Presolicitation Notice Summary

This is a presolicitation notice issued by the U.S. Army, 409th Contracting Support Brigade, for a Firm Fixed Price, single award contract to repair PX Doors in Building #8401 (AAFES PX) located in Baumholder Smith Barracks, Baumholder, Germany. The contract services encompass comprehensive building improvements including site mobilization, safety measures, demolition, door and gate replacement, locking systems, fire-resistant partitions, external metal escape staircase installation, window closure with masonry, plastering and painting, civil engineering work (paved walkways and guardrails), door hold-open device distribution systems, electrical gate systems, fire alarm system expansion, fire protection concept preparation, and shop drawings. The procurement utilizes a Two-Step Sealed Bidding method under RFO FAR Subpart 14.211.

Step One requires submission of technical proposals in English, electronic PDF format, without any pricing information. Technical proposals must demonstrate method of accomplishment and materials to be used, applying German Institute for Standardization (DIN) standards; include a progress schedule meeting a 365 calendar day delivery requirement with detailed mobilization and sequencing information; and provide certificates authorizing business operations in Germany. Proposals will be evaluated for acceptability as either Acceptable, Reasonably Susceptible of Being Made Acceptable, or Unacceptable. All bid prices must be quoted in EURO only, with the Total Evaluated Price calculated as the sum of all Contract Line Item Numbers. The closing date for technical proposals and additional details will be posted to SAM.Gov in the Solicitation Handout document approximately 15 days from the presolicitation notice. The Contracting Officer is Daniel Will (daniel.h.will.civ@army.mil) and Contract Specialist is Cara Borowski (cara.l.borowski2.civ@army.mil).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

The U.S. Army, 409th Contracting Support Brigade (409th CSB), Unit 23163, APO AE 09227, intends to award a Firm Fixed Price, single award contract for the Repair of PX Doors, Building #8401 (AAFES PX) located in Baumholder Smith Barracks, Baumholder, Germany.

This Synopsis is issued to meet the requirements in RFO FAR Subpart 5.101 Presolicitation Notice and RFO FAR Subpart 14.211 Two-Step Sealed Bidding.

Contract services include site mobilization, safety and protection measures, demolition, replacement of doors, replacement of gate, locking system, fire-resistant partitions, external metal escape staircase, closing of window openings with masonry, plastering and painting work, cleaning, civil engineering work: construction of paved walkways and guardrails, sub-distribution system for door hold-open devices and electrical gate, expansion of the fire alarm system, preparation of a fire protection concept, and shop drawings. See attached Statement of Work for more details.

This solicitation and resulting contract are utilizing a Two-Step Sealed Bidding procurement method as described in RFO FAR Subpart 14.211.

Requirements of Technical Proposal:

• Shall be set up so that no additional explanations and information is required;

• Applying German Institute for Standardization, or Deutches Institut fur Normung

(DINs);

• Regulations and Standards shall be indicated;

• Provide Sketches/Drawings, if necessary;

• Alternate proposals are welcome, each proposal will be evaluated separately;

• Proposal must be submitted in English;

• Proposal must be in electronic PDF format;

• Proposal must provide the information/documents requested below in the technical evaluation criteria in order to be found acceptable;

• Technical Proposals MUST NOT include prices;

• All bid prices be in EURO only;

• The Total Evaluated Price (TEP) will be the sum of all Contract Line Item Numbers

(CLIN)

The technical evaluation criteria are as follows:

• FACTOR 1: Offerors shall show method of accomplishment, materials to be used.

o To be found acceptable offerors shall provide the following:

Method of Accomplishment and Materials to be Used- Offerors shall submit a copy of specifications and materials they are proposing. Describe how (method) the project will be accomplished as required by the Statement of Work (attached separately hereto), but do NOT simply restate the Statement of Work. The method of accomplishment and materials proposed must meet or exceed the minimum applicable standards as set forth in the applied German Institute for Standardization, or Deutches Institut fur Normung (DINs), Regulations and Standards.

• FACTOR 2: Offerors shall provide a copy of the following schedules

Progress Schedule – A schedule shall be submitted outlining the offeror’s plan to meet the 365 calendar day delivery time for all specification requirements. The progress schedule shall include the timeframe in which the offeror intends to have deliverables completed, all materials in possession, preparation and mobilization dates. A Planned sequence for performing the various components of the work shall be submitted.

• FACTOR 3: Offerors shall provide the following documentation:

1. Certificates for doing business in Germany – The Offeror shall provide one copy of their certificates authorizing the firm to conduct business in Germany.

The submission requirements of Step One, Request for Technical Proposal, shall not include any prices or pricing information. Under the procedures of RFO FAR Subpart 14.211, Step One consists of the request for submission, evaluation and (if necessary) discussion of a technical proposal. Bidders are welcome and encouraged to submit multiple proposals (see RFO FAR 52.214-24). The proposals will be evaluated for technical acceptability. Proposals will be evaluated to be either Acceptable, Reasonably susceptible of being made acceptable, or Unacceptable.

The closing date and time for Technical Proposals (Step One) can be found on the Solicitation Handout document. The Solicitation Handout document will be posted to SAM.Gov in approximately 15 days.

In the second step, the contracting officer will consider awards based upon bids that have acceptable technical proposals, either initially or as a result of discussions. Each technical proposal must be based on the bidder's own technical proposals.

Bidders should submit technical proposals that are acceptable without additional explanation or information. The Government may make a final determination regarding a technical proposal's acceptability solely on the basis as submitted. The Government may proceed with the second step without requesting further information from any bidder;

however, the Government may request additional information from bidders of bids that it considers reasonably susceptible of being made acceptable and may discuss bids with their bidders.

If the Government finds a technical proposal unacceptable during evaluations, a notice of unacceptability will be forwarded to the offeror upon completion of the technical evaluation.

Information on delivery and specific performance requirements will be included in the Step One Solicitation Handout which will be posted to SAM.Gov. The delivery and performance information included in the Step One Solicitation handout is not binding on the Government. The invitation issued under Step Two will include actual delivery or performance requirements.

The Points of Contact for this action are Contracting Officer, Daniel Will, daniel.h.will.civ@army.mil and Contract Specialist, Cara Borowski, cara.l.borowski2.civ@army.mil mailto:daniel.h.will.civ@army.mil mailto:cara.l.borowski2.civ@army.mil