work may significantly impact the contractor's critical path schedule, with utilities potentially working on site during every project phase. The contractor is required to coordinate and accommodate utility company work and schedule construction windows throughout the project.
The document provides contact information for six utility companies involved in the project: Sparklight, Lumen, Star Sewer and Water, Idaho Power, Intermountain Gas, and Syringa Networks. Each utility listing includes a contact name, phone number, and email address. The ACHD Utility Coordinator, Scott Bennett, is listed as the primary contact for questions, with his contact information provided. The document references ACHD General Conditions Section 26 as applicable to the utility work coordination.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Utility Information
Munger Rd Bridges #1005 and #2001 Project #224008
Utility Company Work Duration and Contact Information:
Utilities require approx. 20 working days from NTP date to complete their relocations, adjustments, and installations after clearing, grubbing, tree trimming and removal. These utility windows may impact the Contractor’s critical path schedule by that amount of time, and utilities may be working on site for every phase of the project. Project phasing may have a significant effect on the schedule for utility relocations, adjustments, and installations. Contractor shall coordinate and accommodate work with utility companies and schedule required construction windows throughout the project.
ACHD General Conditions Section 26 applies. Contact ACHD Utility Coordinator, Scott Bennett, at (208) 387-6259, with questions.
Utilities within the project:
• Sparklight – Michael Stephen – (208) 615-0338 – Michael.Stephen@sparklight.biz
• Lumen – Aaron Kowal – (208) 985-4498 – aaron.kowal@lumen.com
• Star Sewer and Water – Kevin McLeod – (208) 565-8052 – KMcLeod@StarSWD.com
• Idaho Power – Ethan Morgan – (208) 912-6200 – emorgan@idahopower.com or Dan
Hammerquist - (208) 388-2629 - dhammerquist@idahopower.com
• Intermountain Gas – Tony Galvan – (208) 488-5480 – jose.Galvan@intgas.com
• Syringa Networks – Michael DeWitt - (208) 803-4000 - mdewitt@syringanetworks.net mailto:Michael.Stephen@sparklight.biz mailto:aaron.kowal@lumen.com mailto:KMcLeod@StarSWD.com mailto:emorgan@idahopower.com mailto:dhammerquist@idahopower.com mailto:jose.Galvan@intgas.com mailto:mdewitt@syringanetworks.net