STATEMENT OF WORK: INSTALLATION OF HIGH SPEC AUTOMATIC SLIDING GATES AND CONTROL SYSTEM UPGRADE
This Statement of Work (SOW) outlines the design, supply, fabrication, removal of existing equipment, installation, testing, and commissioning of automatic sliding gate systems at two U.S. Embassy Pretoria vehicle access points: CAC A and CAC D. The project is issued by the U.S. Department of State, Office of Facility Management at the Embassy of the United States in South Africa, located at 877 Pretorius Street, Arcadia, Pretoria.
Project Scope and Technical Requirements:
CAC D requires complete replacement of existing gate leaves (approximately 4.1 meters long and 2.2 meters high), replacement of surrounding fence and structure to uniform 2.2-meter height with security spikes, installation of new top and bottom rail guidance systems with independent industrial-duty motors, replacement of the security booth control panel, and fiber optic connection to Post 1 for remote control capability. CAC A involves refurbishment of existing interior and exterior gate leaves, installation of new maintainable guide wheels and motors matching CAC D specifications, and installation of a new control system. The critical requirement at CAC A is proper disconnection of the sliding gates from the existing shared hydraulic system while preserving complete functionality of the Delta barrier hydraulic system; the Contractor must provide detailed hydraulic system survey, mapping, and disconnection planning to ensure zero damage to the Delta barrier. Both locations require anti-climb gate design, run-out prevention measures, entrapment prevention with dual safety devices, corrosion-resistant materials suitable for outdoor service, component standardization where practical, and seamless fence integration without security vulnerabilities.
Deliverables, Timeline, and Contract Terms:
Key deliverables include technical submittal packages (including CAC A hydraulic disconnection plan) due within 10 calendar days of site access approval, work plan and schedule due within 10 days of award, removal and site preparation completion within 25 days, fabrication completion within 40 days, installation completion within 60 days, and commissioning/training/handover packages within 70 days of technical submittal approval. The anticipated period of performance is ten weeks from award, subject to access approvals and material lead times. Contractor must have a minimum of five years of documented, successful experience in automated gate systems including new installations and refurbishment projects; CAC A work specifically requires demonstrated expertise in hydraulic system disconnection where existing system preservation is critical. The U.S. Embassy will issue fixed-price contracts with no deposit payments authorized; payment via EFT will be made within 30 calendar days after delivery and invoice receipt. The solicitation number is PR16185168, with a deadline for expressions of interest by 24 August 2026, a compulsory site meeting on 26 August 2026 at 10:00 AM, and tender submission deadline of 1 September 2026. Points of contact include Contracting Officer Katherine Reilly, Procurement Specialist Jenny Kriek, and Contracting Officer's Representative Jonathan Nieuwoudt. All work must comply with South African Occupational Health and Safety Act 85 of 1993, U.S. Army Corps of Engineers' EM 385-1-1, and U.S. Mission South Africa Policy P-070B-24, with contractors required to submit detailed site-specific safety plans for POSHO review and attend Contractor Safety Awareness training. Contractor must maintain professional appearance and conduct, comply with local and national laws and industry standards, and be accountable for all assigned spaces, supplies, and materials.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CLAUSES FOR PURCHASE ORDERS AND BLANKET PURCHASE AGREEMENTS FAR52.252_2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work: INSTALLATION OF HIGH SPEC AUTOMATIC SLIDING GATES AND CONTROL SYSTEM UPGRADE, VEHICLE ACCESS POINTS CAC A & CAC D
U.S. Department of State • Office of Facility Management Embassy of the United States of America in South Africa 877 Pretorius Street • Arcadia, Pretoria, South Africa • 0083
STATEMENT OF WORK
PROJECT TITLE: INSTALLATION OF HIGH SPEC AUTOMATIC SLIDING GATES AND CONTROL SYSTEM UPGRADE, VEHICLE ACCESS POINTS CAC A & CAC D
I confirm acknowledgement of this Statement of Work and the requirements therein.
CONTRACTOR PRINT NAME: ________________________________________ DATE: ________________
CONTRACTOR SIGNATURE: _________________________________________
Table of Contents
| 1. | Task Order Title | 3 |
| 2. | Introduction | 3 |
| 3. | Background | 3 |
| 4. | Current Environment | 3 |
| 5. | Objectives | 4 |
| 5.1. | Technical Objectives | 4 |
| 5.2. | Service Objectives | 5 |
| 5.3. | Security Objectives | 5 |
| 6. | Scope | 6 |
| 7. | Specific Requirements | 9 |
| 7.1. | Task Description | 9 |
| 7.2. | Key Deliverables, Milestones and Schedule | 17 |
| 7.3. | Government Furnished Equipment & Information (GFE/GFI) | 17 |
| 7.4. | Other Pertinent Information & Special Considerations | 18 |
| 8. | Constraints | 19 |
| 8.1. | Access Control | 19 |
| 8.2. | Safety & Health | 19 |
| 8.3. | Accessibility | 20 |
| 8.4. | Confidentiality & Privacy | 20 |
| 9. | Contract Type | 20 |
| 10. | Period of Performance | 21 |
| 11. | Place of Performance | 22 |
| 12. | Points of Contact | 22 |
| 13. | Contractor Performance, Appearance, and Conduct | 22 |
| 14. | General Notes | 23 |
Task Order Title
Installation of High Spec Automatic Sliding Gates and Control System Upgrade, Embassy Vehicle Access CAC A & CAC D
Introduction
The U.S. Embassy requires the design, supply, fabrication, removal of existing equipment (where applicable), installation, testing, and commissioning of automatic sliding gate systems at two Embassy vehicle access points: CAC A and CAC D, both used for vehicle security checks.
For CAC D: The work includes replacement of the existing gate leaves, rails, wheel assemblies, motors, and replacement of the control system within the security booth, along with perimeter fence height modifications and security enhancements.
For CAC A: The work includes refurbishment of existing gate leaves, installation of new maintainable guide wheels and equipment, replacement of gate motors and controls (similar to CAC D specifications), proper disconnection of gates from the existing hydraulic system while preserving the hydraulic system for continued Delta barrier operation, and installation of a new control system. Critical requirement: The existing hydraulic system must remain fully functional for Delta barrier operation and must not be damaged or compromised in any way during gate system modifications.
Both systems must be suitable for frequent daily operation, provide enhanced perimeter security, and be designed for long-term maintainability with locally serviceable components. Both locations shall include fiber optic connections to Post 1 for secondary remote control capability.
Background
CAC D: The existing vehicle access gates are in urgent need of replacement and are no longer fit for proper and safe operation. The current gates rely on a single hydraulic system that is beyond its working life span, resulting in increasing failures, reduced reliability, and elevated operational risk during security screening operations. The existing gate leaves and guiding mechanisms are aged, heavy, and difficult to maintain. These conditions increase the likelihood of unplanned downtime and create safety concerns for operators, pedestrians, and vehicles using the checkpoint.
CAC A: The existing vehicle access gates consist of one interior and one exterior sliding gate that require comprehensive refurbishment and system upgrades. While the gate leaves may be retained and refurbished, the current hydraulic operating system for the gates, guide wheels, and control equipment are outdated and require replacement to improve reliability, maintainability, and operational safety. The existing hydraulic system at CAC A serves dual purposes: operating the sliding gates and operating the Delta barrier. The hydraulic system must remain in place and fully operational for the Delta barrier. The Contractor must carefully disconnect only the gate-related hydraulic connections while ensuring the Delta barrier hydraulic system remains completely intact and functional. This is a critical security requirement as the Delta barrier provides essential vehicle access control at this checkpoint.
Current Environment
CAC D: The vehicle access point is a high use security location where vehicles are stopped and screened prior to entry. The current gates are heavy and the existing mechanical and hydraulic arrangement limits effective maintenance and timely part replacement. Existing rails, guides, support steelwork, and interface points to the surrounding fence line exhibit age related wear and corrosion and are not aligned with the requirements of a modern high cycle gate system. The surrounding infrastructure in the gate area requires modification and refurbishment to remove weak points, address corrosion, and support the installation of new top and bottom rail guidance and independent industrial duty motors.
CAC A: The vehicle access point features one interior and one exterior sliding gate serving as a critical security checkpoint. The current hydraulic system operates both the sliding gates and the Delta barrier. The gate-related hydraulic components and guide mechanisms are outdated and difficult to maintain. The existing control system requires replacement. The hydraulic infrastructure serving the Delta barrier must remain fully operational and undamaged throughout the project. Supporting structures require refurbishment or replacement to ensure long-term reliability and proper integration with new motorized gate systems. The Contractor must exercise extreme care to identify, isolate, and preserve all Delta barrier hydraulic components, lines, controls, and connections.
Objectives
Overview
The objective of this SOW is to acquire high quality automatic sliding gate systems at both CAC A and CAC D that improve reliability, safety, maintainability, and perimeter security at Embassy vehicle access checkpoints. The Contractor is expected to deliver robust solutions that support high frequency operation, integrate into the existing fence structures without vulnerabilities, and include new control systems compatible with current operational procedures and remote-control requirements from Post One via fiber optic connections.
Technical Objectives
CAC D:
· Replace the existing gate leaves with new sliding gate leaves sized to suit the opening and the specified dimensions (approximately 4.1 meters long and 2.2 meters high).
· Replace all surrounding fence and structure to match the 2.2-meter gate height.
· Install security spikes on top of new gates and fence matching current spikes on Embassy perimeter fence.
· Provide top and bottom wheel and rail guidance to ensure high stability, consistent alignment, and smooth travel.
· Replace the existing single hydraulic system with independent industrial duty gate motors suitable for frequent daily cycling.
· Replace the existing security booth gate control panel with a new control system designed for dual leaf operation, status indication, safety logic, and remote control integration.
· Install fiber optic connection from CAC D to Post 1 for secondary control capability.
· Ensure the design supports ease of maintenance, including rapid replacement of wheel assemblies, wear components, and critical spares using standard tools.
· Provide corrosion resistant materials and finishes suitable for continuous outdoor operation in Pretoria.
CAC A:
· Refurbish existing interior and exterior sliding gate leaves to restore structural integrity and appearance.
· Install new maintainable guide wheels and equipment designed for ease of replacement and long-term serviceability.
· Replace existing gate motors with new independent industrial duty motors (same or similar specification to CAC D) to ensure simplified maintenance and spare part supplies across both locations.
· Properly disconnect the sliding gates from the existing hydraulic system while ensuring the hydraulic system remains fully intact and operational for Delta barrier operation. This is a critical requirement.
· Identify, map, and preserve all hydraulic components, lines, valves, controls, and connections related to Delta barrier operation.
· Ensure zero damage to the Delta barrier hydraulic system and verify continued Delta barrier functionality throughout all phases of work.
· Replace the existing gate control system with a new control panel in CAC A security booth designed for interior/exterior gate operation, status indication, safety logic, and remote control integration, while ensuring Delta barrier controls remain fully functional.
· Install fiber optic connection from CAC A to Post 1 for secondary control capability.
· Refurbish all gate supporting structures, including posts, rails, foundations, and fence interfaces; replace components where refurbishment is not feasible.
· Ensure the design supports ease of maintenance with standardized components compatible with CAC D installation.
· Provide corrosion resistant materials and finishes suitable for continuous outdoor operation in Pretoria.
Service Objectives
· Reduce gate downtime and operational interruptions through robust design, quality components, and maintainable construction at both locations.
· Provide clear operating procedures, training, and documentation to enable Embassy staff (Facilities, Marine Security Guards, and FAC staff) to operate and perform routine checks safely at both CAC A and CAC D.
· Ensure spare parts availability in South Africa and provide recommended spares lists to support prompt repairs, with emphasis on component compatibility between CAC A and CAC D installations.
· Deliver commissioning, handover, and as-built documentation sufficient for long term operation and maintenance at both locations.
· At CAC A, ensure Delta barrier operation is not interrupted or compromised at any time during or after gate system modifications.
Security Objectives
· Enhance perimeter security by providing anti-climb gate design and eliminating weak points at interfaces to the surrounding fence structure at both locations.
· At CAC D, install security spikes on top of gates and perimeter fence matching existing Embassy fence spike design.
· Incorporate tamper resistant construction and anti-lift measures appropriate to high security checkpoints.
· Provide safety and security logic including controlled operation, emergency stop, obstacle detection, and manual override to prevent unsafe movement and unauthorized access.
· At CAC A, ensure proper disconnection of gate hydraulics does not compromise Delta barrier operation or create security vulnerabilities. Delta barrier functionality is critical to checkpoint security and must be maintained at all times.
· Ensure the completed installations maintain continuous security coverage with no gaps or vulnerabilities created by the new work.
· Provide fiber optic connections to Post 1 at both locations for centralized secondary control and monitoring capability.
Scope
This project includes two vehicle access locations:
CAC D: One vehicle access location consisting of two sliding gate assemblies, with each assembly comprising two opposing sliding gate leaves that operate together to open and close the vehicle access opening.
CAC A: One vehicle access location consisting of one interior sliding gate and one exterior sliding gate that operate in sequence to control vehicle access.
The work shall result in fully functional, high-quality, high-cycle automatic sliding gate systems suitable for continuous daily operation in a high-security Embassy environment at both locations.
CAC D Scope:
The scope of work includes site verification, engineering design, fabrication, refurbishment and modification of surrounding support infrastructure, removal and decommissioning of existing gate equipment, installation of new sliding gate leaves, replacement of all surrounding fence and structure to 2.2-meter height, installation of security spikes on gates and fence, installation of new top and bottom rail and wheel systems, installation of independent industrial-duty motors, replacement of the control system in the security booth, fiber optic installation from CAC D to Post 1, completion of all required electrical works, testing and commissioning, training of Government personnel (Facilities, Marine Security Guards, and FAC staff), and submission of complete handover documentation.
CAC A Scope:
The scope of work includes site verification, engineering design, refurbishment of existing interior and exterior gate leaves, refurbishment or replacement of all gate supporting structures (posts, rails, foundations, fence interfaces), installation of new maintainable guide wheels and equipment, careful disconnection of sliding gates from the existing hydraulic system with absolute preservation of hydraulic system integrity for Delta barrier operation, installation of new independent industrial-duty motors (same or similar to CAC D specification), installation of new control system in CAC A security booth with preservation of Delta barrier control functionality, fiber optic installation from CAC A to Post 1, completion of all required electrical works, testing and commissioning including verification of Delta barrier functionality, training of Government personnel (Facilities, Marine Security Guards, and FAC staff), and submission of complete handover documentation.
CRITICAL CAC A REQUIREMENT: The existing hydraulic system serves both the sliding gates and the Delta barrier. The Contractor must:
· Identify and map all hydraulic components, lines, valves, actuators, and controls serving the Delta barrier versus those serving only the gates
· Disconnect only the gate-related hydraulic connections, components, and controls
· Leave the Delta barrier hydraulic system completely intact and operational
· Ensure no damage occurs to any Delta barrier hydraulic components, lines, seals, fittings, or controls
· Cap, plug, or properly terminate any hydraulic lines that served the gates to prevent contamination or leakage
· Verify Delta barrier functionality before, during, and after all gate modification work
· Coordinate all work with the COR and demonstrate Delta barrier operation at key project milestones
Failure to maintain Delta barrier functionality is considered a critical project failure and may result in contract termination and liability for all damages.
Common Requirements for Both Locations:
The Contractor shall design and install the gate systems to meet all operational, safety, and security requirements, including mandatory measures for fall-over prevention, run-out prevention, and entrapment prevention.
Gate leaves shall be designed to prevent fall-over in the event of disconnection, component failure, or maintenance activities. Each gate leaf shall incorporate posts, stanchions, bollards, or a self-supporting structural design that prevents the gate from tipping more than 45 degrees when disconnected from supporting hardware. For opposing sliding gates that close at the center (CAC D), the Contractor may satisfy this requirement through a self-supporting box-frame design, typically with a frame depth of not less than 300 millimeters, such that each gate leaf is capable of standing independently without reliance on a center post.
Sliding gates shall be provided with run-out prevention measures to prevent uncontrolled travel beyond fully open or fully closed positions. This shall include positive mechanical stops at both the fully open and fully closed positions designed to withstand the maximum forces imparted by the gate during normal and fault conditions. All sliding gates shall also be equipped with limit switches that prevent travel beyond programmed operating distances. Existing run-out prevention components shall be inspected and replaced or upgraded as necessary to meet these requirements.
Entrapment prevention shall be incorporated throughout the entire gate travel path. Each gate shall be equipped with a minimum of two independent safety devices. One safety device may be integrated into the gate motor or operator to sense resistance or abnormal slowdown. A second independent safety device shall be installed on the interior side of the gate and shall consist of a photo eye, infrared sensor, light curtain, edge guard, or an approved equivalent. Any space between the moving gate and a fixed surface along the entire length of gate travel that is less than 410 millimeters shall be treated as an entrapment zone and shall be protected by appropriate sensing devices. Where gate run-out areas are accessible to personnel or the public, including interior compound-side areas, the Contractor shall provide physical barriers, fencing, or walls with a minimum height of 1.2 meters to restrict access.
All surrounding infrastructure, including foundations, plinths, fence interfaces, and support steelwork, shall be refurbished or modified as required to remove corrosion, eliminate weak points, and ensure the new installations do not introduce security vulnerabilities. The new gates shall integrate seamlessly with the existing perimeter fence, providing continuous security coverage with no gaps, footholds, or climbable features.
The completed systems shall be designed for ease of maintenance and long-term serviceability. Wheel assemblies, wear components, motors, and safety devices shall be accessible for inspection and replacement with minimal disassembly. All components shall be corrosion resistant and suitable for continuous outdoor operation. Component standardization between CAC A and CAC D installations is strongly preferred to simplify maintenance and spare parts inventory.
The expected result is fully commissioned, high-cycle automatic sliding gate systems at both CAC A and CAC D that operate smoothly, safely, and reliably, support Embassy security operations without interruption, and meet all FAC, OBO, and Embassy operational requirements. At CAC A, the Delta barrier must remain fully functional throughout and after all project work.
Specific Requirements
Task Description
Task 1: Site verification, engineering survey, and approvals
· The Contractor shall conduct site visits at both CAC A and CAC D and verify all measurements, clearances, gate travel zones, foundations, fence interfaces, and existing utility routing.
· The Contractor shall identify constraints including slope, drainage, existing concrete condition, and any obstructions affecting rail alignment at both locations.
· At CAC A, the Contractor shall conduct a comprehensive survey and mapping of the existing hydraulic system to identify:
· All hydraulic lines, valves, actuators, pumps, reservoirs, and controls
· Which hydraulic components serve the sliding gates exclusively
· Which hydraulic components serve the Delta barrier exclusively
· Which hydraulic components, if any, are shared between gates and Delta barrier
· All control wiring and logic related to gates versus Delta barrier
· Delta barrier location, operation, and clearance requirements
· The Contractor shall prepare a detailed hydraulic system disconnection plan showing exactly which components will be disconnected, capped, or removed, and which components will remain in service for the Delta barrier.
· The Contractor shall submit a technical submittal package for Embassy review and approval prior to fabrication. The package shall include:
· Dimensioned technical drawings for each gate leaf and overall layout for both CAC A and CAC D
· Rail and wheel arrangement drawings showing top and bottom guidance
· Structural details at fence and post interfaces, including corrosion remediation approach
· For CAC D: Drawings showing fence height modifications to 2.2 meters and spike installation details matching existing Embassy fence spikes
· For CAC A: Detailed hydraulic system survey and mapping showing gate-related versus Delta barrier-related components
· For CAC A: Hydraulic disconnection plan with step-by-step procedures to isolate gates while preserving Delta barrier functionality
· For CAC A: Risk assessment and mitigation plan for protecting Delta barrier hydraulic system during all phases of work
· For CAC A: Drawings showing gate refurbishment approach, supporting structure refurbishment/replacement
· Motor sizing calculations or justification based on estimated gate mass, duty cycle, and environmental conditions
· Control system architecture including wiring diagrams, control logic, safety devices, and remote integration method via fiber optic connection to Post 1 for both locations
· For CAC A: Control system separation plan showing how gate controls will be isolated from Delta barrier controls
· Fiber optic installation routing and termination details for both CAC A and CAC D to Post 1
· Data sheets for motors, control panels, safety sensors, wheels, rails, and enclosures
· Finish specifications including galvanizing and coating system
· Demonstration of component compatibility between CAC A and CAC D installations
· For CAC A: Delta barrier functionality verification and testing protocol No fabrication or disconnection work shall commence until written approval is received from the COR or designated representative.
Task 2: Removal and disconnection of existing equipment
CAC D:
· The Contractor shall isolate power and coordinate safe access with Embassy security.
· The Contractor shall remove existing gate leaves, rails, guides, motors, hydraulic components, and control equipment designated for replacement.
· The Contractor shall remove existing fence sections and supporting structures to be replaced with 2.2-meter height installations.
· The Contractor shall dispose of removed materials in accordance with local regulations and Embassy requirements. Any salvage items identified by the Government shall be set aside and returned to Government custody.
CAC A:
· The Contractor shall isolate power and coordinate safe access with Embassy security.
· CRITICAL: The Contractor shall carefully disconnect the sliding gates from the existing hydraulic system following the approved hydraulic disconnection plan.
· The Contractor shall:
· Identify and verify all gate-related hydraulic connections before any disconnection
· Isolate gate hydraulic circuits using appropriate valves or isolation methods
· Carefully disconnect only gate-related hydraulic lines, actuators, and components
· Properly cap, plug, or seal all disconnected hydraulic lines to prevent contamination, leakage, or pressure loss
· Protect all Delta barrier hydraulic components from damage, contamination, or disturbance
· Verify hydraulic system pressure and fluid levels remain appropriate for Delta barrier operation
· Test Delta barrier operation immediately after any hydraulic disconnection work to verify functionality
· Document all disconnection steps with photographs and written records
· Have hydraulic system expertise available on-site during all disconnection activities
· The Contractor shall remove gate-related hydraulic components only after verification that they do not serve the Delta barrier.
· The Contractor shall NOT remove, modify, or disturb:
· Any hydraulic lines serving the Delta barrier
· Any hydraulic valves, actuators, or controls serving the Delta barrier
· The hydraulic pump, reservoir, or power unit if it serves the Delta barrier
· Any control wiring or logic related to Delta barrier operation
· The Contractor shall remove existing guide wheels, motors, and gate control equipment designated for replacement.
· Gate leaves shall be carefully removed for refurbishment or retained in place if refurbishment can be performed in situ.
· The Contractor shall coordinate all hydraulic disconnection work with the COR and shall stop work immediately if any Delta barrier functionality issue is observed.
· The Contractor shall dispose of removed materials in accordance with local regulations and Embassy requirements. Any salvage items identified by the Government shall be set aside and returned to Government custody.
Task 3: Refurbishment of surrounding infrastructure and fence integration
CAC D:
· The Contractor shall remove and replace all surrounding fence and structure to achieve uniform 2.2-meter height matching the new gate height.
· The Contractor shall install security spikes on top of new gates and perimeter fence matching the design, spacing, and appearance of existing spikes on the Embassy perimeter fence.
· The Contractor shall inspect existing structural steelwork, posts, anchor points, and fence interfaces within the gate area.
· The Contractor shall modify, repair, reinforce, or replace corroded or structurally compromised elements to ensure no weak points remain.
· The Contractor shall ensure the new gates integrate into the fence line with continuous security coverage, including infill or interface plates where necessary.
· The Contractor shall ensure concrete plinths and foundations are suitable for the new rail and motor loads. Where required, the Contractor shall repair or construct new foundations to achieve correct alignment and long-term stability.
CAC A:
· The Contractor shall inspect all gate supporting structures including posts, rails, foundations, anchor points, and fence interfaces.
· The Contractor shall refurbish all gate supporting structures by removing corrosion, repairing damage, and applying appropriate protective coatings.
· The Contractor shall replace any supporting structure components that cannot be adequately refurbished to ensure structural integrity and long-term reliability.
· The Contractor shall ensure the refurbished/replaced structures integrate seamlessly with existing perimeter fence with continuous security coverage.
· The Contractor shall ensure concrete plinths and foundations are suitable for the new motor and wheel loads. Where required, the Contractor shall repair or construct new foundations to achieve correct alignment and long-term stability.
· The Contractor shall verify that all structural modifications maintain proper clearance and do not interfere with Delta barrier operation or hydraulic system components.
· The Contractor shall protect all Delta barrier hydraulic lines, conduits, and components during structural refurbishment work.
Task 4: Fabrication and installation of gate leaves
CAC D:
· Quantity and configuration:
· Two gate assemblies
· Four gate leaves total, two leaves per assembly
· Dimensions:
· Each gate leaf shall be approximately 4.1 meters long and 2.2 meters high, subject to confirmed site measurements and approved drawings.
· Construction and security features:
· Gates shall be anti-climb and designed to minimize footholds.
· Gates shall be as light as practical while retaining anti-climb performance and structural stiffness.
· Design shall include anti-lift features and tamper resistant fasteners where practical.
· Security spikes shall be installed on top of gates matching existing Embassy fence spike design.
· Corrosion protection:
· Steel components shall be hot dip galvanized and coated, or equivalent approved system suitable for long-term outdoor service.
· Fasteners shall be corrosion resistant, preferably stainless steel where appropriate.
CAC A:
· Quantity and configuration:
· One interior sliding gate
· One exterior sliding gate
· Refurbishment approach:
· Existing gate leaves shall be refurbished to restore structural integrity, appearance, and functionality.
· Refurbishment shall include removal of corrosion, repair of damage, reinforcement where necessary, and application of protective coatings.
· If existing gate leaves cannot be adequately refurbished, the Contractor shall fabricate new gate leaves to dimensions confirmed by site measurements.
· Construction and security features:
· Gates shall maintain anti-climb design and minimize footholds.
· Design shall include anti-lift features and tamper resistant fasteners where practical.
· Corrosion protection:
· Refurbished or new steel components shall be hot dip galvanized and coated, or equivalent approved system suitable for long-term outdoor service.
· Fasteners shall be corrosion resistant, preferably stainless steel where appropriate.
Task 5: Top and bottom rail and wheel guidance system Both CAC A and CAC D:
· The Contractor shall install new top and bottom rails for each gate leaf, aligned to ensure smooth travel and reduced wear.
· The Contractor shall provide new maintainable top and bottom wheel assemblies using sealed bearings suitable for high cycle operation.
· Wheel assemblies shall be designed for rapid replacement with minimal disassembly. The Contractor shall demonstrate the replacement method during handover training.
· The Contractor shall provide drainage and debris management features to reduce rail fouling, including appropriate grading, drainage channels, or covers where feasible.
· Wheel and rail components should be standardized between CAC A and CAC D installations where practical to simplify maintenance and spare parts inventory.
· At CAC A, rail and wheel installation shall not interfere with Delta barrier operation or hydraulic system components.
Task 6: Motors and gate automation Both CAC A and CAC D:
· The Contractor shall supply and install independent industrial duty motors for gate operation. Each leaf shall have a dedicated motor or an approved equivalent configuration that provides equal redundancy and reliability.
· Motors at CAC A shall be the same or similar specification to motors installed at CAC D to ensure simplified maintenance and spare parts supplies across both locations.
· Motors shall be rated for frequent daily operation and suitable for high cycle use, including thermal protection and overload detection.
· The Contractor shall provide manual release mechanisms and emergency operation procedures suitable for power failure or fault conditions.
· The Contractor shall provide soft start and soft stop or equivalent controlled motion to reduce mechanical shock and extend component life.
· At CAC A, motor installation and operation shall not interfere with Delta barrier operation.
Task 7: New control system in security booth and remote integration
CAC D:
· The Contractor shall replace the existing control panel in the security booth with a new control system.
· The new control system shall include:
· Open, close, stop, and emergency stop functions
· Indicator lights for gate status including open, closed, fault
· Safety logic inputs including obstacle detection and auto reverse
· Integration capability with the existing remote control interface used by Embassy security operations
· Fiber optic interface for secondary control from Post 1
· All control equipment shall be installed in appropriate enclosures and mounted in a secure, maintainable manner within the security booth.
CAC A:
· The Contractor shall install a new control panel in the CAC A security booth for gate operation.
· CRITICAL: The new gate control system must be completely separate and independent from Delta barrier controls.
· The Contractor shall:
· Identify and map all existing control wiring to distinguish gate controls from Delta barrier controls
· Remove only gate-related control wiring, panels, and components
· Leave all Delta barrier control wiring, panels, switches, and components completely intact and functional
· Ensure no electrical interference between new gate controls and existing Delta barrier controls
· Verify Delta barrier control functionality after any control system modifications
· The new gate control system shall include:
· Open, close, stop, and emergency stop functions for both interior and exterior gates
· Indicator lights for gate status including open, closed, fault for each gate
· Safety logic inputs including obstacle detection and auto reverse
· Sequencing logic appropriate for interior/exterior gate operation
· Integration capability with the existing remote control interface used by Embassy security operations
· Fiber optic interface for secondary control from Post 1
· All control equipment shall be installed in appropriate enclosures and mounted in a secure, maintainable manner within the security booth.
· Control system installation shall not interfere with or compromise Delta barrier control functionality.
· Control system design should be compatible with CAC D installation where practical to simplify training and maintenance.
Task 8: Electrical works Both CAC A and CAC D:
· The Contractor shall supply and install all electrical cabling, conduits, junction boxes, isolators, breakers, and terminations required for complete systems at both locations.
· Wiring shall be neatly routed, mechanically protected, and labeled at both ends.
· The Contractor shall provide UPS, surge protection, and grounding appropriate for the installations.
· The Contractor shall install fiber optic cable from CAC A to Post 1 and from CAC D to Post 1, including all necessary terminations, patch panels, and interface equipment for secondary gate control capability.
· Electrical work shall comply with applicable South African standards including SANS 10142.
· At CAC A, all electrical work shall be coordinated to avoid interference with Delta barrier electrical systems and controls.
Task 9: Testing, commissioning, and training Both CAC A and CAC D:
· The Contractor shall perform functional testing and commissioning, including:
· Alignment and smooth travel verification
· Duty cycle testing representative of high use conditions
· Safety device testing including obstacle detection and auto reverse
· Emergency stop and manual release testing
· Control system operation from the booth and via remote location (Post 1) through fiber optic connection
· At CAC A: Comprehensive verification that hydraulic system disconnection has not interfered with Delta barrier functionality
· At CAC A: Delta barrier operation testing before, during (at key milestones), and after all gate modification work
· At CAC A: Verification that all Delta barrier hydraulic components, lines, controls, and functions remain fully operational
· At CAC A: Sequencing verification for interior/exterior gate operation
· At CAC A, the Contractor shall demonstrate Delta barrier operation to the COR and obtain written confirmation of satisfactory Delta barrier functionality before final project acceptance.
· The Contractor shall provide comprehensive training to Embassy Facilities personnel, Marine Security Guards, and FAC staff covering:
· Normal operation at both locations
· Emergency procedures
· Manual release and recovery
· Routine inspection points
· Wheel and wear component replacement approach
· Remote control operation from Post 1
· Differences and similarities between CAC A and CAC D systems
· At CAC A: Specific procedures to avoid interference with Delta barrier and hydraulic system
· At CAC A: Delta barrier operation verification procedures
· Training shall be conducted separately for each location and shall include hands-on demonstration of all operational and maintenance procedures.
· The Contractor shall submit commissioning reports for both locations documenting tests performed, results, and final settings.
· At CAC A, the commissioning report shall include detailed documentation of Delta barrier functionality verification and confirmation that the hydraulic system remains fully operational.
Task 10: Documentation and handover Both CAC A and CAC D:
· The Contractor shall provide comprehensive handover packages for both locations including:
· As-built drawings for gates, rails, wheels, motors, and control panels
· Electrical schematics and wiring schedules
· Fiber optic installation drawings and termination schedules
· Manufacturer manuals and data sheets
· Recommended preventive maintenance schedule
· Recommended spare parts list including part numbers and local supplier information, with emphasis on common parts between CAC A and CAC D
· Warranty documentation
· At CAC A: Comprehensive documentation of hydraulic system disconnection including:
· Hydraulic system survey and mapping (as-built)
· Identification of all components disconnected versus components remaining in service
· Photographs documenting disconnection work and Delta barrier hydraulic system preservation
· Delta barrier functionality verification test results
· Hydraulic system pressure and fluid level records
· Maintenance procedures for gate systems that avoid interference with Delta barrier hydraulics
· Cross-reference documentation identifying component compatibility between CAC A and CAC D installations
Key Deliverables, Milestones and Schedule
Deliverable 1: Technical submittal package for approval (both CAC A and CAC D), including CAC A hydraulic system survey, mapping, and disconnection plan Due within 10 calendar days after site access is granted Deliverable 2: Work plan and schedule (both locations) Due within 10 calendar days after award Deliverable 3: Completion of removal and site preparation (both locations), including CAC A hydraulic disconnection with Delta barrier functionality verification Due within 25 calendar days after approval of technical submittals Deliverable 4: Fabrication completion and delivery to site (both locations) Due within 40 calendar days after approval of technical submittals Deliverable 5: Installation completion (both locations) Due within 60 calendar days after approval of technical submittals Deliverable 6: Commissioning, training, and handover package (both locations), including CAC A Delta barrier functionality verification and documentation Due within 70 calendar days after approval of technical submittals
Government Furnished Equipment & Information (GFE/GFI)
The Government will provide the following, subject to security requirements and availability:
· Controlled access to the work sites (CAC A and CAC D) and security booths during approved work windows
· Point of contact coordination for security operations and escort requirements
· Existing system information needed for remote control integration, limited to what is authorized for release
· At CAC A: Information regarding Delta barrier location, operation, and hydraulic system configuration to facilitate proper identification and preservation of Delta barrier components
· At CAC A: Coordination for Delta barrier functionality testing at key project milestones All other tools, equipment, consumables, temporary power distribution, and materials shall be provided by the Contractor.
Other Pertinent Information & Special Considerations
High use area requirements:
· Both CAC A and CAC D are high use security locations. The Contractor shall plan work to minimize disruption and maintain safe access control operations at both locations.
Work sequencing:
· The Contractor shall coordinate shutdowns, removals, and commissioning activities with the COR and security operations to maintain continuous security posture at both locations.
· Work at CAC A and CAC D may be performed concurrently or sequentially based on the Contractor's proposed schedule and Embassy operational requirements.
· At CAC A, all work involving hydraulic system disconnection shall be performed during approved windows with COR oversight and immediate Delta barrier testing capability available.
Compatibility and spares:
· The Contractor shall prioritize components with established support in South Africa and shall identify local service agents where available.
· The Contractor shall maximize component standardization between CAC A and CAC D installations to simplify maintenance and spare parts inventory.
Noise and operational smoothness:
· The installed systems should operate smoothly with minimal vibration and noise consistent with high quality industrial installations.
CAC A specific considerations - CRITICAL:
· Proper disconnection of gates from the hydraulic system while preserving Delta barrier functionality is the most critical aspect of the CAC A project.
· The Contractor must have demonstrated expertise in hydraulic systems and must provide qualified hydraulic technicians for all disconnection work.
· The Contractor shall coordinate with the COR to verify Delta barrier operation before any hydraulic work begins, immediately after any hydraulic disconnection, and at project completion.
· Any damage to the Delta barrier hydraulic system or loss of Delta barrier functionality will be considered a critical project failure.
· The Contractor shall maintain liability insurance adequate to cover potential damages resulting from Delta barrier system compromise.
· The Contractor shall stop all work immediately if any Delta barrier functionality issue is observed and shall not resume until the issue is resolved and approved by the COR.
Constraints
Access Control
· All Contractor personnel shall comply with Embassy access procedures, vetting, escort requirements, and work area restrictions.
· Work may be limited to approved hours and may require coordination with security operations due to the checkpoint functions at both CAC A and CAC D.
· At CAC A, work involving hydraulic system disconnection may require special coordination and oversight due to the critical nature of Delta barrier operation.
· Tools, materials, and equipment shall be subject to inspection and approval.
Safety & Health
All contractors and subcontractors performing duties on behalf of the U.S. Government at U.S. Government-held sites are required to do so safely and healthfully. This is in accordance with South African law via the Occupational Health and Safety Act 85 of 1993 and American regulations via the U.S. Army Corps of Engineers’ EM 385-1-1: Safety and Occupational Health Requirements (accessible at https://www.publications.usace.army.mil/USACE-Publications/Engineer-Manuals/) and U.S. Mission South Africa’s Mission Policy P-070B-24, Safety Requirements for Contractors & Subcontractors. The U.S. Embassy Pretoria Post Occupational Safety & Health Officer (POSHO) must ensure strict compliance with current safety regulations as well as the overall health and safety of personnel, avoiding any damage or injury. The Contractor must accept all legal requirements and/or regulations currently enforced concerning safety for staff, technicians, other workers, and the public whom the work may directly or indirectly impact.
Contractors must submit a detailed, site-specific safety plan for POSHO review as part their tender documents, addressing hazard mitigation and control methods. The safety plan, which must always be accessible at the U.S. Government-held work site, must address the following requirements:
· General Safety
· Barricading and Warning Signs
· Personal Protective Equipment
· Safety Inspections
· Hand & Power Tool Safety
· Emergency Response
· High-Risk Work
· Electrical Safety
· Fall Protection
· Scaffolding
· Hazard Communication & Chemical Substances Safety
· Lifting Loads, Use of Cranes, or Elevating Work Platforms Safety
· Welding & Open Flame Operation Safety
· Confined Spaces Safety
The following items are generally included in the site-specific safety plan:
· Contractor appointment letter
· Agreement between Client and Contractor
· Notification of construction work [if applicable]
· Copy of the Occupational Health and Safety Act 85 of 1993
· Occupational Health and Safety Policy [company-specific]
· Occupational Health and Safety Management Plan [company-specific]
· Letter of Good Standing
· Safety Data Sheets [for all chemicals and hazardous materials, where applicable]
· Tax clearance certificate
· Risk assessments
· Safe work procedure [site-specific]
· Fall protection plan [site-specific, where applicable]
· Legal appointments (e.g., CEO, Risk Assessor, First Aider) [must include proof of training]
· Incident reporting procedures
· Emergency preparedness documents
· First aid documents
· Site-specific list of employees [must include proof of training and issued protective equipment]
· Log of incident reports and accidents
Contractors who are awarded a contract, blanket purchase agreement, or purchase order to conduct work on behalf of the U.S. Government at its work sites are required to attend the Contractor Safety Awareness at U.S. Government Work Sites training session.
Inquiries concerning contractor safety requirements at U.S. Government work sites can be directed to the U.S. Embassy Pretoria Safety Office at PretoriaPOSHO@state.gov.
Accessibility
The Contractor shall maintain safe pedestrian routes and ensure that temporary conditions do not create uncontrolled hazards. The Contractor shall coordinate any temporary barriers, traffic control, and signage to ensure safe movement of staff and visitors near the access point.
Confidentiality & Privacy
The Contractor shall not record, photograph, or disseminate sensitive site details except as authorized in writing. Technical drawings and documentation shall be treated as controlled information and submitted through the COR or designated channels. All discussions of security operations and access control integration shall be limited to approved personnel and approved scope.
Contract Type
The Department of State intends to acquire the deliverables and services outlined in this SOW under a service contract or purchase request vehicle appropriate to local procurement procedures.
Period of Performance
The anticipated period of performance is ten weeks from the date of award, subject to access approvals and material lead times. The Contractor shall propose a detailed schedule aligned to the milestones in Section 7.2, addressing work at both CAC A and CAC D. The schedule shall specifically identify all CAC A hydraulic disconnection activities and associated Delta barrier verification testing windows
Place of Performance
All work shall be performed at:
U.S. Embassy Pretoria 877 Pretorius Street, Arcadia, Pretoria, South Africa, 0083 Vehicle access security check area and associated security booth CAC D
Points of Contact
Contracting Officer (CO)
| Name: |
| Katherine Reilly |
| Phone: |
| 010-141-2479 |
| Email: |
| ReillyKA@state.gov |
Procurement Specialist
| Name: |
| Jenny Kriek |
| Phone: |
| 010-141-2483 |
| Email: |
| KriekJX@state.gov |
Contracting Officer’s Representative (COR)
| Name: |
| Jonathan Nieuwoudt |
| Phone: |
| 0791114386 |
| Email: |
| nieuwoudtj@state.gov |
Facility Manager
| Name: |
| Nicholas Karklins |
| Phone: |
| 012-431-4375 |
| Email: |
| KarklinsNS@state.gov |
Contractor Performance, Appearance, and Conduct
· The Contractor shall take all steps necessary to maintain a line of communication with the Department of State so as to afford optimum deliverables and services under the terms of this SOW. Throughout the effective period of the SOW, the Department of State shall maintain its authority to determine work priorities.
· The Contractor’s employees shall maintain a neat, professional appearance that is commensurate with the tasks being performed on behalf of the Department of State and the U.S. Government.
· The Contractor shall ensure that its employees receive all necessary training to ensure work is accomplished in a manner that complies with local and national laws, applicable industry and safety standards, regulations and codes, and does not pose a threat to the safety and/or welfare of either the Contractor’s employees, personnel representing the Department of State, or the public.
· The Contractor shall ensure be accountable for its assigned spaces, supplies, parts, and materials that are the property of the Department of State, and shall be responsible for any and all damage to or loss of same. The Contractor is responsible for maintaining all assigned space in a clean and orderly manner.
· As directed by the COR, the Contractor will take all necessary action to minimize periods when equipment is out of service. Such action may include rescheduling planned work or the temporary use of additional Contractor personnel onsite to meet workload requirements.
General Notes
· The Contractor shall take all steps necessary to maintain a line of communication with the Department of State so as to afford optimum deliverables and services under the terms of this SOW. Throughout the effective period of the SOW, the Department of State shall maintain its authority to determine work priorities.
· Contractor qualifications for this scope of work is limited to firms, companies, and/or principals specializing in said work with no less than five (5) years of documented, successful experience in automated gate systems, including experience with both new installations and refurbishment projects. For CAC A work, the Contractor must demonstrate specific experience with hydraulic system disconnection, modification, or integration projects where preservation of existing hydraulic system functionality was critical.
· Normal working hours are 08:00 to 17:00 Monday through Friday, except for holidays recognized by the Governments of the United States of America and Republic of South Africa, respectively.
· Parking is very limited in availability. The Contractor shall consult with the COR on any parking requirements.
· The Contractor is advised that Delta barrier functionality at CAC A is a critical security requirement. Any proposal that does not adequately address hydraulic system preservation and Delta barrier protection may be deemed non-responsive.
END OF STATEMENT OF WORK