Performance Work Statement Summary

This is a Performance Work Statement (PWS) issued by the United States Section of the International Boundary and Water Commission (USIBWC) for the refurbishment and maintenance of a 138 KV Oil Circuit Breaker (OCB) at the Amistad Power Plant in Starr County, Texas. The contract is a lump sum, non-personnel services arrangement with a performance period of 180 calendar days from award. The work location is at the Amistad Power Plant Field Office, Texas 349 Spur Del Rio, TX 78540, which is adjacent to the international border with Mexico.

The primary objective requires the contractor to assess and refurbish the 138 KV OCB, including replacement of the air compressor, oil change and proper disposal, replacement of all electrical contact boards, pneumatic parts, and mechanical parts based on detailed assessment. Additional work includes sandblasting and painting the enclosure, replacing mechanical hardware connectors, testing insulation resistance and current transformers per IEEE standards, inspecting and replacing heaters and moisture protection devices, removing and disposing of dielectric oil, installing new insulator oil with high dielectric strength, and providing comprehensive testing and training to plant personnel upon completion. The contractor must submit detailed deliverables including a project schedule within seven calendar days of award, materials certifications ensuring Buy American Act compliance, licenses and certifications for electrical engineers and installers, an installation procedure plan, safety documentation including a Job Safety Analysis form, and a two-year warranty on all work and materials. Work hours are restricted to 7:00 AM to 3:30 PM, Monday through Friday, except federal holidays or government-directed closings. All personnel must sign in at the IBWC Main Office before crossing the Port of Entry. The contractor is responsible for all costs including materials, labor, equipment, supplies, permits, waste disposal, and site security, with the government providing no utilities or field office facilities.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

International Boundary and Water Commission United States and Mexico United States Section

Front Cover

Performance Work Statement (PWS) Falcon Power Plant Refurbish 138 KV Breaker (OCB) ValverdeStarr County, Texas

February 20, 2026

International Boundary and Water Commission United States and Mexico United States Section Operations and Maintenance Division

USIBWC Amistad Power Plant

Refurbish 138 KV OCB Breaker Valverde County, Texas

Feb 20,2026 Performance Work Statement

Page-1 of 15

SECTION 1

PROJECT SPECIFIC INFORMATION

1.1 Project Overview

The United States Section of the International Boundary and Water Commission (USIBWC), Amistad

Power Plant Field Office located at Texas 349 Spur Del Rio, TX 78540 requires improvements to

Refurbish/Maintenance current 138 KV Oil Circuit Breaker (OCB) as described herein.

1.2 General

This is a non-personnel services Contract to provide. Refurbish/Maintenance current 138 KV Oil Circuit

Breaker (OCB). The Government shall not exercise any supervision or control over the Contract service providers performing the services herein. Such Contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.

1.3 Description of Services

The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform Refurbish/Maintenance current 138 KV Oil Circuit Breaker (OCB) as defined in this Performance Work Statement except for those items specified as government furnished property and services. The contractor shall perform to the standards in this contract.

1.4 Objective

A. Refurbish/Maintenance current 138 KV Oil Circuit Breaker (OCB), which include to replace air compressor, oil change and disposal, replace all the electrical contact boards, all pneumatic parts, and mechanical parts. Must of the equipment and parts will be replaced after an assessment to determine all the worn parts. In addition, this project requires to sandblast and paint current enclosure and replace all mechanical hardware connectors to support the 138 KV electrical conductors.

1.5 Project Location

A. The work is within the United States on land owned by the USIBWC in Starr County, Texas. The site is located at Amistad Power Plant Field Office located at Texas 349 Spur Del Rio, TX 78540.

B. The work is located completely within the United States but is adjacent to the international border with Mexico.

1.6 Period of Performance

A. The contractor shall complete this work within 180 calendar days after the Contract has been awarded to the Contractor.

Valverde County, Texas

Feb 20,2026 Performance Work Statement

Page-2 of 15

1.7 Investigation of Site Conditions

A. The Contractor, as well as their subcontractors, is urged to visit the jobsite and to become fully aware as to the existing conditions affecting the work to be performed under this Contract.

B. All Personnel need to sign in in the IBWC Main Office before of crossing Port of Entry

C. The Contractor shall enforce strict discipline and good order among the Contractor’s employees.

The Contractor shall exercise the necessary supervision and control to prevent Contractor’s employees from violating any rules and regulations

D. OFFEROR’S ARE HIGHLY ENCOURAGED TO ATTEND A SITE VISIT PRIOR TO

SUBMISSION OF AN OFFEROR’S QUOTE. A site visit would be scheduled for later date at Texas 349 Spur Del Rio, TX 78540 (Amistad Power Plant). If you have questions, contact Juan Escobar via email juan.escobar@ibwc.gov (Plant Superintendent/COR) or Evelio Siller via email evelio.siller@ibwc.gov(Amistad Field Office Manager).

E. Submission of a bid shall be conclusive evidence that the Contractor has reviewed, investigated, and acknowledged all items below.

1. Conditions bearing upon transportation, disposal, handling, and storage of materials.

2. The availability of labor, water, electric power, and roads.

3. Uncertainties of weather and similar physical conditions at the site.

4. The conformation and conditions of the ground.

5. The character of equipment and facilities needed preliminary to and during work performance.

F. Submission of a bid shall be conclusive evidence that the Contractor has investigated and is satisfied as to the conditions to be encountered, the character, quality, and work to be performed, and the quantities of materials to be furnished.

G. Submission of a bid constitutes agreement that Contractor has provided written notice of all conflicts, errors, ambiguities, and discrepancies discovered in PWS, that responses to these written notices are acceptable to Contractor, and that PWS is sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing required work.

H. Contractor has the sole responsibility to make such independent instigation and examination as they deem necessary in order to satisfy themselves as to the conditions to be encountered in the performance of work and the quantities required to complete the work in accordance with the PWS.

I. The Government assumes no responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this Contract, unless that understanding, or representation is expressly stated in this Contract.

J. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.

Valverde County, Texas

Feb 20,2026 Performance Work Statement

Page-3 of 15

1.8 Duty to Inquire

A. Contractor shall review the full PWS.

B. If during review of these items, the Contractor finds discrepancies, omissions, conflicts, defects, errors, or ambiguities, they have a duty to inquire and shall notify the Contracting Officer prior to the question submission deadline as established in the solicitation. The Contractor shall also inquire about items that are unclear or open to interpretation.

C. The Contractor shall take no advantage of any item of which they have a duty to inquire.

1.9 Work Restrictions

A. The contractor is responsible for conducting business between the hours of 7:00 AM thru 3:30 PM, Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government-directed facility closings.

B. The Contractor may request different working hours and must do so in writing to the COR.

USIBWC Principal Engineer of Operations will make final determination as to the approval of a different work schedule.

1.10 Department of Homeland Security

In any event the staff of the US Department of Homeland Security (DHS, also known as US Customs and

Border Protection or CBP) alerts and directs any field crews to stop work in for any security reasons in the area, the Contractor shall consider this as top priority and fully cooperate with the directions of DHS at all times until the security alert is cleared by the DHS. In addition, the Contractor shall contact and coordinate with the COR for any additional steps to be taken during and after the security alert from the

DHS is cleared.

SECTION 2

PROJECT REQUIREMENTS

2.1 General

A. Contractor shall perform an assessment/ inspection to investigate current conditions of the 138 KV

OCB Breaker and prepare a maintenance plan report.

B. Contractor shall determine all the pneumatic, mechanical, electrical parts that need to be replaced and create a list with the most common brands available in the market and should present a report the lead time for all the parts to be available for installation.

C. The Contractor shall provide a report with a list of parts and material that will be used to perform this refurbish on the 138 KV OCB Breaker, and this list must include the following information:

description, brand, lead time, manufacturer with supplier name and location.

D. The Contractor shall purchase and install a new air compressor inside the 138 KV OCB Breaker enclosure. The specifications, size, model will be determined based on the Breaker Requirements and Specifications.

E. The Contractor shall inspect and test insulation resistance (MEGGER) on current communication and signal wires inside the 138 KV OCB Control Cabinet and present a complete report with test results.

Valverde County, Texas

Feb 20,2026 Performance Work Statement

Page-4 of 15

F. The Contractor shall test all the Current Transformers (CT’s) and Bushings and present a report with test results. The test will be according to IEEE standards and shall include Power Factor and Megger

G. The Contractor shall inspect/repair (if necessary) all the Mechanical Hardware for the Breaker Enclosure Door.

H. The Contractor shall inspect and replace all Heathers and Moisture Protection Devices (If Necessary). Also, The Contractor shall inspect all the connection boards and replace wire connection hardware as necessary for all the signal wire inside the enclosure.

I. This list of equipment/parts/material with the information shall reviewed and approved by Amistad Power Plant Superintendent, via e-mail Juan Escobar via e-mail juan.escobar@ibwc.gov prior to be purchased.

J. The Contractor shall submit a project schedule with outage dates, maintenance schedule, and installation with Amistad Power Plant Superintendent Juan Escobar via e-mail juan.escobar@ibwc.gov for review and approval.

K. The Contractor is responsible to remove and properly disposal of current insulator dielectric oil inside the Oil Circuit Breaker (OCB) Tank.

L. The Contractor shall purchase, and install New Insulator Oil with High Dielectric Strength, based on this OCB Breaker Specifications., The brand, and specifications for this type of Oil will be provided by Power Plant Superintendent on a later date. Also, Contractor is responsible to properly dispose the old oil according to latest standards.

M. Contractor shall purchase and submit the type of sand to perform the sandblast clean on the OCB Tank and Breaker Enclosure and provide type and specifications to Power Plant Superintendent prior to purchase

N. The Contractor shall purchase epoxy paint for the OCB Tank and Breaker Enclosure and provide type and specifications to Power Plant Superintendent prior to purchase.

O. IBWC Personnel is responsible to perform the Electrical Clearance prior to perform this maintenance project and Contractor must be present and agree with the clearance process and install their own locks for this tag out clearance.

P. The Contractor shall submit a Job Safety Analysis (JSA) Form filled out to be reviewed by Power Plant Personnel.

Q. Conduct a Safety Meeting with all the personnel involved in the project and Power Plant Personnel prior to start the project.

mailto:juan.escobar@ibwc.gov

Valverde County, Texas

Feb 20,2026 Performance Work Statement

Page-5 of 15

2.2 Clean-Up and Disposal of Waste Materials

A. The Contractor shall be responsible for the cleanup and disposal of waste materials and rubbish from the site, field office(s), and staging area(s).

B. The disposal of waste materials and rubbish shall be in accordance with applicable Federal, state, and local laws and regulations and with the requirements in these Contract documents. Should a conflict exist in the requirements for cleanup and disposal of waste materials, the most stringent requirements shall apply.

1. All waste unless otherwise noted in these specifications shall be disposed of at a licensed landfill or waste disposal facility.

2. Recyclables

a. The Contractor shall dispose of recyclable and reusable products through waste disposal only as a last option.

b. Scrap metal shall be donated or sold to scrap dealers or recycle centers whenever possible.

C. No excess materials shall be deposited within Government property, unless compliance confirmed by the Government. Excess materials not compliance confirmed by the Government for placement on Government property shall be disposed of or reused by the Contractor at another site.

D. The Contractor shall maintain work and storage areas free from accumulations of waste materials and rubbish and before completing the work, shall remove all temporary facilities, including, buildings, unused materials, concrete forms, and other like materials, which are not a part of the permanent work.

2.3 Testing and Training

The Contractor shall test the breaker to verify proper function of this 138 KV OCB Breaker and provide training to power plant personnel at project completion prior to project acceptance.

2.4 Warranty

A. The Contractor shall warrant that work performed under this PWS conforms to the Contract requirements and is free of any defect in equipment, material, or workmanship performed by the

Contractor or any subcontractor or supplier at any tier for a period of at least two (2) years.

1. The Contractor is responsible for providing warranties on items when the manufacturer's warranty is less than the period indicated in Paragraph 2.4B A or when the manufacturer's warranty does not cover full repair and/or replacement as appropriate.

B. The Contractor shall obtain warranties from responsible subcontractors, suppliers, and manufacturers, within sixty (60) days after completion of the applicable item of work, but no later than the date of warranty commencement.

C. Starting date of warranty is date of substantial completion.

D. A warranty requires that if a warranted item fails to meet Contract requirements, it shall be repaired, replaced, or have other remedial actions taken to bring the item into compliance with the Contract requirements. Any item damaged due to failure or malfunction of item warranted under this

Contract shall be repaired or replaced at no cost to the Government.

Valverde County, Texas

Feb 20,2026 Performance Work Statement

Page-6 of 15

E. The Contractor shall supply the CO with a telephone number, mailing address, email address, and contact name for the point of contact for any required warranty work.

SECTION 3

EXISTING CONDITIONS

3.1 General

A. There is only one 138 KV Oil Circuit Breaker on Amistad Power Plant and had been in service for more than 50 Years. This OCB is critical equipment to maintain the Power Plant running and generating power to the Electrical GRID

3.2 Government Furnished Utilities

A. The Government will not be furnishing any utilities for this project including, but not limited to:

electricity, telephone, sewer, and natural gas.

3.3 Use of Government Land

A. The Contractor's facilities shall be arranged and operated in a manner to preserve and protect existing features, trees, and vegetation to the maximum extent practicable. The location, construction, operation, maintenance, and removal of Contractor's facilities on Government land shall be subject to the approval of the COR.

B. USIBWC land is not available for use for the Contractor's field office and/or sheds.

C. USIBWC property is available for use as the Contractor's staging and/or storage areas.

D. Housing for Contractor personnel will not be permitted on Government land.

3.4 Hazardous Materials

The wiring inside the control boards is a mixture of old and new wiring. Note that the original control wiring that has the fabric sheath typically contains around 30% non-friable asbestos embedded in an inner layer of rubber and should be handled and disposed of properly.

SECTION 4

QUALITY REQUIREMENTS

4.1 Common Product Requirements

A. Materials Certification

The Contractor shall submit a materials certification package to COR which contains a checklist and supporting documentation for all materials used on the project. The supporting documentation shall consist of a summary of all documentation practices utilized for material acceptance and explanations of any deficiencies noted on the checklist.

1. Material certifications shall ensure that all items meet the Buy American Act (41 USC 10a -

10d).

Valverde County, Texas

Feb 20,2026 Performance Work Statement

Page-7 of 15

B. Source Control

1. The Contractor shall use only materials that meet the Contract requirements.

2. Unless otherwise specified or compliance confirmed, the Contractor shall use new materials for the work. Material can be reused onsite upon written approval of COR.

3. All materials installed shall be free of defects.

4. The Contractor shall secure the Government’s compliance confirmation of the proposed source of materials to be used before their delivery.

C. Quality Control / Quality Assurance of Materials

1. Source Limitations

To the greatest extent possible for each item of work, the Contractor shall provide materials of a singular generic kind from a single source.

2. Compatibility of Options

Where more than one choice is available as options for Contractor's selection of a product, material, or equipment, the Contractor shall select an option which is compatible with other products, materials, or equipment. Compatibility is a basic general requirement of product, material, and equipment selections.

3. Field Measurements

Verify field measurements, lines, grades, locations, and details at the jobsite prior to fabrication. It shall be the Contractor's responsibility to conform to and satisfy actual field conditions, for accuracy of dimensions, proper fit, and for adequacy of use intended.

4. The Contractor shall correct or remove materials that fail to meet Contract requirements or that do not produce satisfactory results. The Contractor shall reimburse the Government for cost incurred if additional quality assurance sampling and testing is required by a change of source.

5. Materials not meeting Contract requirements will be rejected, unless the Government approves corrective actions in writing. Upon rejection, the Contractor shall immediately remove and replace rejected materials. Should the Contractor fail to comply with the removal of rejected materials, the Government may remove and replace defective material and the cost of testing, removal, and replacement will be deducted from the Contractor’s monthly pay estimate or final payment.

D. Hazardous Materials

The Contractor shall use materials that are free of hazardous materials. The Contractor shall notify the Government immediately when a visual observation or odor indicates that materials in required material sources or on sites owned or controlled by the Government may contain hazardous materials.

E. Surplus Materials

1. The Contractor shall take ownership of surplus materials unless otherwise indicated in the

Contract documents.

2. The Contractor shall remove and dispose of materials in accordance with Paragraph 2.2 If requested or otherwise noted in these specifications, the Contractor shall provide an appropriate level of documentation to verify proper disposal.

Page-8 of 15

F. Storage and Protection

1. Designate receiving/storage areas for incoming products so that they are delivered according to installation schedule and placed convenient to work area in order to minimize waste due to excessive materials handling and misapplication.

2. Store and protect products in accordance with manufacturers' instructions.

3. Store with seals and labels intact and legible.

4. Prevent contact with material that may cause corrosion, discoloration, or staining.

5. Provide equipment and personnel to store products by methods to prevent soiling, disfigurement, or damage.

6. The Contractor shall store and handle materials to preserve their quality and fitness for the work and shall store materials so that they can be easily inspected and retested. When required by the Government, the Contractor shall protect the material with cover, on wooden platforms, or on other hard, clean surfaces as necessary.

SECTION 5

DELIVERABLES

5.1 General

A. Deliverables include, but are not limited to:

1. Project Schedule

a. Project Schedule is to be delivered to COR within seven (7) Calendar Days of contract award.

2. Licenses and Certifications

a. The Contractor shall submit all Licenses and Certifications of electrical engineers and installers.

3. Refurbish a 138 KV OCB Breaker

a. All Specifications and Equipment Description shall be approved by Power Plant

Superintendent and Power Plant Electrical Engineer prior to installation.

4. Installation Procedure Plan

a. The Contractor shall develop a procedure to performance this maintenance project, and avoid disturbing Amistad Power Plant daily operations.

5. Material and equipment certifications

6. Product submittals

7. Safety documents

8. Warranty

Page-9 of 15

SECTION 6

PROJECT COORDINATION & ADMINISTRATION

6.1 General

A. The Contractor shall provide all materials, equipment, labor, and services required by this

Performance Work Statement to perform the work for the Contract sum and within the Contract time.

B. The Contractor shall be responsible for ensuring that all of its suppliers, manufactures and subcontractors have reviewed all applicable documents relative to their work. The Contractor shall provide all labor, material, equipment, and services not provided by the Contractor’s suppliers, manufacturers, fabricators, and/or subcontractors.

6.2 Security

The Contractor is responsible for securing the work site, equipment, and materials from vandalism and theft.

6.3 Safety

A. The Contractor is solely responsible for worksite safety while performing work or inspections on

Government property. The Contractor shall implement a safety program that protects the lives and health of personnel in the project area, prevents damage to property, and avoids work interruptions.

B. The Contractor is responsible for being cognizant of and ensuring compliance with the requirements set forth. Such responsibility shall apply to both the Contractor’s operations and those of the

Contractor’s subcontractors.

C. The Contractor shall comply with all provisions of all applicable regulations of the Occupational

Safety and Health Administration (OSHA), 29 CFR 1910, Occupational Safety and Health

Standards, and 29 CFR 1926, Construction Standards.

1. The OSHA 29 CFR 1910 and 29 CFR 1926 can be accessed at http://www.osha.gov or http://www.gpo.gov/fdsys/.

D. The Contractor’s personnel shall be required to use appropriate personal protective equipment such as, but not limited to: hard hats, safety goggles, welding shields, face shields, protective footwear, protective gloves, and hearing protection.

E. The Contractor shall perform daily housekeeping. The Government will not provide trash dumpsters.

SECTION 7

PROJECT MEETINGS

7.1 General

A. The Contractor, the COR, or the CO may schedule project meetings at any time.

B. When USIBWC schedule's a meeting, the COR shall inform participants and others involved and individuals whose presence is required, of date and time of each meeting. The COR shall prepare the meeting agenda and distribute to all invited attendees.

http://www.osha.gov/ http://www.gpo.gov/fdsys/

Page-10 of 15

C. When the Contractor schedule's a meeting, the Contractor shall inform participants and others involved and individuals whose presence is required, of date and time of each meeting. The

Contractor shall prepare the meeting agenda and distribute to all invited attendees.

D. The following meetings are anticipated and the Contractor shall identify them in the Schedule:

1. Kickoff Meeting

2. Progress Meetings

7.2 Kickoff Meeting

A. After award of the Contract, the COR will coordinate with the Contractor to schedule a Kickoff

Meeting. The meeting shall take place prior to the beginning of any Contract work.

B. The purpose of the meeting is to introduce project personnel and to review responsibilities and procedures.

C. The Contractor shall reach an understanding with the Government regarding the project requirements as stated is this Performance Work Statement. This understanding shall be documented in writing and approved by the CO after the Kickoff Meeting.

D. Attendees include, but are not limited to:

1. Contractor's Project Manager

2. COR

3. Amistad Power Plant Representative

4. It is recommended that Contractor's engineers, inspectors, subcontractors, suppliers, and other concerned parties also attend the conference. The Contractor may invite anyone they wish to this meeting.

5. All participants at the conference shall be familiar with the project and authorized to conclude matters relating to the work.

E. Agenda

Discussion of items of significance that could affect the work and project, including the following:

1. Introduction/designation of key personnel and their duties.

2. Review of the current phasing, critical work sequencing, and long-lead items.

3. Review of minimum project requirements.

4. Review of Job Safety Analysis prepared by Contractor

5. Review of procedures for handling and processing modifications, RFIs, deliverables, and applications for payment.

6. Preparation of deliverable documents.

7. Use of site.

8. Work restrictions.

9. USIBWC and other's occupancy requirements.

10. Safety and first aid.

11. Security.

12. Maintenance of project site.

13. Working hours.

Page-11 of 15

F. Meeting Minutes

The Contractor will record the discussions of the meeting and distribute the minutes to all attendees for review prior to finalizing.

7.3 Progress Meetings

A. The COR will schedule progress meetings once the Contractor has mobilized onsite. The COR will conduct and issue minutes of the meetings. Meeting minutes will become official Contract correspondence.

B. The Government may call other meetings on an "as needed" basis.

C. The purpose of these meetings shall be to analyze the progress of the work, resolve conflicts, and in general coordinate the operation of all organizations active at the project site.

SECTION 8

PROJECT SCHEDULE

8.1 Description / Purpose

A. The Contractor shall prepare a project schedule which shall reflect completion of all work under this

Performance Work Statement and shall include allotted time for all related activities by other agencies within the allotted Contract period.

B. The first compliance confirmed schedule that properly shows all activities within the allotted period shall be the baseline schedule.

8.2 Schedule Requirements

A. Project schedule submittals for compliance confirmation shall include an electronic pdf file.

1. All abbreviations shall be defined.

2. Each project schedule shall show a revision date.

B. The Contractor shall provide an updated schedule with any invoices.

C. Schedule Requirements

1. Baseline Schedule

a. A complete baseline schedule shall be submitted. The Government will review the project schedule and submit comments and required revisions within fourteen (14) calendar days of receipt.

(1) Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing all work within applicable completion dates, regardless of Government's compliance confirmation of the schedule.

b. Upon compliance confirmation of the baseline schedule, save the schedule as a baseline and update on a monthly basis. The schedule update will be used to evaluate the

Contractor's progress and invoice payments.

Page-12 of 15

2. Baseline Schedule Preparation

Prepare a list of all activities required to complete the work. The baseline schedule shall include all planned work activities and sequences and show Contract completion within the number of calendar days specified in the Contract.

a. Activities

(1) Indicate the estimated duration, sequence requirements, and relationship of each activity in relation to other activities.

b. The baseline schedule as developed shall show the sequence and interdependence of activities required for complete performance of the work.

c. Time Frame

Proposed duration assigned to each activity shall be the Contractor's best estimate of time required to complete the activity considering the scope and resources planned for the activity.

(1) Incorporate inspections, permitting, repairs, and other activities that may affect the completion of the Contract in the project schedule.

(2) Show a beginning date, ending date, and duration in number of calendar days for each activity.

(3) Show float for each work activity.

d. Constraints

Include constraints and work restrictions in schedule and show how the sequence of work is affected.

e. Milestones

Include milestones indicated in this document in schedule, including, but not limited to, the cleaning, inspection, repair, or other items as determined by the Contractor.

SECTION 9

REGULATORY REQUIREMENTS

9.1 Contractor's Responsibility

A. It is the Contractor’s responsibility to perform work in compliance with all applicable requirements of federal, state, and local laws, codes, rules, regulations, ordinances, and standards, including, but not limited to, those outlined in 9.4 below.

B. It shall be the responsibility of the Contractor to acquire copies of all applicable codes, regulations, and standards for ready reference.

C. In instances where requirements are in conflict, the stricter standard shall apply.

D. Any and all inspections, observations, or tests required for code compliance are the responsibility of the Contractor.

9.2 Permits

A. Prior to the beginning of work, the Contractor shall be responsible for researching, coordinating, obtaining, and paying all applicable fees for all permits required by Federal, state, and local entities.

The Government is not responsible for any existing or newly introduced permits required before, during and/or after work on of this project.

Page-13 of 15

B. The Contractor shall be responsible for and shall give and maintain any and all notices required by applicable regulations, laws, or permitting authorities pertaining to work on of this project.

C. Building Permits

1. USIBWC is not required to obtain building permits from local jurisdictions on real estate owned or controlled by USIBWC. However, work on utility connections, sewer connections, and fire-protection systems may require liaison with local jurisdictions. The Contractor shall be responsible for identifying the coordination required.

2. Though the USIBWC is not required to obtain building permits from local jurisdiction, the

Contractor shall comply with state and local building codes to the maximum extent practicable. USIBWC has the final authority to accept or reject any recommendation from state and/or local government officials.

9.3 Dates

A. For all related standards and regulatory requirements in this document, the version, edition, or year shown indicates the governing version.

B. All Public Laws, Code of Federal Regulations (CFR), Federal Acquisition Regulation (FAR), Executive Orders (EOs), Management Policies, Government Directives, Government Standards, refer to the original document as well as any subsequent amendments, corrections, and/or additions.

1. The latest amendments, corrections and additions are to be assumed applicable in the same way as the document itself.

2. The version in effect as of the issuing date of the Solicitation for this project governs unless the law, regulation, order, policy, directive, or standard is updated with a retroactive clause.

9.4 Summary of Regulatory Documents and Agencies

Regulatory requirements applicable to this project are listed below.

A. Institute of Electrical and Electronics Engineers (IEEE)

1. 2017 National Electrical Safety Code (NESC)

B. National Fire Protection Association (NFPA)

1. NFPA 70-2017 Standard for Electrical Safety in the workplace (also known as the National

Electrical Code [NEC]), with Errata through 70-17-4 and TIA through 17-4

C. Occupational Safety and Health Administration (OSHA)

1. Occupational Safety and Health Standards (29 CFR 1910)

a. https://www.osha.gov/law-regs.html

2. Construction Standards (29 CFR 1926)

a. https://www.osha.gov/pls/oshaweb/owasrch.search_form?p_doc_type=STANDARDS& p_toc_level=1&p_keyvalue=Construction

D. State of Texas

1. Texas Engineering Practice Act and Rules Concerning the Practice of Engineering and

Professional Engineering Licensure

a. http://www.tbpe.state.tx.us/downloads/law&rules.pdf https://www.osha.gov/law-regs.html https://www.osha.gov/pls/oshaweb/owasrch.search_form?p_doc_type=STANDARDS&p_toc_level=1&p_keyvalue=Construction https://www.osha.gov/pls/oshaweb/owasrch.search_form?p_doc_type=STANDARDS&p_toc_level=1&p_keyvalue=Construction http://www.tbpe.state.tx.us/downloads/law&rules.pdf

Page-14 of 15

SECTION 10

MEASUREMENTS AND PAYMENTS

10.1 Schedule of Values

A. Breakdown each lump sum item into component work activities used in the schedule for which invoices may be requested. The work activities broken out within the Schedule of Values shall be integrated into and made a logical part of the baseline schedule submitted under this section.

1. The total costs for the component work activities shall equal the Contract price for that lump sum item.

2. Overhead, general and administrative expenses, escrow, bonds, profit, and other across the board markups shall be applied to each line in the Schedule of Values uniformly.

3. An unbalanced Schedule of Values providing for overpayment to the Contractor for items of work to be performed first will not be compliance confirmed but shall be revised by the

Contractor and resubmitted until acceptable to the COR. If requested by the Government, the

Contractor shall furnish full copies of subcontracts showing actual costs.

4. The Government may request data to verify accuracy of dollar values.

B. Do not break down unit price items. Use only the Contract price for unit price items.

C. An acceptable Schedule of Values shall be agreed upon by the Contractor and COR before the first invoice is processed.

D. The following items shall have an entry in the Schedule of Values. The Contractor may breakdown each item listed into subsections if they so choose. The Contractor may add additional items. The items shown are the minimum required.

1. Mobilization/Demobilization

2. Maintenance/Refurbish Improvements

3. Training

10.2 Progress Payment (Lump Sum CLIN)

A. The Schedule of Values shall be used to prepare an invoice request for the items, or portions of items, of the work completed during the monthly progress period.

B. As the activity progresses, the Contractor will be paid the value based on the percentage associated with the activity in the Schedule of Values.

C. The progress payments are made to benefit the Contractor. These payments are made based upon preliminary deliverables, preliminary field inspections, preliminary testing data, and/or preliminary reports. Progress payments do not constitute acceptance of any portion of the work and do not reduce the Contractor’s liability to replace unsatisfactory work, material, or equipment.

D. No progress payment will be made when, in the judgment of the Government, the work is not proceeding in accordance with the provisions of the Contract.

Valverde County, Texas

Feb 20,2026 Performance Work Statement

Page-15 of 15

10.3 Invoices

A.

B.

USIBWC Payment Processing

A. The Contractor shall submit an electronic invoice pursuant to FAR 5.212-4(g) to be processed via the IPP system at www.ipp.gov. B. A copy of the invoice shall be emailed to the

CO and COR concurrently.

C. C. The invoice for this Contract shall not be combined with any other work or other Contracts;

it shall be for this Contract only.

--End of Performance Work Statement--