TSpecs_W912P522Q0006_JPP Station Battery System_RTA_19JUL2022.pdf

PDF 3 MB Posted

Attached to
JPP Power Plant Battery
Solicitation number
W912P522Q0006
Issued by

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CUI

ATTENTION

ATTENTION

All individuals handling this information are required to protect it from unauthorized disclosure.

Handling, storage, reproduction, and disposition of the attached document(s) must be in accordance with 32 CFR Part 2002 and applicable agency policy.

Access to and dissemination of Controlled Unclassified Information shall be allowed as necessary and permissible to any individual(s), organization(s), or grouping(s) of users, provided such access or dissemination is consistent with or in furtherance of a Lawful Government Purpose and in a manner consistent with applicable law, regulations, and Government-wide policies.

Standard Form 901 (11-18) Prescribed by GSA/ISOO | 32 CFR 2002

CUI

Louis Steele

Solicitation No. W912P522Q0006

US Army Corps Of Engineers Nashville District

Station Battery System Modernization

J. Percy Priest Dam Cumberland River Basin, Stones River Nashville,Tennessee

Technical Specifications Ready to Advertise - Certified Final

July 2022

THIS PAGE INTENTIONALLY LEFT BLANK

FOR DUPLEX PRINTING

Station Battery System Modernization J. Percy Priest Dam W912P522Q0006 Ready to Advertise Nashville, TN

PROJECT TABLE OF CONTENTS

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 00 00 GENERAL REQUIREMENTS

01 11 10 SUMMARY OF WORK

01 20 00 PRICE AND PAYMENT PROCEDURES

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 35 50 PROJECT SITE SECURITY AND AT/OPSEC PROCEDURES

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 95 00 FORMS AND ATTACHMENTS

DI VI SI ON 26 - ELECTRI CAL

26 05 19 INSULATED WIRE AND CABLE

26 08 01 SYSTEMS TESTING AND COMMISSIONING

26 32 34 BATTERIES

26 32 36 BATTERY CHARGERS

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

PROJECT TABLE OF CONTENTS Page 2

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 GENERAL

1.2 CONTRACTOR'S STAGING AREA

1.3 DAILY CLEANUP AND DISPOSAL

1.4 PROTECTION AND RESTORATION OF EXISTING FACILITIES

1.5 EVALUATION OF CONTRACTOR PERFORMANCE

1.6 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS

CONTRACTS

1.7 PRICE AND PAYMENT

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION

3.1 AVAILABILITY AND USE OF UTILITY SERVICES

3.1.1 Contractor Responsibilities

-- End of Section Table of Contents --

SECTION 01 00 00 Page 1

SECTION 01 00 00 Page 2

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 GENERAL

This section comprises an explanation of the general contract requirements needed to accomplish the work. All work specified herein shall be accomplished in accordance with the procedures prescribed in the specifications and drawings.

1.2 CONTRACTOR'S STAGING AREA

The Contractor will be assigned an area within or near the project site for use as a staging area. The building of structures, the erection of tents or other forms of protection will be permitted only at such places as the Government shall approve, and the sanitary conditions of the grounds in or about such structures shall at all times be maintained in a satisfactory manner. Temporary Contractor facilities provided during Construction shall be removed prior to final acceptance from the Government. As a minimum the area shall be left looking "broom clean" and at least as clean as before the structure placement.

1.3 DAILY CLEANUP AND DISPOSAL

Work areas shall be kept reasonably neat on a daily basis. Debris resulting from the work, such as empty paint cans, packing cases, scrap lumber, oil and grease spills, and other debris shall be collected, removed, and disposed of off-site at least once per week. Government trash cans, dump boxes and other containers shall not be used. Liquid waste shall not be disposed of in existing drains.

1.4 PROTECTION AND RESTORATION OF EXISTING FACILITIES

Existing facilities shall be protected whether or not shown on the drawings. Upon completion of the work, existing facilities, not included as a portion of the work, shall be left in a condition equal to the original condition prior to the contract. Costs for repair and restoration of any facilities shall be considered to be incidental to and included in the contract price.

1.5 EVALUATION OF CONTRACTOR PERFORMANCE

The Contractor's performance may be evaluated in accordance with FAR Part

42.15 in the areas of quality, schedule, cost control, management, utilization of small businesses, and regulatory compliance at minimum.

The evaluation will include a written narrative and rating of either exceptional, very good, satisfactory, marginal, or unsatisfactory for each. The format for the evaluation is attached at the end of Section

01 95 00 FORMS AND ATTACHMENTS.

The Contractor's review of the evaluation shall be completed electronically at the CPARS, http://www.cpars.gov . This website also includes guidance and the user's manual.

SECTION 01 00 00 Page 3

Upon contract award, the Contractor shall provide the Contracting Officer with the name and e-mail address of the Contractor's Representative to be registered into the system. Following initial completion by the Government, the Contractor will have sixty (60) calendar days to review, comment, and return the evaluation.

1.6 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS

In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS

222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:

Federal Veteran employment information at:

http://www.fedshirevets.gov/index.aspx

Department of Labor Veterans Employment Assistance:

http://www.dol.gov/vets/

Department of Veterans Affairs-VOW to Hire Heroes Act:

http://benefits.va.gov/vow/

Army Wounded Warrior Program:

http://wtc.army.mil/modules/employers/index.html

U.S. Chamber of Commerce Foundation-Hiring Our Heroes http://www.hiringourheroes.org/

Guide to Hiring Veterans - Reference Material:

http://www.whitehouse.gov/sites/default/files/docs/ white_house_business_council_-_guide_to_hiring_veterans_0.pdf

1.7 PRICE AND PAYMENT

No separate payment will be made for the work covered under this section.

The costs thereof shall be included in the item to which the work pertains.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION

3.1 AVAILABILITY AND USE OF UTILITY SERVICES

3.1.1 Contractor Responsibilities

a. The Contractor shall be responsible for the availability of utilities for use on the project. Raw water is available with no charge at the site. The contractor shall supply any other utilities needed at his cost. The Contractor shall carefully conserve any utilities furnished without charge.

b. The Contractor, at its expense and in a workmanlike manner

SECTION 01 00 00 Page 4 satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, and associated paraphernalia.

c. The Contractor is responsible for providing drinking water and restroom facilities for all personnel associated with this contract.

-- End of Section --

SECTION 01 00 00 Page 5

SECTION 01 00 00 Page 6

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 10

SUMMARY OF WORK

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

1.1.1 Battery System Outage Requirements

1.1.2 Outage Coordination Meeting

1.1.3 Safety Preparatory Inspecttion Coordination Meeting With the

Government

1.2 POWER HOUSE CRANE

1.3 CONTRACTOR'S WORKING HOURS

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

SECTION 01 11 10 Page 1

SECTION 01 11 10 Page 2

SECTION 01 11 10

SUMMARY OF WORK

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

The scope of work for this contract consists of the Contractor furnishing all supervision, engineering, labor, materials, and equipment to perform the following required work in strict accordance with the detailed requirements of this contract:

a. Remove the existing and provide a new 125VDC Station Battery and Battery Rack with Electrolyte Spill Containment.

b. Furnish and Install a Battery Monitoring System.

c. Remove the existing and provide new 125VDC Battery Chargers.

d. Provide proper disposal of decommissioned equipment and materials with certificates of disposal as required.

e. Test existing wiring and replace if test results are unacceptabale.

f. Install additonal wiring if the length of the existng wiring is not adequate for installation into the new equipment.

g. Provide commissioning for the new battery and charging systems.

h. Provide training for the new battery and charging systems.

i. Provide commissioning and training for the Battery Monitoring System.

1.1.1 Battery System Outage Requirements

The work site is under the government's Hazardous Energy Control Program (HECP) also commonly known as Lock Out/Tag Out (LOTO). De-energization and isolation of systems will be performed by qualified government personnel. Contractor personnel will also fall under the government's HECP and may also utilize their own HECP as approved.

Contact the Plant Representative at least 45 days in advance of planned work to request system outages. In accordance with EM 385-1-1, Section 12.A.01, where outages involve Government personnel or equipment, coordinate with the Government on all activities involving the control of hazardous energy. These activities include, but are not limited to, a review of Hazardous Energy Control Program (HECP) as well as applicable Activity Hazard Analyses (AHAs). In accordance with EM 385-1-1, Section 11.A.02 and NFPA 70E, work on energized electrical circuits must not be performed without prior Government authorization.

1.1.2 Outage Coordination Meeting

After the system outage request is approved and prior to beginning work on the system requiring shutdown, conduct a pre-outage coordination meeting in accordance with EM 385-1-1, Section 12.A. This meeting must include the

SECTION 01 11 10 Page 3

Prime Contractor, Plant Representative, and the Installation representative. All parties must fully coordinate HECP activities with one another. During the coordination meeting, all parties must discuss and coordinate on the scope of work, HEC procedures (specifically, the lock-out/tag-out procedures for worker and equipment protection), the AHA, assurance of trade personnel qualifications, identification of competent persons, and compliance with HECP training in accordance with EM 385-1-1, Section 12.C. Clarify when personal protective equipment is required during switching operations, inspection, and verification.

1.1.3 Safety Preparatory Inspecttion Coordination Meeting With the Government

For electrical distribution equipment that is to be operated by Government or contract personnel, the Prime Contractor, and the subcontractor performing the work must attend the safety preparatory inspection coordination meeting, which will also be attended by the Plant Representative, as required by EM 385-1-1, Section 12.A.02. The meeting will occur immediately preceding the start of work and following the completion of the outage coordination meeting. Both the safety preparatory inspection coordination meeting and the outage coordination meeting must occur prior to conducting the outage and commencing with lockout/tagout procedures.

1.2 POWER HOUSE CRANE

The Government will operate the power house crane to assist the Contractor in moving equipment, materials, and tools between the floor levels as needed. The Government will assist with rigging. The contractor will not be allowed to operate the crane. Items being lifted shall contain factory tested and approved lift points, defined centers of gravity, and necessary lift weights. Crane use shall be coordinated with the Government at least 5 working days in advance of need. The Contractor shall ensure efficient use of the crane and adjust work sequence as needed should the crane be temporarily unavailable. The Contractor will be responsible for preparing lift plans, activity hazard analysis documents, and any other safety related items necessary for execution of lifts.

1.3 CONTRACTOR'S WORKING HOURS

J Percy Priest Project maintenance personnel must be on site at all times during the Contractor's work. Project personnel currently work Monday through Thursday, 10 hour day shifts 6:00 A.M. to 4:30 P.M. The Contractor's working hours shall be the same as the project staff. No work will be allowed on Federal holidays that are observed during the 4-day work week. Proposed changes to Contractor working hours which extend past 4:30 P.M. weekdays, on Fridays, on weekends, and Federal holidays or which are different from Government working hours shall be coordinated and approved by the Contracting Officer 30 calendar days in advance.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

SECTION 01 11 10 Page 4

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.1 PAYMENT ITEMS

1.1.1 Remove Existing Station Battery and Battery Rack

1.1.1.1 Payment

1.1.1.2 Unit of Measure

1.1.2 Furnish and Install New Station Battery and Battery Rack with

Electrolyte Spill Containment

1.1.2.1 Payment

1.1.2.2 Unit of Measure

1.1.3 Furnish and Install New Battery Monitoring System

1.1.3.1 Payment

1.1.3.1.1 Unit of Measure

1.1.4 Remove the Existing Battery Chargers

1.1.4.1 Payment

1.1.4.2 Unit of Measure

1.1.5 Furnish and Install New Battery Chargers

1.1.5.1 Payment

1.1.5.2 Unit of Measure

1.1.6 Commissioning of the New Batteries, Battery Monitoring System, and Chargers

1.1.6.1 Payment

1.1.6.2 Unit of Measure

1.1.7 Operations and Maintenance Manuals

1.1.7.1 Payment

1.1.7.2 Unit of Measure

1.1.8 Training

1.1.8.1 Payment

1.1.8.2 Unit of Measure

PART 2 PRODUCTS

PART 3 EXECUTION Not Used

SECTION 01 20 00 Page 1

SECTION 01 20 00 Page 2

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.1 PAYMENT ITEMS

Payment items for the work of this contract for which payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular payment item, shall be included in the listed payment item most closely associated with the work involved. The payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, environmental monitoring, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.1.1 Remove Existing Station Battery and Battery Rack

1.1.1.1 Payment

Payment will be made for costs associated with Remove Existing Station Battery and Battery Rack as specified in Section 26 32 34 BATTERIES.

Payment will be made at the contract price per Job for "Remove Existing Station Battery and Battery Rack."

1.1.1.2 Unit of Measure

Unit of measure: Job.

1.1.2 Furnish and Install New Station Battery and Battery Rack with Electrolyte Spill Containment

1.1.2.1 Payment

Payment will be made for costs associated with Furnish and Install New Station Battery and Battery Rack with Electrolyte Spill Containment as specified in Section 26 32 34 BATTERIES. Payment will be made at the contract price per Job for "Furnish and Install New Station Battery and Battery Rack with Electrolyte Spill Containment."

1.1.2.2 Unit of Measure

Unit of measure: Job.

1.1.3 Furnish and Install New Battery Monitoring System

1.1.3.1 Payment

Payment will be made for costs associated with Furnish and Install New Battery Monitoring System as specified in Section 26 32 34 BATTERIES.

Payment will be made at the contract price per Job for "Furnish and Install New Battery Monitoring System."

SECTION 01 20 00 Page 3

1.1.3.1.1 Unit of Measure

Unit of measure: Job.

1.1.4 Remove the Existing Battery Chargers

1.1.4.1 Payment

Payment will be made for costs associated with Remove the Existing Battery Chargers as specified in Section 26 32 36 BATTERY CHARGERS. Payment will be made at the contract price per Job for "Remove the Existing Battery Chargers."

1.1.4.2 Unit of Measure

Unit of Measure: Job.

1.1.5 Furnish and Install New Battery Chargers

1.1.5.1 Payment

Payment will be made for costs associated with Furnish and Install New Battery Chargers as specified in Section 26 32 36 BATTERY CHARGERS.

Payment will be made at the contract price per Job for "Furnish and Install New Battery Chargers".

1.1.5.2 Unit of Measure

Unit of Measure: Job.

1.1.6 Commissioning of the New Batteries, Battery Monitoring System, and Chargers

1.1.6.1 Payment

Payment will be made for costs associated with Commission of the New Batteries, Battery Monitoring System, and Chargers as specified in Sections 26 32 34 BATTERIES and 26 32 36 BATTERY CHARGERS. Payment will be made at the contract price per Job for "Commission of the New Batteries, Battery Monitoring System, and Chargers."

1.1.6.2 Unit of Measure

Unit of Measure: Job.

1.1.7 Operations and Maintenance Manuals

1.1.7.1 Payment

Payment will be made for costs associated with Operations and Maintenance Manuals as specified in Sections 26 32 34 BATTERIES and 26 32 36 BATTERY CHARGERS. Payment will be made at the contract price per Job for "Operations and Maintenance Manuals."

1.1.7.2 Unit of Measure

Unit of Measure: Job.

SECTION 01 20 00 Page 4

1.1.8 Training

1.1.8.1 Payment

Payment will be made for costs associated with Training as specified in Section 26 32 34 BATTERIES. Payment will be made at the contract price per Job for "Training."

1.1.8.2 Unit of Measure

Unit of Measure: Job.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 20 00 Page 5

SECTION 01 20 00 Page 6

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 SUMMARY

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

1.2.2 Approving Authority

1.2.3 Work

1.3 SUBMITTALS

1.4 SUBMITTAL CLASSIFICATION

1.4.1 Government Approved (G)

1.4.2 Information Only Submittals

1.5 PREPARATION

1.5.1 Transmittal Form

1.5.2 Electronic File Format

1.6 SUBMITTAL REGISTER

1.6.1 Use of Submittal Register

1.6.2 Contractor Use of Submittal Register

1.6.3 Approving Authority Use of Submittal Register

1.6.4 Copies Delivered to the Government

1.7 VARIATIONS

1.7.1 Considering Variations

1.7.2 Proposing Variations

1.7.3 Warranting that Variations are Compatible

1.7.4 Environmental Assessment of Variations

1.7.5 Review Schedule Extension

1.8 SCHEDULING

1.9 GOVERNMENT APPROVING AUTHORITY

1.9.1 Review Notations

1.10 DISAPPROVED SUBMITTALS

1.11 APPROVED SUBMITTALS

1.12 WITHHOLDING OF PAYMENT

1.13 STAMPS

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 33 00 Page 1

SECTION 01 33 00 Page 2

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 SUMMARY

The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.

Units of weights and measures used on all submittals are to be the same as those used in the reference drawings.

Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

Contractor's Quality Control (CQC) System Manager to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:

Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.

Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby.

Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.

A submittal register showing items of equipment and materials for when submittals are required by the specifications is included at the back of this section as Attachment 1 Submittal Register.

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

Submittals requirements are specified in the technical sections.

Submittals are identified by Submittal Description (SD) numbers and titles as follows:

SD-01 Preconstruction Submittals

Submittals which are required prior to construction or the start of the next major phase of the construction on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.

Certificates of insurance

SECTION 01 33 00 Page 3

List of proposed Subcontractors

List of proposed products

Submittal register

Health and safety plan

Work plan

Environmental protection plan

SD-02 Shop Drawings

Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

SD-05 Design Data

Design calculations, mix designs, analyses or other data pertaining to a part of work.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.

Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports.

Daily logs and checklists.

Final acceptance test and operational test procedure.

SD-07 Certificates

SECTION 01 33 00 Page 4

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.

Text of posted operating instructions.

SD-09 Manufacturer's Field Reports

Documentation of the testing and verification actions taken by manufacturer's representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must be signed by an authorized official of a testing laboratory or agency and state the test results; and indicate whether the material, product, or system has passed or failed the test.

Factory test reports.

SD-10 Operation and Maintenance Data

Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.

This data is intended to be incorporated in an operations and maintenance manual or control system.

SD-11 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.

1.2.2 Approving Authority

Office or designated person authorized to approve submittal.

1.2.3 Work

As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals , except those SD-01 Pre-Construction Submittals noted above , construction, SECTION 01 33 00 Page 5 materials, products, equipment, and systems incorporated or to be incorporated in such construction.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.

SD-01 Preconstruction Submittals

Submittal Register; G

Authorized Shop Drawing Approvers; G

1.4 SUBMITTAL CLASSIFICATION

Submittals are classified as follows:

1.4.1 Government Approved (G)

Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Within the terms of Contract Clause 52.236-21 Alt SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are considered to be "shop drawings."

1.4.2 Information Only Submittals

Submittals not requiring Government approval will be for information only.

They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above. Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications;

will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

1.5 PREPARATION

1.5.1 Transmittal Form

Use the transmittal form ENG Form 4025 for submitting both Government approved and information only submittals in accordance with the instructions provided. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph pertinent to the data submitted for each item.

SECTION 01 33 00 Page 6

1.5.2 Electronic File Format

Provide submittals in electronic format. Compile the submittal file as a single, complete document, to include the Transmittal Form described within. Name the electronic submittal file specifically according to its contents, coordinate the file naming convention with the Contracting Officer. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. Generate PDF files from original documents with bookmarks so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature, or scan of a signature.

Provide hard copies of submittals when requested by the Contracting Officer. Up to one additional hard copies of any submittal may be requested at the discretion of the Contracting Officer, at no additional cost to the Government.

1.6 SUBMITTAL REGISTER

Prepare and maintain submittal register, as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and

(i) as approved. A submittal register showing items of equipment and materials for which submittals are required by the specifications is provided as an attachment to Section 01 95 00 FORMS AND ATTACHMENTS. This list may not be all inclusive and additional submittals may be required.

The Government will provide the initial submittal register in electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.

Column (c): Lists specification section in which submittal is required.

Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each specification section.

Column (e): Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.

Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the Government. DO NOT pre-assign transmittal numbers when preparing the submittal register.

When a conflict exists between the submittal register and a submittal requirement in the technical sections, other than those submittals referenced in paragraph FIELD TEST REPORTS, the approved submittal register shall govern. The preliminary and then the final approved submittal register will become the scheduling documents and will be updated monthly and used to control submittals throughout the life of the contract. Names and titles of Contractor Authorized Shop Drawing Approvers shall be submitted to the POC with the final Submittal Register.

Supplier or subcontractors certifications are not acceptable as meeting this requirement.

SECTION 01 33 00 Page 7

1.6.1 Use of Submittal Register

Submit submittal register. Submit with QC plan and project schedule.

Verify that all submittals required for project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:

Column (a) Activity Number: Activity number from the project schedule.

Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.

Column (h) Contractor Approval Date: Date Contractor needs approval of submittal.

Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.

1.6.2 Contractor Use of Submittal Register

Update the following fields in the Government-furnished submittal register program or equivalent fields in program utilized by Contractor with each submittal throughout contract.

Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.

Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.

Column (l) List date of submittal transmission.

Column (q) List date approval received.

1.6.3 Approving Authority Use of Submittal Register

Update the following fields in the Government-furnished submittal register program or equivalent fields in program utilized by Contractor.

Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.

Column (l) List date of submittal receipt.

Column (m) through (p) List Date related to review actions.

Column (q) List date returned to Contractor.

1.6.4 Copies Delivered to the Government

Deliver one copy of submittal register updated by Contractor to Government with each invoice request.

1.7 VARIATIONS

Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21

SECTION 01 33 00 Page 8

SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION and will be considered where advantageous to Government.

1.7.1 Considering Variations

Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).

Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.

1.7.2 Proposing Variations

When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.

Clearly mark the proposed variation in all documentation.

Check the column "variation" of ENG Form 4025 for submittals which include proposed deviations requested by the Contractor. Set forth in writing the reason for any deviations and annotate such deviations on the submittal.

The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.

1.7.3 Warranting that Variations are Compatible

When delivering a variation for approval, Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.

1.7.4 Environmental Assessment of Variations

Any variations requested by the Contractor, which may have an environmental impact, shall meet the requirements of Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS. The Contracting Officer reserves the right to disapprove alternate methods, even if they are more cost effective, if the Contracting Officer determines that the proposed alternate method will have an adverse environmental impact.

1.7.5 Review Schedule Extension

In addition to normal submittal review period, a period of 10 calendar days will be allowed for consideration by the Government of submittals with variations.

1.8 SCHEDULING

Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Include certifications to be submitted with the pertinent drawings at the same time. No delay

SECTION 01 33 00 Page 9 damages or time extensions will be allowed for time lost in late submittals.

a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.

b. Submittals called for by the contract documents will be listed on the register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the register or marked "N/A."

c. Re-submit register and annotate monthly by the Contractor with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required.

d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."

e. Except as specified otherwise, allow review period, beginning with receipt by approving authority, that includes at least 30 calendar days for submittals for Contracting Officer approval. Period of review for submittals with Contracting Officer approval begins when Government receives submittal from QC organization.

f. Period of review for each resubmittal is the same as for initial submittal.

1.9 GOVERNMENT APPROVING AUTHORITY

When approving authority is Contracting Officer, the Government will:

a. Note date on which submittal was received.

b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.

c. Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with markings appropriate for action indicated.

1.9.1 Review Notations

Contracting Officer review will be completed within 30 calendar days after date of submission. Submittals will be returned to the Contractor with the following notations:

a. Submittals marked "(A) approved as submitted" for GA submittals or "(F) receipt acknowledged" for FIO submittals authorize the Contractor to proceed with the work covered.

b. Submittals marked "(B) approved except as noted on drawings" authorize the Contractor to proceed with the work covered provided he takes no

SECTION 01 33 00 Page 10 exception to the corrections.

c. Submittals marked "(C) approved, re-submission required" or "(E) disapproved," for GA submittals or "(X)receipt acknowledged, does not comply" indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until resubmittal is approved.

d. Submittals "Returned To Contractor For Corrections" will indicate submittal does not have evidence of being reviewed and approved by Contractor, or is not complete.

1.10 DISAPPROVED SUBMITTALS

Make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the specifications; notice as required under the FAR Clause 52.243-4 CHANGES, is to be given to the Contracting Officer.

Contractor is responsible for the dimensions and design of connection details and construction of work. Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.

If changes are necessary to submittals, make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.

1.11 APPROVED SUBMITTALS

The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing and other information are satisfactory.

Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work .

After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.

1.12 WITHHOLDING OF PAYMENT

Payment for materials incorporated in the work will not be made if required approvals have not been obtained.

1.13 STAMPS

Stamps used by the Contractor on the submittal data to certify that the submittal meets contract requirements is to be similar to the following:

SECTION 01 33 00 Page 11

| CONTRACTOR |

| (Firm Name) | | _____ Approved | | _____ Approved with corrections as noted on submittal data and/or | | attached sheets(s) |

| SIGNATURE: __________________________________________________________ |

| TITLE: ______________________________________________________________ |

| DATE: _______________________________________________________________ |

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 33 00 Page 12

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 35 26

GOVERNMENTAL SAFETY REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

1.2 DEFINITIONS

1.2.1 Competent Person (CP)

1.2.2 Competent Person, Fall Protection

1.2.3 Competent Person (CP) Trainer

1.2.4 High Risk Activities

1.2.5 High Visibility Accident

1.2.6 Load Handling Equipment (LHE)

1.2.7 Medical Treatment

1.2.8 Near Miss

1.2.9 Operating Envelope

1.2.10 Qualified Person (QP)

1.2.11 Qualified Person, Fall Protection (QP for FP)

1.2.12 Recordable Injuries or Illnesses

1.2.13 Government Property and Equipment

1.2.14 Load Handling Equipment (LHE) Accident or Load Handling

Equipment Mishap

1.3 SUBMITTALS

1.4 REGULATORY REQUIREMENTS

1.5 MEETINGS

1.5.1 Meetings

1.5.1.1 Preconstruction Conference

1.5.1.2 Safety Meetings

1.6 ACCIDENT PREVENTION PLAN (APP)

1.6.1 APP - Construction

1.6.2 Plans

1.6.2.1 Hazardous Energy Control Program (HECP)

1.6.2.2 Site Demolition Plan

1.7 ACTIVITY HAZARD ANALYSIS (AHA)

1.7.1 AHA Management

1.7.2 AHA Signature Log

1.8 DISPLAY OF SAFETY INFORMATION

1.8.1 Safety Bulletin Board

1.9 SITE SAFETY REFERENCE MATERIALS

1.10 EMERGENCY MEDICAL TREATMENT

1.11 NOTIFICATIONS and REPORTS

1.11.1 Mishap Notification

1.11.2 Accident Reports

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 35 26 Page 1

3.1 CONSTRUCTION AND OTHER WORK

3.1.1 Unforeseen Hazardous Material

3.2 ELECTRICAL

3.2.1 CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT)

3.2.2 Conduct of Electrical Work

3.2.3 Qualifications

3.2.4 Arc Flash

3.2.5 Grounding

3.2.6 Control of Hazardous Engergy (Lockout/Tagout)

3.2.6.1 Locout/Tagout Isolation

3.2.6.2 Lockout/Tagout Removal

3.2.7 Testing

SECTION 01 35 26 Page 2

SECTION 01 35 26

GOVERNMENTAL SAFETY REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)

ASSP A10.34 (2001; R 2012) Protection of the Public on or Adjacent to Construction Sites

ASSP A10.44 (2020) Control of Energy Sources (Lockout/Tagout) for Construction and Demolition Operations

ASSP Z244.1 (2016) The Control of Hazardous Energy Lockout, Tagout and Alternative Methods

ASSP Z359.0 (2018) Definitions and Nomenclature Used for Fall Protection and Fall Arrest

ASSP Z359.2 (2017) Minimum Requirements for a Comprehensive Managed Fall Protection Program

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

IEEE C2 (2017; Errata 1-2 2017; INT 1 2017) National Electrical Safety Code

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 (2020; ERTA 20-1 2020; ERTA 20-2 2020; TIA

20-1; TIA 20-2; TIA 20-3; TIA 20-4)

National Electrical Code

NFPA 70E (2021) Standard for Electrical Safety in the Workplace

NFPA 241 (2019) Standard for Safeguarding Construction, Alteration, and Demolition Operations

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

SECTION 01 35 26 Page 3

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910.147 The Control of Hazardous Energy (Lock Out/Tag Out)

29 CFR 1910.333 Selection and Use of Work Practices

29 CFR 1915.89 Control of Hazardous Energy (Lockout/Tags-Plus)

1.2 DEFINITIONS

1.2.1 Competent Person (CP)

The CP is a person designated in writing, who, through training, knowledge and experience, is capable of identifying, evaluating, and addressing existing and predictable hazards in the working environment or working conditions that are dangerous to personnel, and who has authorization to take prompt corrective measures with regards to such hazards.

1.2.2 Competent Person, Fall Protection

The CP, Fall Protection, is a person meeting the competent person requirements as defined in EM 385-1-1 Appendix Q and in accordance with ASSP Z359.0 , who has been designated in writing by the employer to be responsible for immediate supervising, implementing and monitoring of the fall protection program, who through training, knowledge and experience in fall protection and rescue systems and equipment, is capable of identifying, evaluating and addressing existing and potential fall hazards and, who has the authority to take prompt corrective measures with regard to such hazards.

1.2.3 Competent Person (CP) Trainer

A competent person trainer as defined in EM 385-1-1 Appendix Q, who is qualified in the training material presented, and who possesses a working knowledge of applicable technical regulations, standards, equipment and systems related to the subject matter on which they are training Competent Persons. A competent person trainer must be familiar with the typical hazards and the equipment used in the industry they are instructing. The training provided by the competent person trainer must be appropriate to that specific industry. The competent person trainer must evaluate the knowledge and skills of the competent persons as part of the training process.

1.2.4 High Risk Activities

High Risk Activities are activities that involve work at heights, crane and rigging, excavations and trenching, scaffolding, electrical work, and confined space entry.

1.2.5 High Visibility Accident

A High Visibility Accident is any mishap which may generate publicity or high visibility.

1.2.6 Load Handling Equipment (LHE)

LHE is a term used to describe cranes, hoists and all other hoisting

SECTION 01 35 26 Page 4 equipment (hoisting equipment means equipment, including crane, derricks, hoists and power operated equipment used with rigging to raise, lower or horizontally move a load).

1.2.7 Medical Treatment

Medical Treatment is treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even when provided by a physician or registered personnel.

1.2.8 Near Miss

A Near Miss is a mishap resulting in no personal injury and zero property damage, but given a shift in time or position, damage or injury may have occurred (e.g., a worker falls off a scaffold and is not injured; a crane swings around to move the load and narrowly misses a parked vehicle).

1.2.9 Operating Envelope

The Operating Envelope is the area surrounding any crane or load handling equipment. Inside this "envelope" is the crane, the operator, riggers and crane walkers, other personnel involved in the operation, rigging gear between the hook, the load, the crane's supporting structure (i.e. ground or rail), the load's rigging path, the lift and rigging procedure.

1.2.10 Qualified Person (QP)

The QP is a person designated in writing, who, by possession of a recognized degree, certificate, or professional standing, or extensive knowledge, training, and experience, has successfully demonstrated their ability to solve or resolve problems related to the subject matter, the work, or the project.

1.2.11 Qualified Person, Fall Protection (QP for FP)

A QP for FP is a person meeting the definition requirements of EM 385-1-1 Appendix Q, and ASSP Z359.2 standard, having a recognized degree or professional certificate and with extensive knowledge, training and experience in the fall protection and rescue field who is capable of designing, analyzing, and evaluating and specifying fall protection and rescue systems.

1.2.12 Recordable Injuries or Illnesses

Recordable Injuries or Illnesses are any work-related injury or illness that results in:

a. Death, regardless of the time between the injury and death, or the length of the illness;

b. Days away from work (any time lost after day of injury/illness onset);

c. Restricted work;

d. Transfer to another job;

e. Medical treatment beyond first aid;

SECTION 01 35 26 Page 5

f. Loss of consciousness; or

g. A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in (a) through (f) above

1.2.13 Government Property and Equipment

Interpret "USACE" property and equipment specified in USACE EM 385-1-1 as Government property and equipment.

1.2.14 Load Handling Equipment (LHE) Accident or Load Handling Equipment Mishap

A LHE accident occurs when any one or more of the eight elements in the operating envelope fails to perform correctly during operation, including operation during maintenance or testing resulting in personnel injury or death; material or equipment damage; dropped load; derailment;

two-blocking; overload; or collision, including unplanned contact between the load, crane, or other objects. A dropped load, derailment, two-blocking, overload and collision are considered accidents, even though no material damage or injury occurs. A component failure (e.g., motor burnout, gear tooth failure, bearing failure) is not considered an accident solely due to material or equipment damage unless the component failure results in damage to other components (e.g., dropped boom, dropped load, or roll over). Document an LHE mishap using the Crane High Hazard working group mishap reporting form.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" classification.

Submittals not having a "G" classification are for information only.