Utility_Information_Sheet.pdf
PDF 54 KB Posted
- Attached to
- Munger Road Bridges #1005 and #2001
- Solicitation number
- CT226-08
- Issued by
- Boise County, Idaho
About this file
This document is a Utility Information sheet for the Munger Rd Bridges #1005 and #2001 Project (#224008), involving multiple utility companies and the Ada County Highway District (ACHD). The project requires utility companies to complete relocations, adjustments, and installations within approximately 20 working days after initial site preparation, with potential impacts on the contractor's critical path schedule. Utility companies are expected to work on-site during every project phase, and the contractor must coordinate and accommodate utility work throughout the project.
The document provides detailed contact information for six utility companies involved in the project: Sparklight, Lumen, Star Sewer and Water, Idaho Power, Intermountain Gas, and Syringa Networks. Each utility listing includes a contact name, phone number, and email address. The ACHD Utility Coordinator, Scott Bennett, is available at (208) 387-6259 for any questions. The utility work is governed by ACHD General Conditions Section 26, and the project requires careful scheduling and coordination to manage utility relocations and installations effectively.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Utility Information
Munger Rd Bridges #1005 and #2001 Project #224008
Utility Company Work Duration and Contact Information:
Utilities require approx. 20 working days from NTP date to complete their relocations, adjustments, and installations after clearing, grubbing, tree trimming and removal. These utility windows may impact the Contractor’s critical path schedule by that amount of time, and utilities may be working on site for every phase of the project. Project phasing may have a significant effect on the schedule for utility relocations, adjustments, and installations. Contractor shall coordinate and accommodate work with utility companies and schedule required construction windows throughout the project.
ACHD General Conditions Section 26 applies. Contact ACHD Utility Coordinator, Scott Bennett, at (208) 387-6259, with questions.
Utilities within the project:
• Sparklight – Michael Stephen – (208) 615-0338 – Michael.Stephen@sparklight.biz
• Lumen – Aaron Kowal – (208) 985-4498 – aaron.kowal@lumen.com
• Star Sewer and Water – Kevin McLeod – (208) 565-8052 – KMcLeod@StarSWD.com
• Idaho Power – Ethan Morgan – (208) 912-6200 – emorgan@idahopower.com or Dan
Hammerquist - (208) 388-2629 - dhammerquist@idahopower.com
• Intermountain Gas – Tony Galvan – (208) 488-5480 – jose.Galvan@intgas.com
• Syringa Networks – Michael DeWitt - (208) 803-4000 - mdewitt@syringanetworks.net mailto:Michael.Stephen@sparklight.biz mailto:aaron.kowal@lumen.com mailto:KMcLeod@StarSWD.com mailto:emorgan@idahopower.com mailto:dhammerquist@idahopower.com mailto:jose.Galvan@intgas.com mailto:mdewitt@syringanetworks.net