CU Boulder - UCB000998 - SPSC - Restroom Renovations
Solicitation number
Notice No: 25-39
Issued by
Boulder County, Colorado

About this file

This is a Request for Proposals (RFP) for a Design/Bid/Build General Contractor issued by the State of Colorado's Office of the State Architect for the University of Colorado Boulder, specifically for the UCB000998 – SPSC Restroom Renovations project. The project involves converting existing men's and women's restrooms with showers in the SPSC building into a gender-neutral restroom with four toilets and three single occupant shower rooms, with lockers to be placed outside the shower rooms. The base bid includes renovations for specific restroom areas, with additional alternates for other restroom cores on the 1st and 2nd floors. The solicitation follows a two-step pre-qualification and bidding process, with key dates including a mandatory pre-submittal conference on 4/11/2025, RFP submittals due on 4/21/2025, bidding documents available on 4/28/2025, and sealed bids due on 5/13/2025. The projected construction timeline spans from a Notice to Proceed on 6/13/2025 to Final Completion on 7/1/2026.

Contractors must meet specific minimum qualifications, including maintaining a Colorado office for the past five years, successfully completing at least three projects over $500,000, demonstrating bonding capacity of $1,000,000, and complying with state prevailing wage and apprenticeship requirements. The estimated construction cost is $610,000, and the project is subject to various state regulations including the Buy Clean Colorado Act, which requires environmental product declarations for eligible materials. Bidders must be prepared to provide documentation of subcontractor apprenticeship program participation, utilize LCPTracker for labor compliance, and submit comprehensive qualifications demonstrating experience, key personnel capabilities, project management approaches, and local subcontractor involvement. Preference will be given to Colorado resident bidders, and a bid bond of 5% of the total bid is required.

View the file

Other files

File Type Posted
Attestation forms.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP DBB (UCB 2-Step) Rev 09/2024

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

REQUEST FOR PROPOSALS

FOR

DESIGN/BID/BUILD GENERAL CONTRACTOR (UCB 2-Step)

For The

UNIVERSITY OF COLORADO BOULDER

Notice Number: 25-39

For The

UCB000998 – SPSC – Restroom Renovations

REQUEST FOR PROPOSALS FOR A

DESIGN/BID/BUILD GENERAL CONTRACTOR

University of Colorado Boulder

TABLE OF CONTENTS

I. GENERAL INFORMATION

A. Introduction/Description of Project B. Minimum Qualifications C. Scope of Services

II. PREQUALIFICATION SUBMITTALS (STEP I)

A. Schedule B. Mandatory Pre-submittal Conference C. Clarifications D. General Information E. Prequalification Submittals F. Submittal Requirements G. Notes for Subcontractors Qualifications H. Short List

III. BIDDING (STEP II)

IV. EVALUATION CRITERIA

A. PREQUALIFICATION SUBMITTAL CRITERIA

1. General Information

2. Location

3. General Firm Experience

4. Successful Project Completion

5. Bonding Capacity and Insurance

6. Qualifications of Key Personnel

7. Schedule Control

8. Current Workload/Capacity

9. Projected Construction Period

10. Project Management

11. Performance Following Pre-qualifications

12. Percentage of Local Subcontractor Involvement

13. Apprenticeship Training Program (if applicable)

14. Acknowledgement and Attestation

15. Other (if needed)

V. DESIGN/BID/BUILD CONTRACT INFORMATION

VI. ACKNOWLEDGMENT AND ATTESTATION

APPENDICES

Appendix A: Prequalification Submittal/Evaluation Form (To be completed by Jury Panel)

Appendix B: Contractor’s Design/Bid/Build (D/B/B) Agreement (Form SC-6.21), The General Conditions of the Contractor’s Design/Bid/Build (D/B/B) Agreement (Form SC-6.23), University of Colorado Boulder Supplemental Terms and Conditions to SC-6.21 and SC-6.23

Appendix C: Not Used

Appendix D: Direct Labor Burden Calculation form (SBP-6.18)

Appendix E: Applicable Prevailing Wage Rates and Apprenticeship Contribution

Rates

Appendix F: Apprenticeship Utilization Certifications (SBP-6.17)

Appendix G: IE Program Plan, etc. Insert if desired or note NOT USED

Appendix H: OSA-AFB-1 and Bid Bond form

Rev 09/2024

REQUEST FOR PROPOSALS FOR A

DESIGN/BID/BUILD GENERAL CONTRACTOR

Settlement Notice For all projects with a total dollar value above $150,000 Notice of Final Settlement is required by C.R.S.

§38-26-107(1). Final Settlement, if required, will be advertised in the same location as the original solicitation.

I. GENERAL INFORMATION

A. INTRODUCTION/DESCRIPTION OF PROJECT

The base scope for the project at the SPSC building will include converting the existing men’s and women’s Restrooms with showers RRNW-140,140A and RRNM142,142A into a gender-neutral restroom with four toilets and three single occupant shower rooms. Lockers will be provided outside of the shower rooms. Existing restroom cores RRMN121, RRWN125 on the 1st floor and RRMN231A, RRWN231B on the 2nd floor will be the add alternates with the 2nd floor cores being add alternate #1. These existing restroom cores will only receive new fixtures and finishes and remain as separate men’s and women’s restrooms.

The Regents of the University of Colorado Boulder anticipates using a Design/Bid/Build General Contractor (DBB/GC) approach to project delivery, and requests submittals for pre-qualification of General Contractors for Construction Project titled UCB000998 – SPSC – Restroom Renovations. It is the intent of the Department of Facilities Management to pre-qualify General Contractors and select a minimum of THREE (3) to bid this project in accordance with Colorado Revised Statutes 24-92-107, 24-103-402, and 24-30-1303 (1) (Q) and in accordance with Section 3-402.01 of the Colorado Procurement Rules. Pre-qualification and inclusion on the selected bidders list will be necessary for bidding on this project. This pre-qualification process is unique to this project and not withstanding other pre-qualifications by the State Buildings Division and the University of Colorado, all contractors wishing to bid this project must be pre-qualified as defined in this document.

The process to be used in the selection of the General Contractor is comprised of two (2) steps. STEP I is the Submittal of Prequalification as described in Section II. STEP II is submission of the bid as described in detail in Section III. A Jury Panel of individuals who will be involved in the project and/or understand the required services associated with Design/Bid/Build General Contractor will evaluate responses to this RFP for STEP I. Sealed bids will be accepted only from those firms who are selected as pre-qualified by the University of Colorado Boulder for this project.

B. MINIMUM QUALIFICATIONS

Notice is hereby given to all interested parties that all firms will be required to meet ALL the minimum qualifications to be considered for these projects. To be considered as qualified, interested firms shall have, as a minimum:

1. Continuously maintained a Colorado office for the last five (5) years.

Rev 09/2024

2. Successful completion within the last five (5) years, in the capacity of General Contractor, of at least three (3) projects similar to the project description in Section I-A for public or quasi-public entities; and

3. The adjusted completed Construction Contract amount for these projects shall amount to at least $500,000 per project and at least one (1) of which shall have been completed by the Project Manager and Superintendent proposed for this project. Enclose resumes of these and other key personnel who will be on this project through completion.

Demonstrate that the Project Manager and/or Superintendent has experience with similar projects, close owner/operation coordination, and quality management experience.

4. Certified bonding capacity of $1,000,000 each per labor and materials payment bond and performance bond. Capability of insurance as described in the attachment in Appendix B.

5. Per C.R.S. §24-92-Part 2, a public construction project in the amount of five hundred thousand dollars ($500,000.00) or more shall be subject to the State prevailing wage rate, of the regular, holiday, and overtime wages paid and the general prevailing payments on behalf of employees to lawful welfare, pension, vacation, apprentice training, and educational funds in the State, for each employee needed to execute the contract.

Payments to the funds must constitute an ordinary business expense deduction for federal income tax purposes by contractors and subcontractors. Contractors are required to pay their employees at weekly intervals and shall comply with the enforcement provisions of C.R.S. §24-92-209. Contractors awarded a project of this size will be required to utilize the LCPTracker cloud-based labor compliance and certified payroll application.

It is the intent of the University of Colorado Boulder that after reviewing and scoring of the pre-qualification submittals for this project, the top pre-qualified firms will be invited to bid the project conventionally with the intent of awarding to the lowest responsible bidder.

C. SCOPE OF SERVICES

The scope of services will be as required by the Contractor’s Design/Bid/Build Agreement (Form SC-6.21) and the Construction Documents prepared by Architectural Workshop, LLC.

A public construction project in the amount of five hundred thousand dollars ($500,000.00) or more shall be subject to the State prevailing wage rate, of the regular, holiday, and overtime wages paid and the general prevailing payments on behalf of employees to lawful welfare, pension, vacation, apprentice training, and educational funds in the State, for each employee needed to execute the contract. Payments to the funds must constitute an ordinary business expense deduction for federal income tax purposes by contractors and subcontractors.

Contractors are required to pay their employees at weekly intervals and shall comply with the enforcement provisions of C.R.S. §24-92-209. Contractors awarded a project of this size will be required to utilize LCP Tracker cloud-based labor compliance and certified payroll application.

Rev 09/2024

Per C.R.S. §24-92-117, a public construction project in the amount of five hundred thousand dollars or more shall be subject to the Buy Clean Colorado (BCCO) Act program requirements. The BCCO Act requires the Office of the State Architect to establish a maximum acceptable global warming potential (GWP) limit for each category of eligible materials, which include asphalt and asphalt mixtures, cement and concrete mixtures, glass, post-tension steel, reinforcing steel, structural steel, and wood structural elements. For any solicitation for a contract for the design of an eligible project, a State Agency or institution shall require the designer who is awarded the contract to include, in project specifications when final construction documents are released, a current Environmental Product Declaration (EPD) that meets the maximum acceptable GWP limits for each eligible material specified for the project. A contractor that is awarded a contract for an eligible project shall not install any eligible materials on the project until the contractor submits an EPD for each eligible material procured for the project.

II. PREQUALIFICATION SUBMITTALS (STEP I)

A. SCHEDULE

1. The schedule of events for the RFP process and an outline of the schedule for the balance of the project are as follows:

2. All submittals are to be submitted electronically via BIDNET at:

https://www.bidnetdirect.com/colorado/universityofcoloradodesignandconstruction

Pre-Qualification (Step I) RFP Advertisement and Document Release 4/4/2025 Mandatory Pre-submittal Conference 4/11/2025 @ 9:00 AM via Zoom Deadline to submit Questions via BIDNET 4/16/2025 @ 3:00 PM Deadline for Answers/Clarifications/Revisions via BIDNET 4/18/2025 RFP Submittals Due via BIDNET 4/21/2025 @ 2:00 PM Selected Short List Available via BIDNET 4/25/2025

Bidding (Step II) Bidding Documents Available via BIDNET

4/28/2025

Optional Pre-bid Meeting (At PM discretion) 4/29/2025 at 10:00 AM

@ SPSC

Deadline to submit Questions via BIDNET 5/5/2025 Deadline for Answers/Clarifications/Revs via BIDNET 5/8/2025 Sealed Bids Due via BIDNET Public Bid Opening

5/13/2025 @ 2:00 PM

5/13/2025 @ 2:05 PM

Construction (Projected Dates) Notice to Proceed 6/13/2025 Substantial Completion 6/1/2026 Final Completion 7/1/2026

Rev 09/2024

3. The above schedule is tentative. Responding firms shall be notified of revisions in a timely manner by email. Respondents may elect to verify times and dates by email, but no earlier than 36 hours before the schedule date and time.

B. MANDATORY PRE-SUBMITTAL CONFERENCE

To ensure sufficient information is available to teams preparing submittals, a mandatory pre-submittal conference has been scheduled. The intent of this conference is to tour the site and to have University of Colorado Boulder staff available to discuss the project. Firms preparing submittals must attend and sign-in in order to have their submittals accepted. The mandatory pre-submittal conference will be held at:

Location or Remote Link: https://cuboulder.zoom.us/j/92993313946

Date/Time: April 11, 2025 @ 9:00 AM via ZOOM meeting

C. CLARIFICATIONS

1. Owner initiated changes to this RFP will be issued under numerically sequenced BIDNET addenda. Addenda generally consist of the following items:

a. Clarifications

b. Scope Changes

c. Time and/or Date Changes

2. Respondent initiated requests for clarification will be received via BIDNET per the schedule above. All State responses will be issued by BIDNET addenda per the schedule above.

3. Respondents must acknowledge all issued addenda in their submittal and proposal.

D. GENERAL INFORMATION

1. All respondents accept the conditions of this RFP, including, but not limited to the following:

a. All submittals shall become the property of the State of Colorado and will not be returned.

b. Late submittals shall not be evaluated.

c. Any restriction as to the use of submitted materials must be clearly indicated as proprietary. The requested limitation or prohibition of use or release shall be identified in writing on a cover sheet. Blanket claims of proprietary submittals will not be honored. Fee proposals will be considered proprietary.

d. The State reserves the right to reject any or all proposals on the basis of being unresponsive to this RFP or for failure to disclose requested information.

e. The State shall not be liable for any costs incurred by respondents in the preparation of submittals and proposals nor in costs related to any element of the selection and contract negotiation process.

https://cuboulder.zoom.us/j/92993313946

Rev 09/2024

f. The respondent has reviewed Appendix B and by responding has agreed that the terms and conditions of the sample Design/Bid/Build Agreements are expressly workable without reservation. All documents can be found at:

https://osa.colorado.gov/state-buildings/project-management-policies-guidelines/contract-forms

E. PREQUALIFICATION SUBMITTALS

1. Respondent must comply with the following items, a through f. The State retains the right to waive any minor irregularity, or requirement should it be judged to be in the best interest of the State. (Note that the primary focus of the Prequalification evaluation will be firm capabilities).

a. Submit one (1) electronic (pdf format) of all material via BIDNET.

b. Submittals shall be formatted and bookmarked in the exact form and numeric sequence of the Evaluation Form (1 through 5) in Appendix A. A two-sided single page cover letter addressed to the University of Colorado Boulder, Attn: Michael Gilbert outlining the firm qualifications is required at the front of the submittal.

c. Submittals shall be evaluated in accordance with criteria as indicated in Section IV.-

A. Prequalification Submittal Criteria and ranked on the corresponding Evaluation Form in Appendix A.

d. Response to all items shall be complete.

e. All references shall be current and relevant.

f. Complete and execute the appropriate Acknowledgment and Attestation Form as provided in Section VI and submit at the back of the submittal.

F. SUBMITTAL REQUIREMENTS

Listed below are the submittal items required for consideration to be pre-qualified to bid on the project. Most specific submittal requirements will be scored. Failure to provide any of the requested information will affect the score the firm’s submittal receives, and in the cases where the minimums are required or in cases where a submittal item is required, failure to submit the required information may disqualify the submittal from further consideration.

General criteria used to judge each submittal item are described in the following Section IV- Evaluation Criteria. Firms are requested to respond directly to each item separately.

1. General Introduction

Provide a simple concise description of the firm. Description shall not be more than two

(2) typewritten pages. It may be supplemented by brochures. Description shall identify at a minimum:

a. Legal business name, address, contact person name, phone number. (If a branch office or subsidiary, provide the same information for head office as well as branch or subsidiary.)

b. Number of years in business https://osa.colorado.gov/state-buildings/project-management-policies-guidelines/contract-forms

Rev 09/2024

c. Brief overview of staff

2. Location

Provide a description of your office during the last five (5) years including all business addresses used in Colorado during the last five (5) years.

3. General Firm Experience

a. Provide a brief description of at least three (3) projects with construction costs of at least $500,000.00 successfully completed within the last five (5) years with firm in the capacity of General Contractor. Exemplary projects provided should be similar to this project as described above.

b. Project descriptions shall include:

• Gross square footage (GSF) / Brief project description

• Approximate construction cost

• Project owner’s name, address, and current phone number

• Project Architect’s or Engineer’s name and address and current phone number

• Approximate start and substantial completion dates

• Construction project manager and superintendent

c. Other related experience of the firm applicable to this RFP, for example: additional projects, team experience, etc.

4. Successful Project Completion

a. Indicate the number and dollar amounts of all delay claims, court, or arbitration judgements for and against your firm in the last five (5) years.

b. For all projects completed within the last five (5) years, where applicable, identify separately:

• Dollar amount of liquidated damages paid, and project involved.

• Dollar amount of bonus received for early completion and project involved.

• The Contractor-requested change orders as percentage of the final contract cost but not including changes to scope or schedule directed by the Owner.

5. Bonding Capacity and Insurance

Submit evidence from, or attested by, your bonding company that verifies your firm will have bonding capacity of $1,000,000.00 if this project is added to your current and anticipated workload. Bonding will be required of the bid amount and if awarded the contract, 100% Performance and 100% Labor and Material Payment Bonds will be required. Also verify that your company can meet the insurance requirements shown in the attachment in Appendix B.

6. Qualifications of Key Personnel

Provide information on the key personnel below proposed and intended for this project. If more than one person is proposed for each role, provide information on each.

Rev 09/2024

• Project Manager o Resume o Experience: List of projects of similar size, type and systems o References: with current phone numbers, outside your company to verify experience o Will this person be available uninterrupted through project completion?

• Project Superintendent o Resume o Experience: List of projects of similar size, type and systems o References: with current phone numbers, outside your company to verify experience o Will this person be available uninterrupted through project completion?

7. Schedule Control

a. Describe firm’s schedule management system.

b. Provide sample(s) schedule from previous similar project(s)

8. Current Workload and Capacity to Complete this Project

a. List current projects, dollar volume by project, and anticipated completion dates of current projects.

b. For projects within five (5) years, indicate the following for the largest amount at any one time:

• Total number of projects

• Total dollar amount of all projects

c. Estimate firm’s anticipated largest dollar volume if this project is added to current and anticipated volume. Estimate this project for this item at $1,000,000.00.

9. Projected Construction Period

a. See projected construction schedule in Section II.A.

b. Indicate firm’s ability to meet the above noted schedule and completion deadlines.

10. Project Management

Describe firm’s proposed project management system for this project.

Include the following:

• General organization

• Staffing roles

• Commitment of key personnel and resources including a description of trades provided internally to your organization

• Responsibilities

• Plan for management and control of subcontractors

• Reporting systems to Owner and Architect/Engineer

Rev 09/2024 o General communications o Actual progress o Problems resolution o Costs

• Quality control/assurance

• Project closeout

11. Performance Following Pre-qualification

Provide a separate list of three (3) Design/Bid/Build projects similar to this project for which firm has been selected during a pre-qualification process.

12. Percentage of Local Subcontractor Involvement

a. Provide an estimate percentage of local subcontractor involvement that you anticipate can be accomplished and certified as part of the bid. Local involvement shall be defined as any subcontractors within a seventy-five (75) mile radius of the building site. If pre-qualified, contractors will be required to equal or exceed the percentage proposed.

b. Provide a list of potential major-trade subcontractors, including MEP, structural, civil/earthwork, exterior envelope, and landscaping, that the General Contractor has previously used to complete similar projects.

13. Apprenticeship Training Program (if applicable)

Where an Apprentice Training Program certified by the Office of Apprenticeship located in the Employment and Training Administration in the United States Department of Labor exists in the State, or a comparable program for the training of apprentices is available in the State:

a. Firm shall demonstrate access to the certified program or a comparable alternative (Note that it is the responsibility of the submitter to demonstrate the comparability of a non-certified program) and,

b. Subcontractors at any tier with a contract value of two hundred fifty thousand dollars ($250,000) or more shall demonstrate access to the certified program or a comparable alternative.

Complete and sign the applicable version of form and insert at back of submittal.

G. NOTES FOR SUBCONTRACTOR QUALIFICATIONS

1. Subcontractor Listing

a. General Contractor Qualification Submissions must include a list of potential major-trade subcontractors, and that the General Contractor has worked with to complete previous, similar projects.

Rev 09/2024

b. Bid Proposals will be required to include a list of the subcontractors proposed for the project. Submitted bids without this list may be considered non-responsive.

2. The Contract Documents will require that the successful bidder submit the qualifications of subcontractors as listed for General Contractors in Section II.F.1.abc above, within seventy-two (72) hours of the opening of bids for approval by the Architect/Engineer and the Department of Facilities Management, University of Colorado Boulder.

3. Subcontractors will be required to meet the same minimum project experience requirements as listed for General Contractors in Sections I.A & I.B above; and must also meet certain requirements for their designated work as called for in the Contract Documents.

H. SHORT LIST

From the submittals received, a short list of qualified respondents shall be identified using the scoring indicated on the enclosed Evaluation Form Appendix A. Firms failing to meet the minimum required qualifications will not receive further consideration.

III. BIDDING (STEP II)

Bidding documents will be made available via BIDNET only to the pre-qualified, shortlisted firms. The project will be bid conventionally with the intent of awarding to the lowest responsible bidder.

IV. PREQUALIFICATION EVALUATION SUBMITTAL CRITERIA

The primary focus of the Prequalification evaluation will be firm capabilities.

Listed below, corresponding to the item numbers in Section II.F (Submittal Requirements), are the general criteria to be used to judge and score the submittals for pre-qualifications.

1. General Introduction

No scoring will be done regarding this item. However, submittals which do not include the requested information will be given no further consideration.

2. Location

It is a minimum requirement to have continuously maintained a Colorado office for the last five (5) years, preference will be given to those Contractors with home offices located in Colorado.

3. General Firm Experience

It is a minimum requirement for pre-qualification that the General Contractor’s office shall have successfully complete three (3) projects of similar complexity as defined in Section IA and Appendix G. Meeting this requirement will suffice. However, scoring will occur on this item based on the number of projects in this category and based upon the extent that the projects match the minimum requirements as defined in Section II.F.3.a above.

4. Successful Project Completion

Scoring will be based upon the extent that judgements and damages paid, or bonuses received, indicate the ability to successfully complete projects. Failure to supply this information will disqualify the submittal from further consideration.

5. Bonding Capacity and Insurance

It is a minimum requirement for pre-qualification that the General Contractor provide evidence that it can bond a single project at $1,000,000.00 and have excess bonding capacity available. Also verify that the firm can meet the insurance requirements as outlined in Appendix B.

6. Qualifications of Key Personnel

Scoring will be based upon the indicated ability of the key personnel and based on experience to successfully manage and supervise the project. Failure to supply this information may disqualify the submittal from further consideration. Note that the Contract Documents issued for bid will contain a requirement to list Key Personnel to be assigned to the project for duration of the contract.

7. Schedule Control

This item has no minimum requirement. However, scoring will be based upon the indicated adequacy of the proposed system for the project. Failure to submit the requested information may disqualify the submittal from further consideration.

8. Current Workload/Capacity to Complete this Project indicated adequacy of the proposed system for the project. Failure to submit the requested information may disqualify the submittal from further consideration.

9. Projected Construction Period indicated ability to successfully meet this project’s projected schedule and completion deadlines. Liquidated damages, if applicable, are mentioned in Section I.B and/or Appendix D. Failure to submit the requested information may disqualify the submittal from further consideration.

10. Project Management

It is a minimum requirement that the General Contractor has a total quality management or an established quality control/assurance program in place. Scoring will be based upon the indicated ability of the management system to successfully complete this project at a high level of quality. Failure to submit the requested information may disqualify the submittal from further consideration.

11. Performance Following Pre-qualification

Scoring will be based on the number and type of projects your firm has been pre-qualified for and upon the extent that your firm has completed bid submittals following pre-qualification.

12. Percentage of Local Subcontractor Involvement

a. This item has no minimum requirement. However, scoring will be based upon the indicated ability to involve local subcontractors to successfully complete this project. Failure to submit the requested information may disqualify the submittal from further consideration.

b. This item will not be scored. However, failure to supply this information may disqualify the submittal from further consideration.

13. Apprenticeship Training Program (If applicable)

Where an Apprenticeship Training Program certified by the Office of Apprenticeship located in the Employment and Training Administration in the United States Department of Labor exists in the State, or a comparable program for the training of apprentices is available in the State:

c. Firm shall demonstrate access to the certified program or a comparable alternative (Note that it is the responsibility of the submitter to demonstrate the comparability of a non-certified program) and,

d. Subcontractors at any tier with a contract value of two hundred fifty thousand dollars ($250,000) or more shall demonstrate access to the certified program or a comparable alternative.

This item will not be scored. However, failure to supply this information may disqualify the submittal from further consideration.

15. Other (If needed)

This option is included for other items provided by a firm. Examples may include standard firm promotional literature, testimonials, awards, corporate memberships in professional organizations or sponsorships, additional project/contract histories, etc., intended to demonstrate why a firm is uniquely qualified for this project.

V. DESIGN/BID/BUILD CONTRACT INFORMATION

A. Carefully review the Design/Bid/Build contract samples provided in Appendix B before initiating your response submittal. Any exceptions to the contract must be communicated formally in accordance with the written questions schedule noted in Section II.A.

B. Appendix E and F of this RFP includes mandatory State apprenticeship and prevailing wage requirements based on the construction value of the project.

Rev 09/2024

C. The State reserves the right to make non-material changes to the appended model agreement, including additions and /or modifications that may be necessary to more completely describe the services defined or implied herein.

D. Any approved reimbursable expenses made under the terms of the final agreement shall be a direct pass-on cost with no adjustment to the fee described therein.

E. Any and all products, systems, methods, and procedures developed as a result of this agreement shall remain the exclusive property of the State.

VI. ACKNOWLEDGEMENT AND ATTESTATION FORM

A. Several versions of the Acknowledgment and Attestation Form follow this section. Proper completion and inclusion of the appropriate form is a mandatory requirement for consideration.

B. Qualifications made by a respondent in executing this form may render a submittal non-responsive as determined by the State.

End of RFP

ACKNOWLEDGEMENT AND ATTESTATION FORM

(Partnership Format)

Date: ______________________________

By responding to this RFP, the respondent(s) certify that he/she has reviewed the Design/Bid/Build sample contract, and its exhibits contained herein, and is familiar with their terms and conditions and finds them expressly workable without change or modification.

We certify and declare that the foregoing is true and correct.

Subscribed on _______________________________ at ____________________________ Date City

___________________________, State of _______________________________________ County State

1)___________________________________________ Partner Signature

Typed Name: _________________________

2)___________________________________________ Partner Signature

Typed Name: _________________________

Notary: ________________________________________________ ________________ Date

Commission Expires: _____________________________________

Note: Add additional signatures if there are more than two partners.

(Joint Venture Format)

Date: ______________________ sample contract, and its exhibits contained herein, and is familiar with their terms and conditions and

Subscribed on _______________________________ at _________________________, ___________________________, State of _____________________________________.

County State

1)________________________________________________ _____________________ Venture Partner Binding Signature Date

________________________ Typed Name: _____________________________ Type of Business Title: ____________________________________

Witness Date

Typed Name: _____________________________

2)______________________________________________ ______________________ Venture Partner Binding Signature Date

________________________ Typed Name: _____________________________ Type of Business Title: ____________________________________

Witness Date

Typed Name: _____________________________

Note:

1. Add additional venture partners as necessary.

2. Witnesses of venture partners shall be corporate secretary for corporations, partners for partnerships, and notaries for sole proprietorships.

3. Attach venture agreement

4. Type of business shall identify the venture partner as a corporation, venture, partnership, sole proprietorship, or other legal entity.

(Corporate Format) sample contract, and its exhibits contained herein, and is familiar with their terms and conditions and

___________________________, State of _____________________________________.

Corporate Officer Signature Date

Secretary Date

Note: Use full corporate name and attach corporate seal here.

(SEAL)

(Sole Proprietorship Format) sample contract, and its exhibits contained herein, and is familiar with their terms and conditions and

___________________________, State of _____________________________________.

Respondent Date

Typed Name: ________________________

Notary: _______________________________________________________________ Date

Commission Expires: ___________________

Appendix A

STATE BUILDINGS PROGRAM

PREQUALIFICATION SUBMITTAL/EVALUATION FORM

DESIGN/BID/BUILD GENERAL CONTRACTOR SERVICES

Name of Firm: ________________________________________________________________ __ _ Name of Project: _UCB000998 – SPSC – Restroom Renovations ___________________________ Evaluator No: _________________________________________ Date: _______________________

RFP REFERENCE

MINIMUM REQUIREMENTS Y _____ N ____

If the minimum requirements (including letter from Surety) have not been met, specify the reason(s):

Acknowledgement and Attestation included Y _____ N _____

SCORE Weight2 x Rating3 = Score

1. GENERAL INTRODUCTION Y _____ N _____

2. LOCATION

Colorado office during last five (5) years 1 x =

3. GENERAL FIRM EXPERIENCE

Project #1 3 x =

a. GSF / Functional Use d. A/E Firm

b. Construction Cost e. Schedule

c. Owner f. Team

Project #2 3 x =

a. GSF / Functional Use d. A/E Firm

Project #3 3 x =

a. GSF / Functional Use d. A/E Firm

Related experience of the firm 3 x =

4. SUCCESSFUL PROJECT COMPLETION

Delay claims, court, or arbitration judgements 1 x = Early completion 1 x = Percentage of contractor requested change orders 1 x =

5. BONDING CAPACITY AND INSURANCE

Bonding capacity 1 x = Insurance requirement 1 x =

6. QUALIFICATIONS OF KEY PERSONNEL

Qualifications and relevant experience of project manager 1 x = Qualifications and relevant experience of superintendent 1 x = Qualifications and relevant experience of other 1 x =

7. SCHEDULE CONTROL

Schedule management system 1 x = Sample schedules 1 x =

8. CURRENT WORKLOAD

Ability to add project to current workload 1 x =

9. PROJECTED CONSTRUCTION PERIOD

Ability to meet proposed schedule 1 x =

10. PROJECT MANAGEMENT

General organization / staffing / responsibilities Commitment of personnel and resources 1 x = Management plan / subcontractor control 1 x = Reporting systems 1 x = Quality control / assurance 1 x = Project closeout 1 x =

11. PERFORMANCE FOLLOWING PRE-QUALIFICATION

Number of projects pre-qualified 1 x = Number of pre-qualified projects bid 1 x =

12. PERCENTAGE OF LOCAL SUBCONTRACTOR INVOLVEMENT

Ability to involve local subcontractors 1 x = Provided list of subcontractors 1 Y N

13. APPRENTICESHIP PROGRAM (if applicable)

Demonstrate access or comparable alternative 0 x =

TOTAL SCORE: ________

NOTES:

1. Criteria: Agencies/Institutions are encouraged to include additional criteria that reflect unique characteristics of the project under each category to help determine the submitter’s overall qualifications.

2. Weights: Agency/Institutions to assign weights, using whole numbers, to all criteria on evaluation forms for inclusion into RFQ document and prior to evaluations.

3. Ratings: Evaluator to assess the strength of each firms qualifications and assign a numerical rating of 1 to 5 with 5 being the highest rating. (Use whole numbers)

4. Total Score: Includes the sum of all criteria. Note: a passing score (as a percentage of the total points available) is optional and should be assigned by the agency/institution prior to evaluation.

Appendix B

CONTRACTOR’S DESIGN/BID/BUILD AGREEMENT

(SC-6.21)

THE GENERAL CONDITIONS OF THE CONTRACTOR’S DESIGN/BID/BUILD AGREEMENT

(SC-6.23)

UNIVERSITY OF COLORADO BOULDER SUPPLEMENTAL TERMS AND CONDITIONS

TO THE SC-6.21 AND SC-6.23

Sample forms may be found at the following link:

HTTPS://OSA.COLORADO.GOV/STATE-BUILDINGS/PROJECT-MANAGEMENT-POLICIES-

GUIDELINES/CONTRACT-FORMS

Appendix D

DIRECT LABOR BURDEN

(SBP-6.18)

Appendix E

APPLICABLE PREVAILING WAGE RATES and APPRENTICESHIP CONTRIBUTION RATES

Prevailing Wage Rates and Apprenticeship Rates will be included in bid documents at a later date.

Appendix F

APPRENTICESHIP CERTIFICATION

(SBP-6.17)

Appendix G

PROGRAM PLAN ETC (Optional)

Appendix H

OSA-AFB-1 and Bid Bond

Attached herein.

OSA-AFB-1 pg. 1

REV 1/2024

UCB Rev 8/2024

ADVERTISEMENT FOR BIDS

Design/Bid/Build State of Colorado

Notice Number: 25-39

Project No & Title: UCB000998 – SPSC – Restroom Renovations Estimated Construction Cost: $610,000.00

Settlement Notice For all projects with a total dollar value above $150,000 Notice of Final Settlement is required by C.R.S. §38-26-107(1). Final Settlement, if required, will be advertised in the same location as the original solicitation.

Project Description / Scope of Services

The base scope for the project at the SPSC building will include converting the existing men’s and women’s Restrooms with showers RRNW-140,140A and RRNM142,142A into a gender-neutral restroom with four toilets and three single occupant shower rooms. Lockers will be provided outside of the shower rooms. Existing restroom cores RRMN121, RRWN125 on the 1st floor and RRMN231A, RRWN231B on the 2nd floor will be the add alternates with the 2nd floor cores being add alternate #1. These existing restroom cores will only receive new fixtures and finishes and remain as separate men’s and women’s restrooms.

Minimum Requirements

Notice is hereby given to all interested parties that all firms will be required to meet all minimum requirements to be considered for this project. Interested bidders should be prepared to show evidence of the following to be considered as qualified, as a minimum:

1. Provided General Contracting services within the last three (3) years for at least two (2) projects each in excess of $500,000.00 (hard costs), utilizing the expertise present in their Colorado Office;

and

2. Demonstrated specific General Contracting experience in projects of similar scope and complexity; and

3. Demonstrated bonding capability up to $1,000,000.00 for an individual project coincidentally with current and anticipated workloads; provide a letter from surety that affirms this capacity.

4. Per C.R.S. §24-92-115 unless prohibited by applicable federal law, contract for any public project in the amount of one million dollars or more, that does not receive federal money, in the amount of one million dollars or more shall require the general contractor to which the contract is awarded to submit, at the time the mechanical, electrical, or plumbing subcontractor is put under contract, documentation that Identifies the contractors or subcontractors that will be used for all

OSA-AFB-1 pg. 2

UCB Rev 8/2024 mechanical, sheet metal, fire suppression, sprinkler fitting, electrical, and plumbing work required on the project and certifies that all firms identified participate in apprenticeship programs registered with the United States department of labor’s employment and training administration or state apprenticeship councils recognized by the United States department of labor and have a proven record of graduating a minimum of 15% of its apprentices for at least three of the past five years.

5. Per C.R.S. §24-92-Part 2, a public construction project in the amount of five hundred thousand dollars or more shall be subject to the State prevailing wage rate, of the regular, holiday, and overtime wages paid and the general prevailing payments on behalf of employees to lawful welfare, pension, vacation, apprentice training, and educational funds in the State, for each employee needed to execute the contract. Payments to the funds must constitute an ordinary business expense deduction for federal income tax purposes by contractors and subcontractors.

Contractors are required to pay their employees at weekly intervals and shall comply with the enforcement provisions of C.R.S. §24-92-209. Contractors awarded a project of this size will be required to utilize the LCPTracker cloud-based labor compliance and certified payroll application.

6. Per C.R.S. §24-92-117, a public construction project in the amount of five hundred thousand dollars or more shall be subject to the Buy Clean Colorado (BCCO) Act program requirements.

The BCCO Act requires the Office of the State Architect to establish a maximum acceptable global warming potential (GWP) limit for each category of eligible materials, which include asphalt and asphalt mixtures, cement and concrete mixtures, glass, post-tension steel, reinforcing steel, structural steel, and wood structural elements. For any solicitation for a contract for the design of an eligible project, a State Agency or institution shall require the designer who is awarded the contract to include, in project specifications when final construction documents are released, a current Environmental Product Declaration (EPD) that meets the maximum acceptable GWP limits for each eligible material specified for the project. A contractor that is awarded a contract for an eligible project shall not install any eligible materials on the project until the contractor submits an EPD for each eligible material procured for the project.

Firms meeting the minimum requirements may obtain the bidding documents on the website accompanying this advertisement.

University of Colorado Boulder – Open Notices

Other Information

Preference shall be given to Colorado resident bidders and for Colorado labor, as provided by law.

Per C.R.S. §24-105-201 If the construction value is $50,000 or greater a Bid Bond and Power of Attorney or Proposal Guaranty is required in an amount not less than 5% of the total Bid.

State Buildings Program Note to Drafter: This language may be omitted for projects less than $1 million in construction

Note to Drafter: This language may be omitted for project less than $500,000 in construction

OSA-AFB-1 pg. 3

UCB Rev 8/2024

Schedule/Submission Details

1. The schedule of events for the AFB process and an outline of the schedule for the balance of the project is as follows:

1. The schedule of events for the RFP process and an outline of the schedule for the balance of the project are as follows:

Agency:

Contact Name: Michael Gilbert, Project Manager; michael.gilbert@colorado.edu Chris Kerr, Project Coordinator; chris.kerr@colorado.edu

Comments: Late sealed bids will be rejected without consideration. The University of

Colorado Boulder and the State of Colorado assume no responsibility for costs related to the preparation of submittals.

1. The above schedule is tentative. All submittals are to be submitted electronically via BIDNET at:

Pre-Qualification (Step I) RFP Advertisement and Document Release 4/4/2025 Mandatory Pre-submittal Conference 4/11/2025 @ 9:00 AM via Zoom Deadline to submit Questions via BIDNET 4/16/2025 @ 3:00 PM Deadline for Answers/Clarifications/Revisions via BIDNET 4/18/2025 RFP Submittals Due via BIDNET 4/21/2025 @ 2:00 PM Selected Short List Available via BIDNET 4/25/2025

Bidding (Step II) Bidding Documents Available via BIDNET

4/28/2025

Optional Pre-bid Meeting (At PM discretion) 4/29/2025 at 10:00 AM

@ SPSC

Deadline to submit Questions via BIDNET 5/5/2025 Deadline for Answers/Clarifications/Revs via BIDNET 5/8/2025 Cost Proposals Due via BIDNET Public Bid Opening

5/13/2025 @ 2:00 PM

5/13/2025 @ 2:05 PM

Construction (Projected Dates) Notice to Proceed 6/13/2025 Substantial Completion 6/1/2026 Final Completion 7/1/2026 mailto:michael.gilbert@colorado.edu mailto:chris.kerr@colorado.edu

OSA-AFB-1 pg. 4

UCB Rev 8/2024

APPENDICES:

Appendix A: Information for Bidders (SBP-6.12)

Appendix B: Bid Form (SBP-6.13)

Appendix B1: Bid Alternates (SBP-6.131) (if Applicable)

Appendix B2: Unit Pricing (SBP-6.133) (if Applicable)

Appendix B3: Bid Bond (SBP-6.14)

Appendix C: Sample: Direct Labor Burden Calculation (SBP-6.18)

Appendix D: Applicable Prevailing Wage and Apprenticeship and Fringe Rates – To be included in the bid documents later.

Appendix E: Sample: Apprenticeship Utilization Certifications (SBP-6.17)

State Buildings Program Note to drafter: Agency/IHE should confirm that each of the following templates is made project specific and either included in the Project Manual from the Architect or uploaded to the Solicitation site.

State Buildings Program Note to Drafter: Direct Labor Burden is not related to prevailing wage and is required to be completed as part of the construction contract.

Delete this text, Appendix D and/or Appendix E if not applicable

SBP-6.14

Rev. 7/2022

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

BID BOND

Institution/Agency: University of Colorado Boulder Project No./Name: UCB000998 – SPSC – Restroom Renovations

KNOW ALL MEN BY THESE PRESENTS:

WHEREAS, hereinafter called the “PRINCIPAL”, is submitting a PROPOSAL for the above described project, to the STATE OF COLORADO, hereinafter called the “OBLIGEE”.

WHEREAS, the Advertisement for Bids has required as a condition of receiving the Proposals that the Principal submit with the PROPOSAL GUARANTY in an amount not less than five per cent (5%) of the Proposal, which sum it is specifically agreed is to be forfeited as Liquidated Damages in the event that the Principal defaults in his obligation as hereinafter specified, and, in pursuance of which Requirement, this Bid is made, executed and delivered.

NOW THEREFORE, the Principal and a corporation of the State of , duly authorized to transact business in Colorado, as Surety, are held and firmly bound unto the Obligee, in the sum of five per cent (5%) of the Principal’s total bid price, lawful money of the United States for the payment of which sum, well and truly to be made to the Obligee, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.

FURTHER THAT, a condition of the obligation that the Principal shall maintain his Proposal in full force and effect for thirty (30) days after the opening of the proposals for the project, or, if the Principal’s Proposal is accepted, the Principal shall, within the prescribed time, execute the required Agreement, furnish the required Performance Bond, Labor and Material Payment Bond, Insurance Policy, Certificates of Insurance and Certification and Affidavit Regarding Illegal Aliens, then this obligation shall be null and void, otherwise it shall remain in full force and effect, and subject to forfeiture upon demand as Liquidated Damages.

IN WITNESS WHEREOF said Principal and Surety have executed this Bond, this day of , A.D., 20 .

(Corporate Seal) THE PRINCIPAL

Company Name

ATTEST

Address (including city, state and zip) Secretary Phone number:

Name (Print) Signature

Name (Print) and Title

SIGNATURES If the “Principal” is doing business as a Corporation, the Bid Bond shall be signed by an officer, i.e., President or Vice President. The signature of the officer shall be attested to by the Secretary and properly sealed.

If the “Principal” is an individual or a partnership, the Bid Bond shall so indicate and be properly signed.

(Corporate Seal) THE SURETY

By __________________________________________

Secretary Attorney-in-Fact

THIS BOND MUST BE ACCOMPANIED BY POWER OF ATTORNEY, EFFECTIVELY DATED.

FAILURE TO PROVIDE A PROPERLY EXECUTED BID BOND WITH A PROPERLY EXECUTED POWER OF ATTORNEY

WILL RESULT IN THE BIDDER’S PROPOSAL BEING DEEMED NON-RESPONSIVE.

TABLE OF CONTENTS
I. GENERAL INFORMATION
A. Introduction/Description of Project
B. Minimum Qualifications
C. Scope of Services
II. PREQUALIFICATION SUBMITTALS (STEP I)
A. Schedule
B. Mandatory Pre-submittal Conference
C. Clarifications
D. General Information
E. Prequalification Submittals
III. BIDDING (STEP II)
IV. EVALUATION CRITERIA
1. General Information
V. DESIGN/BID/BUILD CONTRACT INFORMATION
VI. ACKNOWLEDGMENT AND ATTESTATION
A. INTRODUCTION/DESCRIPTION OF PROJECT
B. MINIMUM QUALIFICATIONS
C. SCOPE OF SERVICES
A. SCHEDULE
B. MANDATORY PRE-SUBMITTAL CONFERENCE
C. CLARIFICATIONS
D. GENERAL INFORMATION
E. PREQUALIFICATION SUBMITTALS
F. SUBMITTAL REQUIREMENTS
G. NOTES FOR SUBCONTRACTOR QUALIFICATIONS
H. SHORT LIST
III. BIDDING (STEP II)
IV. PREQUALIFICATION EVALUATION SUBMITTAL CRITERIA
V. DESIGN/BID/BUILD CONTRACT INFORMATION
VI. ACKNOWLEDGEMENT AND ATTESTATION FORM
ACKNOWLEDGEMENT AND ATTESTATION FORM
Page 1 of 1
ACKNOWLEDGEMENT AND ATTESTATION FORM
Appendix A
DIRECT LABOR BURDEN (SBP-6.18)
APPLICABLE PREVAILING WAGE RATES and APPRENTICESHIP CONTRIBUTION RATES
APPRENTICESHIP CERTIFICATION
(SBP-6.17)
PROGRAM PLAN ETC (Optional)
OSA-AFB-1 and Bid Bond