This is a Statement of Work for the National Park Service Regional IR2 for the cyclic replacement of a security fence and entrance gate at the Tuskegee Institute National Historic Site (TUIN) in Tuskegee, Alabama.
The contractor shall remove the existing vandalized chain-link fence and gate surrounding the TUIN Maintenance Shop and Curatorial Storage facility and install a new security rod iron fence approximately 1,300 feet in length, 8 feet high with security spikes curved away to prevent intrusion. The project includes an 18-foot sliding gate with power opener (push code option), three touch remotes, a side manual gate for pedestrian access with lock, and 4x4 post caps. Materials specified include 8-foot x 8-foot rod iron fence panels (14-gauge metal) and 4x4x10 posts (12-gauge). The contractor must remove and dispose of existing materials offsite, prepare the site by removing vegetation and debris, clean up upon completion, repair any damage to match existing conditions, and seed bare soil with native grass to prevent erosion. Commercial-grade fencing is required, with material substitutions permitted if specified gauging is unavailable upon government approval.
The contractor is responsible for providing all labor, equipment, materials, insurance, and permits. Work must be performed during normal business hours of 8:00 AM to 4:00 PM, Monday through Friday, excluding Federal Holidays, with specific on-site schedules coordinated with the Contracting Officer Representative (COR) five days prior to start. Work completion is required within 90 days from notice to proceed. The contractor must comply with OSHA, local, state, and federal environmental regulations, maintain public safety through barricading and safety equipment, minimize disruptions to park visitors, and develop quality control procedures aligned with commonly accepted commercial practices. Close coordination with NPS staff and the park Facility Manager is essential, with the Facility Manager holding final authority on facility closures.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| TUIN_Fence_Project_Q_A_0001.pdf | ||
| Updated_TUIN_Replace_Security_Fence_SOW_2026_0001.pdf | ||
| Sol_140P5126Q0037_Amd_0001.pdf | ||
| Alabama_Wage_Determinations_0001.pdf | ||
| Sol_140P5126Q0037.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NATIONAL PARK SERVICE
REGIONAL IR2
Region IR2
Tuskegee Institute (TUIN) / Tuskegee Airmen (TUAI) National Historic Site
Project Name:
Cyclic Replacement of Maintenance Shop and Curatorial Storage Security Gate at TUIN
PMIS No.: 349585
PEPC No.: 130541
Tuskegee Institute (TUIN) /Tuskegee Airmen National
Historic Site (TUAI)
Tuskegee, AL 36088
Statement of Work
TABLE OF CONTENTS
1. Introduction
2. Background
3. Scope of Work
4. Contractor Responsibilities
5. Business Hours
6. Safety and Environmental Compliance
7. Public Convenience and Safety
8. Definitions and Terms
9. Park Hours
10. Other Unique Requirements
11. Quality Assurance Requirement
12. Pictures and Map
1. Introduction
Tuskegee Institute National Historic Site is located at 1600 Boy Scout Circle, Tuskegee, Al.
36088 and is managed by the National Park Service and is the only national park located on a fully functioning college campus, Tuskegee University. The park is responsible for both the
George Washington Carver Museum and "The Oaks," home of Booker T. Washington.
The Tuskegee Institute National Historic Site in Tuskegee, Alabama, commemorates the contributions of African American men George Washington Carver and Booker T Washington to many inventions and discoveries to help the Medical and Technological advances we have today, the GWC Museum and BTW “The OAKS” Home is now operated by the National Park
Service to interpret their history and achievements.
The TUIN park’s mission is to protect, preserve, and interpret the natural, cultural, and historical resources in its care for the benefit and inspiration for present and future generations.
2. Background
The existing chain link fence and entrance gate surrounding the TUIN/ TUAI
Maintenance Shop and Curatorial Storage area have been vandalized over the years and must be replaced with a stronger security alternative. It is the Park's intention to have a new security iron fence and security entrance gate installed to properly secure the building assets.
3. Scope of Work
Project Description
Contractor shall provide all labor, equipment, and materials required to install a new fence and entrance gate to better secure the TUIN Maintenance Shop and Curatorial Storage and add openers to the entrance and exit gates. This project shall include the removal and proper disposal of existing fence and gate offsite. The following list are the necessary requirements needed:
• Remove the existing chain-link fence and remove the off site for disposal. Prep the area for the new fence removing vegetation and debris from the site.
• The fence to be installed shall be made of rod iron and measure approximately 1300 feet in length. The height should measure 8 feet in height with security spikes curved away from the fence to prevent intrusion. The entrance gate shall be an 18 feet long sliding gate made with the same rod iron material as the fence gate. Commercial grade fencing is required. Materials can be substituted if specified gauging is not available upon government approval.
• Fence Panel 8ft x 8ft rod iron fence14ga metal
• 4x4x10 12ga post
• 18 ft sliding gate with power opener (Option Push Code).
• (3) Touch Remotes for Power Gate
• Side Manual Gate for Walking Travel with Lock
• 4x4 post caps
• Once work is complete, the contractor shall clean up the project area and repair any damage incurred, returning the project area to its original condition. If bare soil is exposed the area will be seeded with native grass to prevent erosion.
4. Contractor Responsibilities
a. Contractors will provide necessary labor, equipment, materials, insurance, permits, etc., to perform work.
b. Contractors shall remove existing chain link fence, gate, and associated hardware and properly dispose of materials offsite.
c. The contractor shall seek to minimize disruptions to the public and staff by coordinating with COR.
d. Contractor shall restore all surfaces disturbed by construction to match with existing finish.
e. Any deviation from the original contract/scope of work shall be informed to
COR before work begins. No additional work or changes will be carried out without a contract modification.
f. The contractor shall confirm all measurements and specifications for accurate estimates prior to start of work.
g. The Contractor shall manage the total work effort in accordance with effective and efficient management principles and safe working practices to ensure on-time completion of the contract.
5. Business Hours
The contractor shall complete on-site work during normal business hours of 8:00am to
4:00pm, Monday through Friday, excluding Federal Holidays. The Contractor shall coordinate specific on-site work schedule with the contracting officer and contracting officer representative (COR) five days prior to performance start date. Work shall be completed within 90 days after contracting the officer issue notice to proceed. Any work outside of normal business hours shall be pre-approved by the contracting officer and COR.
6. Safety & Environmental Compliance
• The contractor shall comply with pertinent provisions of the Occupational Safety and Health Act (OSHA), state, and local safety laws and regulations.
• The contractor shall comply with pertinent local, state, and federal environmental guidelines, policies, and regulations. The Park safety officer has the authority to issue restraint or cease-and-desist orders to the contractor when violations or unsafe acts are present and threaten the Government and contractor employees or damage to Government property.
• The contractor shall be responsible for the safety of his employees and equipment, and for any injury or damage done to or by them from any source or cause. He shall save and hold the United States free from all claims for damages to all persons and (or) property arising from the execution of the work covered by these specifications.
• The contractor shall immediately report to the COR all accidents resulting in employee injury or death or damage to property while performing this contract.
• Contractor agrees to accept the sole responsibility for always complying with local, County, State or other legal requirements including but not limited to full compliance with the terms of the applicable O.S.H.A. Safety Orders, to protect all persons, including employees from foreseeable injury, or damage to property.
• It shall be the Contractor's responsibility to inspect and identify any conditions that render any portion of the maintenance area unsafe, as well as any unsafe practices occurring thereon. The NPS COR shall be notified immediately of any unsafe conditions.
7. Public Convenience and Safety
Contractor acknowledges and agrees that public safety is of utmost importance, and
Contractor agrees that during the progress of the Work, Contractor shall constantly protect and preserve the safety of the public. Contractor shall not unnecessarily cause inconvenience to the public during the progress of the Work and shall minimize the inconvenience caused by Contractor's operations. Such operations include, but are not limited to, work performed on or adjacent to the Work site, traffic lane and pedestrian closures and deliveries of material and equipment.
8. Definitions and terms
• CO - Contracting Officer
• COR-Contracting Officer's Representative
• NPS - National Park Service
• OSHA - Occupational Safety and Health Administration
• TUIN- Tuskegee Institute Site
• TUAI- Tuskegee Airmen Site
• SERO- Southeast Regional Office
9. Park hours
Normal working hours are from 8:00 AM until 4:00 PM. The Contractor can plan to work on site from 8:00 AM to 4:00 PM. Contractor cannot work outside of these hours without prior approval from the TUIN Facility Manager
10. Other Unique Requirements
Close coordination with the National Park Service staff and COR is essential to maintaining the park for visitors’ enjoyment during work to the greatest extent possible. Visitor safety is of paramount concern. Barricades, cones, etc. and all safety equipment must be in place prior to the start of work and during all work on site. The Facility Manager is the final authority on the closure of the park facility.
11. Quality Assurance Requirement
The contractor shall develop and maintain a quality program to ensure services are performed in accordance with commonly accepted commercial practices. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. As a minimum, the contractor shall develop quality control procedures addressing the critical areas identified in this statement of work. The government will periodically evaluate the contractor's performance in accordance with the statement of work.
12. Pictures and Map (Below)
| Project Name: |
| PMIS No.: 349585 |
| Statement of Work |
| TABLE OF CONTENTS |
| 1. Introduction |
| 2. Background |
| 3. Scope of Work |
| 4. Contractor Responsibilities |
| 5. Business Hours |
| 6. Safety and Environmental Compliance |
| 7. Public Convenience and Safety |
| 8. Definitions and Terms |
| 7. Public Convenience and Safety |
| 8. Definitions and terms |
File details come from the government source that posted it. Updated .