Text version

Date: RFI No.

RFP Reference (Sect/Para/Page) QUESTION GOVERNMENT RESPONSE

3/15/2018 1 Was the site visit mandatory in order to bid this?

Thanks for any information.

The site visit is not mandatory in order to submit a bid.

However, it can provide a great way to view site conditions prior to bidding as all bidders will be held to the same standard of work as listed in the solicitation whether they come to the site visit or not.

Pre-Bid RFI Log for W912L6-18-B-6003 Engine Shop Lighting