UPDATED-528-19-102-BuffaloUrology Combined Specifications 05-18-2026.pdf
PDF 12 MB Posted
- Solicitation number
- 36C24226B0065
About this file
This is a comprehensive 100% construction specification and design document for the renovation of the Urology Department at Buffalo Veterans Medical Center (VAMC), Project 528-19-102. The project scope encompasses the renovation of two Cystoscopy rooms (214 and 215), Procedure Rooms (211 and 212), a control room (215-1), electrical room (214-1), check-in area, office, vestibule, dressing area, toilet facilities, and corridor. The anticipated construction period is 720 days, with the document issued for construction on April 29, 2026. The specifications are organized into 28 divisions following CSI standards, covering structural steel, metals, wood, thermal and moisture protection, openings, finishes, specialties, furnishings, special construction, fire suppression, plumbing, HVAC, electrical, communications, and electronic safety and security systems. The construction documents include detailed architectural, structural, mechanical, plumbing, electrical, fire protection, and telecommunications drawings with specific requirements for installation, testing, commissioning, and coordination of all building systems.
The contractor must comply with extensive site management and operational requirements, including VA security procedures requiring PIV badges for all personnel, restricted parking areas, key control protocols, and document security measures. The contract requires coordination with VA utility services, maintenance of minimum 40-degree Fahrenheit temperatures, and adherence to phasing plans to minimize disruption to ongoing medical center operations. Key deliverables include shop drawings, product data, as-built drawings, warranty management documentation, training and instruction manuals, photographic documentation (150-200 photos with online indexing), testing and commissioning reports, and final elevation digital images. The contractor must establish a submittal register, coordinate with manufacturer representatives for installation and training, conduct final inspections, and maintain equipment warranties throughout construction. The document emphasizes quality control, infection control risk assessment compliance, and comprehensive documentation requirements for all construction phases through project closeout.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24226B0065 0001.docx | DOCX document | |
| UPDATED- Final Construction Drawings-2_01.pdf | ||
| FAR 52.225-2 Buy American Certification.pdf | ||
| 36C24226B0065_1.docx | DOCX document | |
| Facility Approved Finishes and Devices.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF VETERANS AFFAIRS
SPECIFICATIONS
“Renovate Urology”
Project Number 528-19-102
100% CONSTRUCTION DOCUMENTS
ISSUED FOR CONSTRUCTION
For
Buffalo VAMC - Buffalo, NY
April 29th, 2026
00 01 10-1
Buffalo VAMC Design Urology Equipment Site Prep
Buffalo, NY Project# 528-CSI-102
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 10 Masters Specifications Index
00 01 15 List of Drawing Sheets 10-24
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21
01 33 23 Shop Drawings, Product Data, and Samples 06-21
01 35 26 Safety Requirements 11-21
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 57 19 Temporary Environmental Controls 01-21
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 04-22
01 91 00 General Commissioning Requirements 04-22
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-18
05 50 00 Metal Fabrications 08-18
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
06 16 63 Cementitious Sheathing 01-21
06 20 00 Finish Carpentry 01-21
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 13 Thermal Insulation 01-21
07 84 00 Firestopping 01-21
07 92 00 Joint Sealants 04-22
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21
08 14 00 Interior Wood Doors 01-21
08 17 10 Integrated Door Assemblies 01-21
08 31 13 Access Doors and Frames 04-22
08 71 00 Door Hardware 05-22
08 71 13 Automatic Door Operators 01-21
00 01 10-2
Buffalo, NY Project# 528-CSI-102
SECTION NO. DIVISION AND SECTION TITLES DATE
08 80 00 Glazing 01-21
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21
09 22 16 Non-Structural Metal Framing 06-18
09 29 00 Gypsum Board 04-20
09 51 00 Acoustical Ceilings Tile 12-18
09 65 13 Resilient Base and Accessories 01-21
09.67.23.40 Resinous Poured In Place Resilient Flooring 01-21
09 91 00 Painting 01-21
DIVISION 10 – SPECIALTIES
10 14 00 Signage 01-21
10 26 00 Wall and Door Protection 01-21
10 28 00 Toilet, Bath, and Laundry Accessories 01-21
10 44 13 Fire Extinguisher Cabinets 08-18
DIVISION 12 – FURNISHINGS
12 31 00 Manufactured Metal Casework 01-21
12 32 00 Manufactured Wood Casework 01-21
12 36 00 Countertops 12-18
DIVISION 13 - SPECIAL CONSTRUCTION
13 49 00 Radiation Protection 01-21
DIVISION 21- FIRE SUPPRESSION
21 08 00 Commissioning of Fire Suppression System 11-16
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 09-20
22 07 11 Plumbing Insulation 09-19
22 08 00 Commissioning of Plumbing Systems 11-16
22 11 00 Facility Water Distribution 05-21
22 13 00 Facility Sanitary and Vent Piping 09-20
22 40 00 Plumbing Fixtures 09-15
22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 09-15
22 63 00 Gas Systems for Laboratory and Healthcare Facilities 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 04-22
23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment
02-20
00 01 10-3
Buffalo, NY Project# 528-CSI-102
SECTION NO. DIVISION AND SECTION TITLES DATE
23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20
23 07 11 HVAC and Boiler Plant Insulation 02-20
23 08 00 Commissioning of HVAC Systems 04-22
23 09 23 Direct-Digital Control System for HVAC 09-11
23 21 13 Hydronic Piping 02-20 23 22 13 Steam and Condensate Heating Piping 02-20 23 31 00 HVAC Ducts and Casings 02-20
23 36 00 Air Terminal Units 02-20
23 37 00 Air Outlets and Inlets 02-20
23 40 00 HVAC Air Cleaning Devices 03-20
23 50 00 Indoor Central-Station Air-Handling Units 03-20
23 73 00 Mechanical Skid Package 03-20
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17
26 05 26 Grounding and Bonding for Electrical Systems 01-17
26 05 33 Raceway and Boxes for Electrical Systems 01-18
26 05 73 Overcurrent Protective Device Coordination Study 01-18
26 09 23 Lighting Controls 01-18
26 20 11 Isolated Power Systems 01-18
26 22 00 Low-Voltage Transformers 01-18
26 24 16 Panelboards 01-18
26 27 26 Wiring Devices 01-18
26 29 11 Motor Controllers 01-18
26 29 21 Enclosed Switches and Circuit Breakers 01-17
26 43 13 Surge Protective Devices 01-17
26 51 00 Interior Lighting 01-18
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 09-19
27 05 26 Grounding and Bonding for Communications Systems 06-15
27 05 33 Raceways and Boxes for Communications Systems 10-18
27 10 00 Control, Communication and Signal Wiring 06-15
27 15 00 Communications Structured Cabling 01-16
27 52 23 Nurse Call and Code Blue Systems 10-18
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18
28 05 13 Conductors and Cables for Electronic Safety and
Security
10-18
28 05 26 Grounding and Bonding for Electronic Safety and
Security
09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and
Security
09-11
28 13 00 Physical Access Control System 10-11
28 31 00 Fire Detection and Alarm 10-11
Buffalo, NY Project #528-CSI-102 10-17-24
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GENERAL
GI001 COVER SHEET
GI002 ABBREVIATIONS AND SYMBOLS
GI003 INTERIOR PARTITIONS & TOP OF WALL DETAILS
GI004 ASBESTOS REPORT FINDINGS
GI005 ASBESTOS REPORT FINDINGS
GI006 ICRA RISK ASSESSMENT
GI100 CODE COMPLIANCE PLAN
GI101 INFECTION AND DUST CONTROL PLAN – FIRST FLOOR
GI102 INFECTION AND DUST CONTROL PLAN – SECOND FLOOR
GI103 PHASING PLAN – FIRST FLOOR
GI104 PHASING PLAN – SECOND FLOOR
GI105A ICRA DETAILS
GI105B ICRA DETAILS
STRUCTURAL
S001 STRUCTURAL GENERAL NOTES
S002 STRUCTURAL GENERAL NOTES
S003 LIGHT CAGE FRAMING DETAILS
S004 EQUIPMENT BRACING AND ANCHORAGE DETAILS
S401 FRAMING DETAILS
SF101 FRAMING MODIFICATION PLANS
SF102 FRAMING MODIFICATION PLANS
ARCHITECTURAL
AC111 REFLECTED CEILING PLAN
AD100 DEMOLITION PLAN – FIRST FLOOR
AD101 DEMOLITION PLAN – SECOND FLOOR
AE100 OVERALL BUILDING PLANS
AE102 PROPOSED FLOOR PLAN – SECOND FLOOR
AE401 ENLARGED PLANS
AE402 ENLARGED PLANS
00 01 15 - 2
AE403 ENLARGED PLANS
AE404 ENLARGED PLANS
AE501 DETAILS - BUILDING
AE521 DETAILS – CASEWORK
AE601 SCHEDULE – DOOR
ID101 FINISH PLAN & SCHEDULE
ID601 FINISH SAMPLES
IF101 FURNITURE PLAN
FIRE PROTECTION
FP001 FIRE PROTECTION LEGEND, DETAILS & GENERAL NOTES
FD102 SECOND FLOOR FIRE PORTECTION DEMOLITION PLAN
FP102 SECOND FLOOR FIRE PROTECTION PLAN
MECHANICAL
M001 MECHANICAL LEGEND AND ABBREVIATIONS
M002 MECHANICAL GENERAL NOTES
MD102 SECOND FLOOR MECHANICAL DEMOLITION PLAN
MH102 SECOND FLOOR HVAC DUCTWORK PLAN
MP102 SECOND FLOOR HVAC PIPING
M401 ENLARGED MECHANICAL ROOM & PARTIAL ROOF PLAN
M501 MECHANICAL DETAILS
M601 MECHANICAL SCHEDULES
M602 MECHANICAL SCHEDULES
M651 MECHANICAL SCHEMATICS
PLUMBING
P001 PLUMBING LEGEND AND ABBREVIATIONS
PD102 SECOND FLOOR PLUMBING DEMOLITION PLAN
PG102 SECOND FLOOR MEDICAL GAS PLAN
PL101 UNDERFLOOR PLUMBING PLAN
PL102 SECOND FLOOR PLUMBING PLAN
P501 PLUMBING DETAILS AND SCHEDULES
ELECTRICAL
E001 ELECTRICAL LEGEND, GENERAL NOTES, AND ABBREVIATIONS
00 01 15 - 3
E501 ELECTRICAL DETAILS
E502 ELECTRICAL DETAILS
E901 ELECTRICAL PHOTOGRAPHS
E902 ELECTRICAL PHOTOGRAPHS
E903 ELECTRICAL PHOTOGRAPHS
E904 ELECTRICAL PHOTOGRAPHS
E905 ELECTRICAL PHOTOGRAPHS
E906 ELECTRICAL PHOTOGRAPHS
E907 ELECTRICAL PHOTOGRAPHS
E908 ELECTRICAL PHOTOGRAPHS
E909 ELECTRICAL PHOTOGRAPHS
E910 ELECTRICAL PHOTOGRAPHS
E911 ELECTRICAL PHOTOGRAPHS
ED101 ELECTRICAL DEMOLITION PLAN – SECOND FLOOR
EL101 ELECTRICAL LIGHTING PLAN – SECOND FLOOR
EL501 LIGHT FIXTURE SCHEDULE
EL502 ELECTRICAL LIGHTING DETAILS
EL503 LIGHT FIXTURE CUT SHEETS
EL504 LIGHT FIXTURE CUT SHEETS
EL505 NORMAL LIGHTING CALCULATION – SECOND FLOOR
EL506 EMERGENCY LIGHTING CALCULATIONS – SECOND FLOOR
EM101 MOTOR & EQUIPMENT PLAN – SECOND FLOOR
EM102 MOTOR & EQUIPMENT PLAN – FOURTH FLOOR ROOF
EM601 MOTOR AND EQUIPMENT SCHEDULE
EP100 ELECTRICAL POWER PLAN – FIRST FLOOR
EP101 ELECTRICAL POWER PLAN – SECOND FLOOR
EP102 ENLARGED ELECTRICAL POWER PLAN – SECOND FLOOR
EP103 ELECTRICAL POWER PLAN – SECOND FLOOR
EP401 PARTIAL ONE LINE DIAGRAM AND FEEDER SCHEDULE
EP402 ELECTRICAL SCHEDULES AND DETAILS
EP403 SIEMENS UROSKOP OMNIA DETAILS
EP404 SIEMENS UROSKOP OMNIA DETAILS
EP601 ELECTRICAL PANEL SCHEDULES
EP602 ELECTRICAL PANEL SCHEDULES
EP603 ELECTRICAL PANEL SCHEDULES
EP604 ELECTRICAL PANEL SCHEDULES
00 01 15 - 4
ES101 ELECTRICAL SITE PLAN
ET101 ELECTRICAL TELECOMMUNICATIONS PLAN – SECOND FLOOR
ET102 ELECTRICAL TELECOMMUNICATIONS PLAN – SECOND FLOOR
ET501 ELECTRICAL TELECOMMUNICATIONS DETAILS
EY101 ELECTRICAL SYSTEMS PLAN – SECOND FLOOR
EY102 ELECTRICAL SYSTEMS PLAN – SECOND FLOOR
EY501 NURSE CALL RISER DIAGRAM AND NURSE CALL DETAILS
FA001 FIRE ALARM LEGEND, GENERAL NOTES AND ABBREVIATIONS
FA101 FIRE ALARM PLAN – SECOND FLOOR
FA102 FIRE ALARM PLAN – SECOND FLOOR
FA103 PARTIAL FIRE ALARM RISER DIAGRAM AND FIARE ALARM MATRIX
- - - END - - -
11-10-21
01 00 00 - 1
Buffalo, NY Project# 528-CSI-102
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work.
B. Visits to the site by Bidders may be made only by appointment with the
Medical Center Engineering Officer.
C. Offices of Paradigm Engineers and Constructors, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the
Government without affirmations by Contracting Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.4 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
01 00 00 - 2
Buffalo, NY Project# 528-CSI-102
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Every Contractor (Subcontractor included) must have a physical access PIV Badge. This has to be a current VA issued badge but does not need to be issued at this facility. This requires a minimum of 2 scheduled visits to a VA- to get fingerprints taken (approx. 1 hr.), to get sponsored (approx. 30 min) and to get the badge (approx. 1 hr.). The second two are possible to get done in one day. The only exception is contractors who do not need access to the VA buildings and who is also just working for the day.
3. Badges must be worn and visible at all times on the jobsite.
4. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
5. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including toolboxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71
00, DOOR HARDWARE and coordinate.
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
01 00 00 - 3
Buffalo, NY Project# 528-CSI-102
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. Motor Vehicles belonging to any contractor must be registered at the
Police HQ in Bldg. 25, Eagle building and attain a parking pass for employee lots. This includes personally owned and company vehicles.
These must be visibly displayed at all times while parked on VAMC campus.
3. Contractor parking will be limited to Lots N and P and by written permission of the COR at any other employee lot. There will be
01 00 00 - 4
Buffalo, NY Project# 528-CSI-102 absolutely no parking in patient parking spaces or ADA spaces
(unless the contractor has an applicable decal/tag).
4. Parking is rigidly controlled throughout the Medical Center.
Contractor parking is only allowed in designated areas (subject to change). Parking in designated patient parking areas is strictly prohibited. Parking on grass is also prohibited. Parking in roadways is prohibited. Parking for equipment necessary to perform the work will be authorized in advance of starting the project.
1.5 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers, and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined and coordinated with by the COR.
E. Provide Logistics Plan that includes delivery routes, container/equipment staging, temporary toilets, dumpsters, expected
01 00 00 - 5
Buffalo, NY Project# 528-CSI-102 ingress and egress if applicable, location of fencing for work area and laydown area, parking, etc.
F. All containers / pallets must be marked with the contract/task order number and 8 digit project number. Dumpster locations (not the individual dumpsters) will also be marked if used over 5 business days.
G. Workers are subject to rules of Medical Center applicable to their conduct.
H. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
I. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two workdays. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
J. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
K. Phasing:
01 00 00 - 6
Buffalo, NY Project# 528-CSI-102
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service interrupting any portion of the VA campus beyond Building 14 must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to ensure accomplishment of this work in successive completion mutually agreeable to Medical Center Director, COR and Contractor, as follows:
L. Building No. 14_ will be vacated during performance of work. The work shall be accomplished in one overall phase, with work items as shown in the contractor’s approved schedule.
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access.
Coordinate alteration work in areas occupied by Department of
Veterans Affairs so that Medical Center operations will continue during the construction period.
01 00 00 - 7
Buffalo, NY Project# 528-CSI-102
2. Immediate areas of alterations not mentioned in preceding
Subparagraph 1 will be temporarily vacated while alterations are performed.
M. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings.
Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm
(one inch) above grade. Remove the fence when directed by COR. All work areas and laydown spaces are required to be fenced.
N. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
O. Utilities Services: Maintain existing utility services for Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a
01 00 00 - 8
Buffalo, NY Project# 528-CSI-102 detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR
COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR
ELECTRONIC SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
P. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged-in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
Q. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
01 00 00 - 9
Buffalo, NY Project# 528-CSI-102
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
R. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.6 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by all three, to the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR and/or Supply Representative, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by
Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE
CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on
01 00 00 - 10
Buffalo, NY Project# 528-CSI-102 conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.7 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to
01 00 00 - 11
Buffalo, NY Project# 528-CSI-102 be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
a) Copies of the following listed CFR titles may be obtained from the Government Printing Office:
40 CFR 261........Identification and Listing of Hazardous Waste
40 CFR 262........Standards Applicable to Generators of Hazardous
Waste
40 CFR 263........Standards Applicable to Transporters of
Hazardous Waste
40 CFR 761........PCB Manufacturing, Processing, Distribution in
Commerce, and use Prohibitions
49 CFR 172........Hazardous Material tables and Hazardous
Material Communications Regulations
49 CFR 173........Shippers - General Requirements for Shipments and Packaging
49 CRR 173........Subpart A General
49 CFR 173........Subpart B Preparation of Hazardous Material for
Transportation
49 CFR 173........Subpart J Other Regulated Material; Definitions and Preparation
TSCA..............Compliance Program Policy Nos. 6-PCB-6 and 6-
PCB-7
1.8 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS (FAR 52.236-9)
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by
01 00 00 - 12
Buffalo, NY Project# 528-CSI-102 the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the
Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
01 00 00 - 13
Buffalo, NY Project# 528-CSI-102
1.11 COORDINATION
A. Coordinate work and products meeting the requirements associated with all applicable specification sections and plans to produce a system complete, functional and ready for the purpose intended.
B. Pre-worksite Re-visit Requirements: Before starting work in a particular area, visit the worksite and carefully examine the areas to verify complexity, existing conditions and difficulties that will affect work including all work done under various specification sections and the VA. Commencement of work shall be construed as acceptance of the existing conditions and difficulties. No change to the contract price or schedule shall be allowed for work caused by unfamiliarity with the site conditions that are visible or readily construed by an experienced observer.
C. Coordinate the location of all work, equipment and components with all trades and equipment installers to prevent interferences, and maintain proper use and access to all items and spaces. Refer to the
“Coordination Drawing Checklist” for further details. General
Contractor is responsible for coordinating all equipment and components being installed with the placement location and dimension requirements.
Prior to job execution each trade shall submit “complete” coordinated shop drawings indicating all equipment and material layouts with locations from walls/columns, bottom/top elevations, vibration isolators, supports, dimensions, utility requirements and equipment submittal numbers. Each trade shall maintain a set of working drawings to document as-built information as the work progresses and submit to the COR monthly for review.
D. New work shall be installed and connected to existing work neatly and carefully. All work shall be coordinated with other trades to avoid conflicts and to obtain a neat competent installation that will afford maximum accessibility for easy and proper operation, maintenance, service and headroom. All work shall be installed in a manner that permits easy accessibility and proper removal of system components requiring periodic service. Disturbed or damaged work shall be replaced or repaired to new conditions. Any items determined to be in non-compliance shall be corrected by the Contractor at no additional expense to the Government.
01 00 00 - 14
Buffalo, NY Project# 528-CSI-102
E. The drawings show or describe the general arrangement of equipment, articles, assemblies, appurtenances but do not show all required fittings, drains, air vents, supports and may not identify all required accessories, components, fittings, and offsets that are necessary to properly complete the installation for the purpose intended. The contract drawings are diagrammatic only intended to show general layout of conduit, ductwork, piping, equipment, terminals, specialties and not intended to show all required offsets, details, accessories and equipment to be connected. Provide all necessary fittings, offsets and pipe runs based on field measurements and reviewed coordination drawings. Coordinate with other trades for space available and relative location of equipment and accessories to be connected at all locations. The Contractor shall alter locations of items where necessary to avoid interference and clearance difficulties. Locations of components and equipment shall be adjusted to accommodate the work with interferences anticipated and encountered. The Contractor shall determine the exact routing and location of systems prior to fabrication and installation. Accurate field measurements and coordination drawings shall be prepared to establish the locations and characteristics of the various systems (new and existing to remain).
It is the intent of the drawings/specifications that the Contractor provides all materials, labor and coordination necessary to complete the work described or implied by the contract documents at no additional cost/time to the Government. The Contractor shall propose with submitted coordination drawings other dimensions with similar characteristics where necessary to avoid interferences and clearance difficulties. Should the contract documents not agree with themselves the greater quantity of superior work and materials shall be performed.
F. Coordinate all mechanical (eg, HVAC), electrical, plumbing (MEP) utility service, fire protection sprinkler system shutdowns and space access three (3) weeks in advance with the COR. Due to facility scheduling and access difficulties, some shutdowns and the performance of certain work will need to be performed during off-hours by the
Contractor. Arrange phases and perform work to insure utility services for other buildings and areas at all times as required.
G. Before placement and installation of work subject to tests the
Contractor shall coordinate and notify the COR in sufficient time to
01 00 00 - 15
Buffalo, NY Project# 528-CSI-102 enable testing personnel to be present at the site in time for proper testing and field inspection. Such prior notice shall be not less than two (2) weeks unless otherwise designated by the COR.
1.12 AS-BUILT/RED-LINE DRAWINGS
A. The contractor shall maintain two full size sets of as-built/red-line drawings which will be kept current during construction of the project, to include all contract changes, modifications, and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built/red-line drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built/red-line drawings in the electronic version (scanned PDF) to the COR within
15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.13 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction at least 30 days before the planned pre-warranty conference, submit two sets of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the
Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:
01 00 00 - 16
Buffalo, NY Project# 528-CSI-102
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
01 00 00 - 17
Buffalo, NY Project# 528-CSI-102
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
1. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.
B. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for
Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for
Contractor response, and other details deemed necessary by the
Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor.
This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This
01 00 00 - 18
Buffalo, NY Project# 528-CSI-102 requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.
C. Contractor’s Response to Construction Warranty Service Requirements:
D. Following oral or written notification by the Contracting Officer, the
Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period.
Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the
Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.
1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.
2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.
3. Third Priority Code 3. All other work to be initiated within 3 workdays and work continuously to completion or relief.
4. The “Construction Warranty Service Priority List” is as follows:
a) Code 1-Life Safety Systems
Fire suppression systems.
Fire alarm system(s).
b) Code 1-Air Conditioning Systems
Air conditioning leak in part of the building, if causing damage.
Air conditioning system not cooling properly.
c) Code 1 Doors
Overhead doors not operational, causing a security, fire or safety problem.
1) Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.
d) Code 3-Doors
Overhead doors not operational.
01 00 00 - 19
Buffalo, NY Project# 528-CSI-102
Interior/exterior personnel doors or hardware not functioning properly.
e) Code 1-Electrical
Power failure (entire area or any building operational after
1600 hours).
Security lights.
Smoke detectors.
f) Code 2-Electrical
Power failure (no power to a room or part of building).
Receptacle and lights not operational (in a room or part of building).
g) Code 3-Electrical
Exterior lights not operational.
h) Code 1-Gas
Leaks and pipeline breaks.
i) Code 1-Heat
Power failure affecting heat.
j) Code 1-Plumbing
Hot water heater failure.
2) Leaking water supply pipes
k) Code 2-Plumbing
Flush valves not operating properly
Fixture drain, supply line or any water pipe leaking.
Toilet leaking at base.
l) Code 3- Plumbing
Leaky faucets.
m) Code 3-Interior
Floors damaged.
Paint chipping or peeling.
Casework damaged.
n) Code 1-Roof Leaks
Damage to property is occurring.
o) Code 2-Water (Exterior)
No water to facility.
p) Code 2-Water (Hot)
No hot water in portion of building listed.
q) Code 3
01 00 00 - 20
Buffalo, NY Project# 528-CSI-102
All work not listed above.
E. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting
Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .