TS State of Michigan Statement of Work and Drawings - Attachment 1.pdf
PDF 4 MB Posted
- Attached to
- FY23 TS State of Michigan Spring Repairs
- Solicitation number
- 69727623Q000007
About this file
This solicitation requests quotations for repair services for the Training Ship State of Michigan. The U.S. Department of Transportation Maritime Administration seeks to award a firm fixed price contract to complete repairs described in the statement of work and drawings. Quotations are due by April 3, 2023 and must include pricing for all materials, equipment, and labor using the vendor pricing sheet. Repairs include renewing flooring, replacing handrails, installing a rescue boat and davit, refurbishing generator exhaust insulation, replacing chiller valves, conducting vibration and thermographic inspections, and providing supplemental labor and materials. The solicitation is set aside for small businesses with a NAICS code of 336611 and size standard of 1,250 employees. Award will be made to the responsible offeror with the lowest total evaluated price based on fixed unit rates for labor and materials.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AM0002.pdf | ||
| AM0001 Stalwart Class Drawings.xlsx | XLSX spreadsheet | |
| AM0001 69727623Q000007 TS SOMI FY23 Spring Repairs 3-30-23.pdf | ||
| AM0001 Drawings.zip | ZIP file | |
| E-Invoicing Requirement and Wage Determination - Attachment 4.pdf | ||
| Vendor Price Sheet - Attachment 2.xlsx | XLSX spreadsheet | |
| Solicitation Provisions and Contract Clauses - Attachment 3.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
T.S. State of Michigan
2023 Spring Repair Package
T.S. State of Michigan 2023 Spring Repair
GENERAL CONDITIONS AND SPECIFICATIONS
FOR REPAIRS AND RENEWALS
FOR THE
"TRAINING SHIP “STATE OF MICHIGAN”
Table of Contents
VESSEL PARTICULARS 10
ITEM NO. 101 – SERVICES 11
ITEM NO. 102 – GAS FREE CERTIFICATES 13
ITEM NO. 103 – RENEW 700‐SQFT OF FLOORING OF FOC’SLE DECK PASSAGEWAY 14
ITEM NO. 104 – REPAIR OR REPLACE APPROXIMATELY 100 LINEAR FEET OF STEEL
PIPE HANDRAILS 15
ITEM NO. 105 – TS STATE OF MICHIGAN RESCUE BOAT & DAVIT INSTALL DRAWINGS 16
ITEM NO. 106 – REFURBISH, RENEW ALL 4 SSDG EXHUAST PIPING LAGGING
INSULATION 18
ITEM NO. 107 – CARRIER™ CHILLER PLANT(S) HAND EXPANSION VALVE REPLACEMENT
ITEM NO. 108 – PERFORM A VIBRATION CONDITION MONITORING SURVEY &
THERMOGRAPHIC INSPECTION 20
ITEM NO. 109 ‐ SUPPLEMENTAL LABOR 21
ITEM NO. 110 ‐ SUPPLEMENTAL MATERIAL 22
Page
VESSEL PARTICULARS
NAME: T. S. State of Michigan (ex USNS Persistent)
TYPE: Twin screw diesel‐electric ‐ Training Vessel.
OWNERS: U. S. Government / U.S. DOT Maritime Administration
Official Number: CG003458
USCG Certification: Public Nautical School Ship
Radio Call Sign: NFSJ
ABS Classification A1‐E, Ice Strengthened Class "C", AMS, ACCU
ABS I.D. No. 8502561
IMO No. 8835451
Builder: Tacoma Boat Building Co., Tacoma WA.
Keel Laid: October 1984
Commissioned: August 1985
Port of Registry: NORFOLK, VA Length Overall 224' 00"
Beam: 43' 00" Design Draft: 15' 01"
Vertical Clearance: 71' 00" (Air Draft)
Deadweight : 2,250 tons
USCG Gross Tonnage: 1,914 tons
USCG Net Tonnage: 574 tons Cruising
Speed: 10 knots
Complement: 65 Officers and Midshipmen
Main Engines: Four (4) Caterpillar D398TA; 970 HP Main
Generators: Four (4) Kato 600 kW, 600 VAC, 3 Phase
Propulsion Motors: Two (2) General Electric, 800HP, 750 VDC
Bow Thrusters: Harbormaster 48" tunnel, 550 HP
Diesel Fuel Capacity: 228,615 gallons
Salt Water Ballast Capacity: 146, US Tons
Fresh Water Capacity: 5,099 gallons
ITEM NO. 101 – SERVICES
1.0 ABSTRACT
1.1 This item describes the requirements for providing services for the pre and post-cruise repair availability for the work that will be done at the vessel’s berth at Great Lakes Maritime Academy, Traverse City, Michigan.
2.0 REFERENCES/ENCLOSURES
2.1 None
3.0 ITEM LOCATION/DESCRIPTION
3.1 Great Lakes Maritime Academy, 715 E. Front St., Traverse City, MI 49686
4.0 GOVERNMENT FURNISHED MATERIALS/EQUIPMENT/SERVICE
4.1 None
5.0 NOTES
5.1 Provisions for services shall be considered on a per diem basis, and the total cost for the entire availability shall be included in the submitted firm-fixed-price. In the case of an increase or decrease in the length of the Contract, the cost (or credit) for services shall be based on the per diem amount, figured by dividing the submitted price by the length of Phase 1 (in days) as specified in the contractor’s proposal.
6.0 QUALITY ASSURANCE REQUIREMENTS
6.1 None additional.
7.0 STATEMENT OF WORK
7.1 Office: None required. Contractor will be allowed to utilize a space designated aboard the vessel if desired to conduct administrative work.
7.2 Shore Power: None required – shore power will be provided by Great Lakes Maritime Academy.
7.3 Compressed air: Provide 100 psi dry filtered compressed air at for their own purposed should it be required for accomplishment of repairs. Furnish, connect and disconnect all valves, fittings and hoses required. The ship’s air compressors shall not be used for any work or services.
7.4 Fire protection: Will be furnished from the vessel’s fire main system. System to remain charged at all times at areas where hot work is being performed. This is to be coordinated with the ship’s crew. Connect and disconnect all valves, fittings and hoses required.
7.4.1 The vessel’s fire pumps will be used for any work.
7.4.2 Provide contractor furnished portable fire extinguishers in all work areas where repair work is being carried out and must be of the nature and quantity that they can extinguish all types of fires.
7.4.3 The vessel’s fire extinguishers shall not be considered to fulfill the requirements of 7.4.2; however, this does not prevent personnel from using them in case of a real emergency.
7.4.4 Fire watch is to be provided on a continuous basis at all areas where hot work is being performed
7.5 Lighting: Provide adequate temporary lighting in way of repairs, surveys and inspections throughout the vessel.
7.6 Garbage and debris removal: Remove all waste, dirt and debris detailed for removal in these specifications and resulting from the work from the ship on a daily basis. All areas involved in work or traversed by workers or equipment shall be left clean and in good order.
7.6.1 Provide trash receptacles throughout the vessel to prevent trash from being littered on the vessel. Receptacles shall be emptied on a daily basis, or when required.
7.6.2 Remove hazardous materials such as paint containers, oily refuse, etc. and dispose of in accordance with local, state and federal regulations.
7.6.3 The Contractor and Owner shall make a joint survey of the entire vessel approximately one week prior to delivery to determine final clean up prior to completion of contract.
7.7 Crane service: Contractor to provide adequate crane service with qualified crane operators and riggers to accomplish any and all items within these specifications and any addenda thereto. Crane service will not be provided by the vessel’s crane/crew.
7.7.1 In addition to meeting the requirements of these specifications, the crane shall be of reach and capacity to meet the contractor’s needs; however, dock loading cannot exceed the dock’s allowable limits.
ITEM NO. 102 – GAS FREE CERTIFICATES
1.1 Work detailed in these specifications requires a hot work/gas free certificate, this item describes requirements. The contractor shall obtain required gas free certificates for "safe for workers" and "safe for hot work" from a certified Marine Chemist for all tanks or spaces where entry and/or hot work shall be required and adjacent tanks/spaces that are affected by hot work. A competent person shall maintain the certificates daily, including days when no worked is performed until such entry and hot work is completed.
2.0 REFERENCES/ENCLOSURES:
2.1 NFPA 306, Standard for the Control of Gas Hazards on Vessels.
2.2 NFPA 312, Standard for the Protection of Vessels during Construction, Repair, and
Layup.
3.0 ITEM LOCATION/DESCRIPTION
3.1 Various Locations throughout the vessel.
4.0 OWNER FURNISHED EQUIPMENT/MATERIAL/SERVICES
4.1 None.
5.0 STATEMENT OF WORK REQUIRED
5.1 Contractor shall provide the services of a Certified Marine Chemist to provide all gas free certificates in accordance with the above references.
5.2 Certificates shall be issued only by a Certified Marine Chemist and shall be maintained, on a daily basis, by a "Competent Person" as defined by the OSHA Regulations 29 CFR
1915.14 or NFPA 306.
5.3 Copies of the daily the Marine Chemist, Gas Free Certificate ‘Competent Person Log to be distributed as follows:
5.4 One copy to the MARAD representative.
5.5 One copy to the Vessel’s Master
5.6 One copy to the shipyard’s safety person.
5.7 Additional copy(s) to be displayed on the top of the gangway(s) as well as in the vicinity of the gas freed space(s).
5.8 Contractor shall provide and maintain ventilation to confined spaces as required by the
Marine Chemist, Gas Free Certificate ‘Competent Person Log to ensure the safety of personnel during work and inspections of confined spaces.
6.0 NOTES:
6.1 None
7.0 DELIVERABLES:
7.1 One copy of Marine Chemist, Gas Free Certificate ‘Competent Person Log to be provided daily to the MARAD Representative and an additional copy to the vessel’s Master.
ITEM NO. 103 – RENEW 700‐SQFT OF FLOORING OF FOC’SLE DECK PASSAGEWAY
1.0 ABSTRACT:
1.1 The intent of this item is to define the requirements for the contractor to remove existing vinyl tile flooring on the Foc’sle Deck Passageway and lay down new vinyl tile.
2.0 REFERENCES / ENCLOSURES:
2.1 46 CFR Part 167 (Public Nautical School Ships)
2.2 DWG 801 5988703 General Arrangement Above Main Deck
3.0 ITEM LOCATION / DESCRIPTION:
3.1 Location: Main Deck, BWO FR-14 to 54
4.0 GOVERNMENT FURNISHED EQUIPMENT / MATERIAL:
5.0 STATEMENT OF WORK
5.1 Contractor shall furnish all materials and consumables to complete the scope of work required.
5.2 Contractor shall remove all debris and removed materials and dispose of IAW applicable Federal, State and Local regulations as required
5.3 Test current flooring to be prepared for acceptance of new flooring and determine if current flooring will require renewal, or refurbishment
5.4 Ensure all material to be removed does not contain prohibited substances, such as asbestos.
5.5 Contractor shall utilize Lock-Out-Tag-Out procedures to disconnect items that will have to either be removed or relocated to prepare and make allowance for the floor to be prepped and the new flooring installed.
5.6 Prepare flooring to receive new flooring
5.7 Repair or replace all current galley deck drains located variously throughout as original.
5.8 Prep and coat all disturbed coatings as original
5.9 Replace all equipment that was removed or relocated to install flooring.
6.0 QUALITY ASSURANCE
6.1 All material and/or items used or renewed are to be type approved by the ABS or USCG and in compliance with ABS Rules and USCG Regulations for Fire and Volatile Organic (VOC’s).
6.2 All work to be approved by the vessel’s aster and MARAD COR
ITEM NO. 104 – REPAIR OR REPLACE APPROXIMATELY 100 LINEAR FEET OF STEEL PIPE
HANDRAILS
1.1 Repair or replace up to 100 Linear Feet of Handrails, located variously throughout the ship.
2.1 None
3.1 Location: Variously throughout the ship, specifically to be determined at ship check
5.0 STATEMENT OF WORK
5.1 Contractor will furnish all materials and consumables to complete the scope of work required in this specification.
5.2 Each linear foot of handrail consists as a top, middle bottom, rail
5.3 Top rail is 1-1/2” dia., Intermediate rails 1-3/8”. Stanchions are 8ft apart
5.4 Material ABS Copper Nickle with stainless keeper connecting rings
5.5 Crop off wasted sections of steel pipe handrails where specified and replace as original
5.6 A spacing between rails meets all USCG requirements with spacing be- tween courses not greater than 12 inches. The opening below the lowest course must not be more than 9 inches.
5.7 Prep and then coat as original
5.8 Installation must be to the satisfaction of the vessel’s Chief Engineer, Master or
MARAD COR
6.0 DELIVERABLES
6.1 None
ITEM NO. 105 – TS STATE OF MICHIGAN RESCUE BOAT & DAVIT INSTALL DRAWINGS
1.1 Maritime Administration (MARAD) DGO has a need for rapid turnaround Naval Architecture and Marine Engineering Services for the schoolship STATE OF MICHIGAN (SOMI), (sister ship to the TS GENERAL RUDDER) in conjunction with the installation of a new Palfinger Fast Rescue Boat (FRB), and A-Frame Davit.
1.2 The drawings and design will also need to take into account, the addition of six (6) new staterooms, which will also require drawings, to be installed during the vessel’s 2025 regularly scheduled required dry docking on the upper O2 Decks).
2.0 REFERENCES/ENCLOSURES
2.1 46 CFR – Chapter I, Sub-Chapter 160.156 – Rescue Boats and Fast Rescue Boats
(SOLAS)
2.2 Dwg. 0721-43600301 Foc’sle 01-Deck
2.3 1355-S9-1-1 REV C GENERAL ARRANGEMENT
2.4 General Arrangement Maindeck
2.5 General Arrangement Above Maindeck
2.6 Outboard Profile
2.7 Inboard Profile
2.8 Palfinger Provided Dwg.
2.8.1 Davit PRHE 35 - 2 Data Sheet
2.8.2 Davit Footprint 3P-5007578
2.8.3 FRB Technical_datasheet_600A-SWJ_D023584_C
2.8.4 FRB 3FA-100041E 600A SWJ
2.9 TS SOMI STATEROOM FEASIBILITY STUDY
Ship: STATE OF MICHIGAN, IMO 8835451 Tacoma Boat, Hull No. 408 LOA: 198.9′ x 43.0′ x 20.0′ School Ship (R)
PSTP, DVTP & FMEA USCG COI 65POB
FRB: Palfinger FRSQ 600A, FRSQ 600 A SWJ, 46 CFR 160.156 SOLAS Approved Fast Rescue Boat, (FRB), Weight WE (fully equipped incl. fuel) 1890 kg 1890 kg Weight WEP (fully loaded) 3130 kg 3130 kg
Davit: Palfinger GA PRHE 35-2 Davit, Winch, 04-04ES LH., SWL 36 kN
3.0 ITEM LOCATION/DESCRIPTION
3.1 Vessel is located at the Great Lakes Maritime Academy, 715 E Front Street, Traverse
City, Michigan 49686
3.2 01-Focsle Deck, Co-located with vessel’s current life rafts, starboard side.
3.3 Originally, the FRB was installed on the O1 deck port side but was moved up one deck to the current location following MARAD’s revised configuration to accommodate a Master Plan alteration for both the TS State of Michigan and its sister ship, TS General Rudder.
4.0 OWNER FURNISHED EQUIPMENT/MATERIAL/SERVICES
4.1 2022 Additional 02 Upper Deck Stateroom Feasibility Study
5.0 STATEMENT OF WORK REQUIRED
5.1 Contractor shall conduct an initial ship check to identify final location for installation of new rescue boat and staterooms.
5.2 Contractor shall discuss the options with MARAD surveyor, Chief Engineer and Master to finalize the locations and requirements.
5.3 Prepare preliminary arrangement (master conversion plan) of the modifications and obtain approval by MARAD and ship.
5.4 Prepare detailed engineering package for both modifications, including but not limited to structural, piping, electrical, HVAC, joiner drawings, and should include detailed bill of materials.
5.5 Conduct lightship weight calculations for the modifications, conduct inclining experiment to determine lightship particulars and update stability documents.
5.6 Revise and update ship’s selected record plans to reflect the current as-built condition on board the vessel, as will be required by ABS and USCG
5.6.1 General Arrangement
5.6.2 Fire & Safety Plan
5.6.3 Electrical One Line Diagram
5.7 Contractor shall submit a package that contains revisions in stability, design and engineering to ABS and USCG MSC for approval.
5.8 Arrange for:
5.8.1 ABS attended Stability Weight Test if Required
5.8.2 US Coast Guard attendance and approval
6.0 DELIVERABLES
6.1 Two (2) Full sized approved drawings and an electronic drawing in .pdf format, so it may be viewed without a special proprietary program.
ITEM NO. 106 – REFURBISH, RENEW ALL 4 SSDG EXHUAST PIPING LAGGING INSULATION
1.1 The intent of this item is to renew the insulate main engine piping, flexes and flanges with removable exhaust lagging and blankets on all four (4) Ship Service Diesel Generators (SSDG)
2.0 REFERENCES / ENCLOSURES:
2.1.1 Ref 2 - DWG 801-5988702 General Arrangement Main Deck & Below
2.1.2 Ref 8 - Photo Sheet SSDG NO.1 Current Lagging
3.0 ITEM LOCATION / DESCRIPTION:
3.1 Location – Hold Deck – Main Generator Room 3-34-0
3.2 No. 1,2,3 & 4 SSDG Exhaust Piping
5.0 CONTRACTOR FURNISHED EQUIPMENT / MATERIAL:
6.0 STATEMENT OF WORK
6.1 Contractor shall furnish all materials and consumables to complete the scope of work required, i.e. lagging/insulation and ancillary parts and equipment to secure the lagging as original
6.2 Contractor to provide all labor to remove the existing lagging and reinstall new lagging.
6.3 Contractor shall coordinate w/Original Equipment Manufacturer (OEM) for proper material to be used, as well as function and installation
6.4 Remove all poor conditioned, ripped, torn or otherwise damaged or oil-soaked lagging throughout the SSDG exhaust system
6.5 Replace lagging with OEM approved Lagging
6.6 Contractor shall remove all debris and removed materials and dispose of IAW applicable Federal, State and Local regulations as required
7.0 QUALITY ASSURANCE
7.1 All work to be done to the Satisfaction of the Chief Engineer, or MARAD COR
ITEM NO. 107 – CARRIER™ CHILLER PLANT(S) HAND EXPANSION VALVE REPLACEMENT
1.1 Replace hand expansion valves on both chillers, on the low side of the system.
2.1 Ref 2 - DWG 801-5988702 General Arrangement Main Deck & Below .pdf
3.1 Hold Deck Air Cond MCHRY Space 2-24-4
5.0 CONTRACTOR FURNISHED PARTS / EQUIPMENT / MATERIAL
5.1 Mueller B34595 1 5/8" X 1 5/8" ODF Refrigeration Sweat Angle Valve
5.2 Mueller AC17867 1 5/8” X 1 5/8" Refrigeration Sweat Straight Ball Valve W/Access
5.3 Henry 6298N 1 1/8" X 1 1/8" ODF Refrigeration Hand Expansion Valve
5.4 Carrier 5H80 1 5/8" Discharge Service Valve
5.5 Carrier 5H80 2" Suction Service Valve 1 5/8" ACR Copper Tube
5.6 Copper Refrigeration Fittings
5.7 Torch And Braze
5.8 30 LB Cylinder R-134A
6.0 STATEMENT OF WORK
6.1 Procure and provide all parts required per paragraph (5) of this work statement, plus any additional parts not mentioned if required
6.2 Recover refrigerant from each chill plant.
6.3 Cut and fit in new valve assemblies.
6.4 Pressure test system with dry nitrogen.
6.5 Evacuate system.
6.6 Start each system and charge with R-134A
7.0 DELIVERABLES / QUALITY ASSURANCE
7.1 All work must be done, and the system tested to the satisfaction of the vessel’s Chief Engineer.
7.2 Provide a complete technician report outlining what service was performed, including condition found and the remedy used to ensure proper function of the chiller.
ITEM NO. 108 – PERFORM A VIBRATION CONDITION MONITORING SURVEY & THERMOGRAPHIC
INSPECTION
1.0 ABSTRACT:
1.1 Perform a Baseline Vibration Condition Monitoring Survey & Thermographic Inspection on board the Training Ship, TS State of Michigan
2.0 REFERENCES / ENCLOSURES:
2.1 The following is an example of the type of reports generated for the State of Michigan’s Sister Ship, TS General Rudder
2.2 Ref 5 - TSGR - CAC Executive Summary - Dated 4-12-22
2.3 Ref 6 - TSGR - CAC Vibration Analysis - Dated 4-12-22
2.4 Ref 7 - TSGR - CAC Thermographic Insp - Dated 4-12-22
3.0 ITEM LOCATION / DESCRIPTION:
3.1 The ship will be located at their homeport, at the Great Lakes Maritime Academy, 1701 East Front
Street, Traverse City, MI 49686
4.0 GOVERNMENT FURNISHED EQUIPMENT / MATERIAL
4.1 None
5.0 STATEMENT OF WORK
5.1 Utilizing a portion of the relevant data listed in para (2), identify all critical machinery required to be surveyed and/or inspected
5.2 Evaluate the present operating condition of selected equipment of the vessel and provide recommendations based on the Vibration Analysis and Thermographic Inspection
5.3 Identify for the Chief Engineer and the Master, which equipment requires an at sea or dock trial to test, survey or inspect.
5.4 Provide Machine Ratings as follows:
5.4.1 Unsatisfactory: Machines that require attention.
5.4.2 Marginal: Machines that are vibrating above initial alarm levels. Increasing wear.
5.4.3 Satisfactory: Machines operating within acceptable vibration ranges.
5.4.4 Non-available: Not operating or not safe to take readings
6.0 DELIVERABLES / QUALITY ASSURANCE
6.1 All work must be done, and the system tested to the satisfaction of the vessel’s Chief
Engineer.
6.2 Conclude the survey and inspection with a discussion with the Chief Engineer and the
MARAD COR prior to departing the vessel.
6.3 Generate and provided a final report to the ship and MARAD, similar to those produced in Section 2
ITEM NO. 109 ‐ SUPPLEMENTAL LABOR
1.1 It is the intent of this item to provide supplemental labor to accomplish additional work if authorized.
2.0 REFERENCES / ENCLOSURES:
2.1 None
3.0 ITEM LOCATION / DESCRIPTION:
3.1 None
4.0 GOVERNMENT FURNISHED EQUIPMENT / MATERIAL:
4.1 None
5.0 CONTRACTOR FURNISHED EQUIPMENT / MATERIAL:
5.1 As Required
6.0 STATEMENT OF WORK:
6.1 Contractor shall furnish a unit price quote for 500 man-hours of supplemental labor. This shall be a fully burdened labor rate, and is applicable seven days a week (i.e., no overtime, penalty time or other escalations will apply).
6.2 These hours will only be allocated for industrial labor. Supervision, management, QA, yard maintenance and other such labor is considered part of the rate burden. When Supplemental Labor is required by MARAD, a Contractor-submitted Condition Report with fully documented price quotations shall be documented by a work structure breakdown on a Contractor-developed estimating form, as an attachment to the Condition Report.
6.3 Supplemental hours, if authorized, will be allocated by the COR via delivery orders. No oral directions shall be accepted by the Contractor or its personnel from any individual other than the COR. Any oral direction provided by the COR other than guidance on existing tasking shall be documented via delivery order Request for Pricing within 24 hours.
6.4 All tasking provided by the COR will normally be in writing, and no work shall begin on any tasking of another than emergency nature until received by the Contractor, negotiated and settled by the COR and/or the Contracting Officer. Any questions, concerns or disputes of tasking given (including challenges as to whether CLINs are within scope or genuine new work) shall be presented to the Contracting Officer in writing for resolution.
ITEM NO. 110 ‐ SUPPLEMENTAL MATERIAL
1.1 Contractor shall include in their quote $50,000.00 for material charges, in the event needed and ordered by the COR for supplemental growth.
2.1 In the past, MARAD has contracted the services of None
3.1 None
5.0 CONTRACTOR FURNISHED EQUIPMENT / MATERIAL:
5.1 As Required
6.0 STATEMENT OF WORK:
6.1 Contractor shall provide an allowance for up to $25,000.00 in Supplemental Material charges.
There shall be no burden on these charges for either subcontracted costs or material charges up to $50,000. If this item is modified to add additional funds in excess of $50,000 the burden will be subject to negotiation.
6.2 If Supplemental Material is required, it will be allocated by the COR via delivery orders.
6.3 The Contractor shall provide to the COR invoices for goods or services applicable to
Supplemental Material charges for each delivery order with material charges in excess of $250.00
6.4 Negotiations based on material estimates will be credited or debited accordingly, once the actual material invoice is received by the COR.
6.5 All material invoices must be received no later than the completion of each delivery order.
6.6 Retainage will not be released until all material invoices have been received and approved by the
COR. The contract cannot be closed out until all material invoices are submitted, or delivery orders will be debited accordingly.
7.0 QUALITY ASSURANCE:
7.1 All material and/or items used or renewed are to be type approved by the ABS or USCG and in compliance with ABS Rules and USCG Regulations.
- , -AGos 10-ao1-s9El870J
T-1'Cl<lS
LLI::::; '-' z1.,._ -w•:i "' :J
!i
,1·! I •
' 0
'" um
' C ro
'it·
!,l.
I, ;s JS lh a H i I
!i r I, i 1•t ,, 'l jN 0 -
'I ,!
r\ t, u ro
0"z
I
- , -AGos 10-ao1-s9El870J
T-1'Cl<lS
LLI::::; '-' z1.,._ -w•:i "' :J
!i
,1·! I •
' 0
'" um
' C ro
'it·
!,l.
I, ;s JS lh a H i I
!i r I, i 1•t ,, 'l jN 0 -
'I ,!
r\ t, u ro
0"z
TAGOS61NBDPROF
11 10
REVISIONS -
H
G
APPLICABLE SHIPS
NO.
T-AGOS 10 U$N
NO CN.IBEJI
(DEO< Rl5£ POI fR • 0.272 INCH)
""-'N, FCSLE, ,. UPPEJ! OECl<S
INBOARD PROFILE
11,.WNEI. •-7-0
>fl). Pl.AN HO. nru:
REFERENCES
r:.;oos 10---SJS-59881o4 ';'" ..
A ERICAN BUREAU Of" SHIPPING
10 SV8MIT RESUBMIT ..,,PROV,.. ,.
OAT(
11 10
RECOAI> 442
2 .,,,.., SCAI.( 1/4" • 1'-0" ts,,(ET 1 Of' 1
TAGOS60UTBDPROF
14 11 10
REVISIONS
DESC"1Pll0N
H
NA,V,HSEANT
& OIR£CTION
r 'w
G
!AS>< LICHT P/s (RID)
TV/Fl,I ,,HENNA
Ylt!ISI\.E
BOAT DA"!
F"IY NHS
TOW,NG LIGHT
0!6
P/S
UFFJ!A
BREADTH. MOWED
MOWED
ORAF"l,DESIGN s,>EF;IJ. TO\\ING
CRUISING RANGE
NET TONNAGE
G.E, PROPIJLSOON MOlQi,S RA1£D SHP
OFFlCERS ANO CREW OlHERS
43"-o· a.so N Mil.ES
CAPACITIES:
FUEL Oil AT 98
POTABLE WATER AT ,oo,i
Cl ASSlflCATION· ABS@ AH] , CLJ,SS C ICE STJ!.NGlH.NING @AWs,® ACCU.
MID5><1P
(Fa 4S
OUTBOARD PROFILE
AWORICAN BUREAU OF SHIPPING
SUBMITTED TO
OUTBOARD PROFILE
14 13
Prepared for U.S. MARITIME ADMINISTRATION (MARAD), GENERAL RUDDER (06/01/2022) | Page 1/3
Copyright © 2000 - 2022 - Condition Analyzing Corporation - All rights reserved.
Condition Analyzing Corporation 1637 Race Track Rd. Suite 136 St Johns, Florida 32259 904-903-6116
U.S. MARITIME ADMINISTRATION (MARAD)
GENERAL RUDDER
Executive Summary of machine vibration data collected during the period of:
Wednesday, April 27th 2022 Through Friday, May 13th 2022
UNSATISFACTORY
Occurs
007 U #2 D/G STBD TURBOCHARGER Imbalance/wear. 1
066 U #2 FIRE/BALLAST PUMP Imbalance/flexibility/wear. Greater in the pump. 1
004 M #4 DIESEL GENERATOR CAT D-398B Monitor generator. 1
027 M PROP. MOTOR VENT FAN Fan imbalance/wear. 1
042 M #1 PROP. MOTOR LUBE OIL PUMP Decreased. Pump imbalance/foundation flexibility. 1
050 M BOW THRST. S/W COOLING PUMP Bearing wear. 1
060 M FUEL OIL TRANSFER PUMP Looseness. 1
080 M #1 STARTING AIR COMPRESSOR Compressor wear. 2
081 M #2 STARTING AIR COMPRESSOR Belt looseness/wear. 1
082 M #1 S.S. AIR COMPRESSOR Compressor wear/misalignment. 2
116 M STBD ER SUPPLY FAN Motor imbalance/flexibility. 1
120 M AC RECIRC FAN 0-2 Fan looseness/misalignment. 1
001 S #1 DIESEL GENERATOR CAT D-398B 5
002 S #2 DIESEL GENERATOR CAT D-398B
003 S #3 DIESEL GENERATOR CAT D-398B
005 S #1 D/G STBD TURBOCHARGER
006 S #1 D/G PORT TURBOCHARGER
008 S #2 D/G PORT TURBOCHARGER
009 S #3 D/G STBD TURBOCHARGER Mild imbalance. 4
010 S #3 D/G PORT TURBOCHARGER
011 S #4 D/G STBD TURBOCHARGER Mild imbalance. 5
012 S #4 D/G PORT TURBOCHARGER Mild imbalance. 5
013 S #1 D/G ATTACHED S/W COOLING
PUMP
MARGINAL Occurs
SATISFACTORY Occurs
Executive Summary of machine vibration data collected during the period of:
Wednesday, April 27th 2022 Through Friday, May 13th 2022
Prepared for U.S. MARITIME ADMINISTRATION (MARAD), GENERAL RUDDER (06/01/2022) | Page 2/3
014 S #2 D/G ATTACHED S/W COOLING
015 S #3 D/G ATTACHED S/W COOLING
016 S #4 D/G ATTACHED D/W COOLING
020 S BOW THRUSTER
025 S #1 PROPULSION MOTOR
026 S #2 PROPULSION MOTOR
033 S #1 STEERING GEAR
034 S #2 STEERING GEAR
035 S STBD SHAFT SEAL
036 S PORT SHAFT SEAL
037 S EMERGENCY GENERATOR CAT.
3408TA
038 S E/G TURBOCHARGER Mild imbalance. 2
040 S LUBE OIL TRANSFER PUMP Short run. 1
043 S #2 PROP. MOTOR LUBE OIL PUMP
044 S #1 SHAFT LUBE OIL PUMP
045 S #2 SHAFT LUBE OIL PUMP
051 S #1 AUX. S/W COOLING PUMP Moderate imbalance/misalignment. 2
052 S #2 AUX. S/W COOLING PUMP Decreased. 2
061 S FUEL OIL PURIFIER
065 S #1 FIRE/BALLAST PUMP
071 S #2 A/C CHILLER
073 S #1 CHILLED WATER PUMP
074 S #2 CHILLED WATER PUMP
075 S #3 CHILLED WATER PUMP
083 S #2 S.S. AIR COMPRESSOR
084 S ROTARY COMPRESSOR
101 S DECK CRANE
102 S MAIN ANCHOR WINDLASS PUMP
103 S #1 MOORING WINDLASS
Executive Summary of machine vibration data collected during the period of:
Wednesday, April 27th 2022 Through Friday, May 13th 2022
Prepared for U.S. MARITIME ADMINISTRATION (MARAD), GENERAL RUDDER (06/01/2022) | Page 3/3
104 S #2 MOORING WINDLASS 2
105 S #3 MOORING WINDLASS
111 S SUPPLY FAN 1-37-2 Moderate fan imbalance. 1
117 S PORT ER SUPPY FAN Check belts. 1
121 S STEERING GEAR SUPPLY FAN 2-96-1 2
053 N PROP. MOTOR S/W COOLING PUMP Not used. 3
070 N #1 A/C CHILLER Out of service. 3
072 N #3 A/C CHILLER Out of service. 3
077 N #1 REFRIGERATION COMPRESSOR
078 N #2 REFRIGERATION COMPRESSOR
096 N #1 BILGE PUMP Docked. 3
097 N #2 BILGE PUMP Docked. 3
098 N #3 BILGE PUMP Docked. 3
110 N HOUSE VENTILATION FAN Inaccessible. 3
112 N SUPPLY 1-35-4 Inaccessible. 3
113 N SUPPLY 1-68-3 Inaccessible. 3
114 N SUPPLY FAN AC ROOM 2-32-2 Inaccessible. 3
115 N LAUNDRY ROOM EXHAUST FAN 2-2-1 Inaccessible. 3
118 N GALLEY EXHAUST FAN Inaccessible. 3
119 N AC RECIRC FAN 2-55-2 Inaccessible. 3
NOT AVAILABLE Occurs
Prepared for U.S. MARITIME ADMINISTRATION (MARAD), GENERAL RUDDER (06/01/2022) | Page 1/15
1637 Race Track Rd. Suite 136 St Johns, Florida 32259 904-903-6116
Thank you for the opportunity to complete a vibration analysis condition monitoring survey. This report contains analysis of the vibration data, including comments and recommendations for corrective action.
Survey information:
Vessel name: GENERAL RUDDER Company: U.S. MARITIME ADMINISTRATION (MARAD) Sign on Port: Galveston, TX Sign off Port: Galveston, TX Data collection start date: Wednesday, April 27th 2022 Data collection end date: Friday, May 13th 2022 Data collected by: PJR and Crew Data collection instrumentation: VA3 - 631712 - PJR, Cal due 2023-04-28 Data collection instrumentation: DC-101058-Rental, Cal due 2023-04-03
Data collection and analysis software: DDS 2022 v 3.6.2.6, CAC Decision Point v5
CAC vibration data collection:
Vibration measurements were obtained in in/sec peak and were taken on each accessible bearing location in three measurement planes. Both overall and vibration signature traces were obtained.
Vibration limit levels:
Measured vibration is compared to vibration limit levels established by CAC's experience with shipboard machinery, as well as ANSI and other standards organizations.
Experienced CAC vibration analysts factored the following:
• Trend analysis
• Readings compared to alarm levels
• Comparison to sister machines and like machinery on sister vessels
• Reported repair history sent to CAC
• Operating conditions.
CAC machine ratings:
This report categorizes machines as follows:
• Unsatisfactory: Machines that require attention.
• Marginal : Machines that are vibrating above initial alarm levels. Increasing wear.
• Satisfactory: Machines operating within acceptable vibration ranges.
• Non-available: Not operating or not safe to take readings.
CAC has the following 'Condition Monitoring' Class certificates:
• ABS Certificate Number 20-4564981-A as a "Recognized External Specialist".
• Lloyds Register Certificate Number LR21116508AS as an "Approved Service Supplier".
CAC maintains all historical data from the vessel. Additional data including vibration signatures and Report Links (PDF) are available on the vessel's home page on the CAC Decision Point ® website at www.cacvibe.net.
DISCLAIMER: CAC assumes no responsibility for machinery failures whatsoever or for any aspect of vessel or machinery operation. Liability is limited to the cost of the service work performed by CAC. CAC service personnel are considered as 'Persons in Addition to the Crew' while onboard. This report is for the use of the client only.
http://www.cacvibe.net/
Analysis of machine vibration data obtained during the period of:
Wednesday, April 27th 2022 through Friday, May 13th 2022
Machine Description CAC ID Client ID
Prepared for U.S. MARITIME ADMINISTRATION (MARAD), GENERAL RUDDER (06/01/2022) | Page 2/15
066 #2 FIRE/BALLAST PUMP UNSATISFACTORY
Summary: Imbalance/flexibility/wear. Greater in the pump.
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 1 Vibration levels are excessive at rotation rate on the motor and pump. Levels are greatest on the pump in the horizontal direction. Imbalance and wear aggravated by foundation flexibility or looseness are indicated.
Recommend Inspect foundation and mounting bolts. Inspect motor cooling fan and coupling.
Service the pump, then the motor.
027 PROP. MOTOR VENT FAN MARGINAL
Summary: Fan imbalance/wear.
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 1 Comment: B point inaccessible.
Vibration levels have increased and are elevated at fan rotation rate. Fan imbalance and wear is indicated.
Recommend Inspect foundation and mounting bolts. Evaluate support structure. Clean and inspect the fan. Inspect the fan shaft, sheave, and keyway. If levels persist, renew the fan bearings. Balance the fan as a last step.
Summary: Imbalance/wear.
#2 D/G STBD TURBOCHARGER UNSATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 1 Vibration levels exceed the upper alarm at rotation rate. Imbalance and wear are indicated.
Recommend Clean and inspect the rotor. Plan service.
Summary: Monitor generator.
#4 DIESEL GENERATOR CAT D-398B MARGINAL
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 1
Comment: At speed no load Vibration levels are excessive on the driven end of the generator and greater than seen on the other units at no load. Vibration is elevated at 7,200 cpm which is either the 6X-rotation rate firing order from the engine or 2X-60Hz line frequency. Rough engine firing at no load is indicated. An electrical fault in the generator cannot be ruled out.
Recommend Retest under load. Inspect foundation bolts. Evaluate generator operation. Do not delay any planned maintenance.
Analysis of machine vibration data obtained during the period of:
Wednesday, April 27th 2022 through Friday, May 13th 2022
Machine Description CAC ID Client ID
Prepared for U.S. MARITIME ADMINISTRATION (MARAD), GENERAL RUDDER (06/01/2022) | Page 3/15
050 BOW THRST. S/W COOLING PUMP MARGINAL
Summary: Bearing wear.
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 40 Occurs: 1 Comment: Recently overhauled.
Vibration levels have increased and are over the alarm. Vibration at 3.64X-rotation rate and multiples indicates a bearing fault. Levels are elevated on the motor and pump.
Recommend Review recent overhaul. Renew bearings.
042 #1 PROP. MOTOR LUBE OIL PUMP MARGINAL
Summary: Decreased. Pump imbalance/foundation flexibility.
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 1 Comment: Recently replaced with new motor/pump.
Vibration levels have decreased since the August 2021 readings but remain elevated on the pump. Vibration at rotation rate indicates imbalance and misalignment in the pump or coupling. Levels are twice as high in the horizontal direction indicating flexibility in the support skid. Levels are acceptable on the motor.
Recommend Review recent repairs. Inspect foundation, mounting bolts, and support skid.
Evaluate condition of skid mounts. Inspect the coupling and check alignment. If levels persist, replace the pump.
Summary: Looseness.
FUEL OIL TRANSFER PUMP MARGINAL
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 1 Vibration levels are over the alarm on the motor and driven end of the pump. Levels are greatest at 3X-motor rotation rate in the axial direction indicating looseness or misalignment. Vibration at 6X-pump rotation rate is likely characteristic and affected by flow. Additional vibration at 35,760 cpm has been seen in the past and is likely gear mesh.
Recommend Inspect foundation and mounting bolts. Inspect motor cooling fan, shaft, and coupling for looseness. Check alignment. Verify gearbox lubrication. If levels persist, service the motor.
Analysis of machine vibration data obtained during the period of:
Wednesday, April 27th 2022 through Friday, May 13th 2022
Machine Description CAC ID Client ID
Prepared for U.S. MARITIME ADMINISTRATION (MARAD), GENERAL RUDDER (06/01/2022) | Page 4/15
080 #1 STARTING AIR COMPRESSOR MARGINAL
Summary: Compressor wear.
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 2 Vibration levels are excessive and greater than on the #2 compressor. The greatest readings are in the horizontal direction on the compressor at 780 rpm or compressor rotation rate. Vibration at 390 cpm and multiples is seen on the other reciprocating compressors and may come from the belts. Levels are excessive on the motor but come from the compressor.
Recommend Inspect foundation, mounting bolts, and skid. Evaluate condition of skid mounts.
Inspect sheaves and belts. Service the compressor.
082 #1 S.S. AIR COMPRESSOR MARGINAL
Summary: Compressor wear/misalignment.
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 2 Vibration levels are excessive and greater than on the #2 compressor. Vibration at 780 rpm indicates imbalance and wear in the compressor. Misalignment cannot be ruled out. Levels are excessive on the motor but come from the compressor.
Vibration at 420 cpm and multiples likely comes from the belts.
Recommend Inspect foundation, mounting bolts, and skid. Evaluate condition of skid mounts.
Inspect sheaves and belts. Check alignment. Service the compressor.
081 #2 STARTING AIR COMPRESSOR MARGINAL
Summary: Belt looseness/wear.
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 1 Vibration levels have increased at 1,200 cpm or 3X-belt rate. Belt looseness or wear is indicated.
Recommend Inspect belts and sheaves.
116 STBD ER SUPPLY FAN MARGINAL
Summary: Motor imbalance/flexibility.
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 1 Vibration levels are elevated at motor rotation rate. Motor or sheave imbalance is indicated. Levels may be aggravated by support flexibility.
Recommend Inspect foundation and mounting bolts. Evaluate support. Inspect the motor sheave. Service the motor.
Analysis of machine vibration data obtained during the period of:
Wednesday, April 27th 2022 through Friday, May 13th 2022
Machine Description CAC ID Client ID
Prepared for U.S. MARITIME ADMINISTRATION (MARAD), GENERAL RUDDER (06/01/2022) | Page 5/15
120 AC RECIRC FAN 0-2 MARGINAL
Summary: Fan looseness/misalignment.
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 1 Vibration levels are elevated at 2X-fan rotation rate. Levels are greatest in the axial direction. Looseness in a fan component is indicated. Misalignment cannot be ruled out.
Recommend Verify foundation and mounting bolts. Evaluate condition of flexible mounts. Inspect fan sheave, shaft, and keyway for looseness. Check alignment. Clean and inspect the fan. If levels persist, renew the fan bearings.
002 #2 DIESEL GENERATOR CAT D-398B SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 5 Comment: At speed no load Vibration levels are acceptable. Firing order vibration increased on the generator at no load. The same effect is seen on all four generator.
005 #1 D/G STBD TURBOCHARGER SATISFACTORY
Vibration levels are acceptable.
001 #1 DIESEL GENERATOR CAT D-398B SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 5 Comment: At speed no load Vibration levels are acceptable. Firing order vibration increased on the generator at no load. The same effect is seen on all four generator.
003 #3 DIESEL GENERATOR CAT D-398B SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 5 Comment: at speed no load Vibration levels are acceptable. Firing order vibration increased on the generator at no load. The same effect is seen on all four generator.
Analysis of machine vibration data obtained during the period of:
Wednesday, April 27th 2022 through Friday, May 13th 2022
Machine Description CAC ID Client ID
Prepared for U.S. MARITIME ADMINISTRATION (MARAD), GENERAL RUDDER (06/01/2022) | Page 6/15
008 #2 D/G PORT TURBOCHARGER SATISFACTORY
010 #3 D/G PORT TURBOCHARGER SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 4
012 #4 D/G PORT TURBOCHARGER SATISFACTORY
Summary: Mild imbalance.
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 5 Vibration levels are acceptable. Rotation rate vibration has increased indicating mild imbalance or wear. Wash the rotor. Monitor for further increases.
006 #1 D/G PORT TURBOCHARGER SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 5 Vibration levels are acceptable.
Summary: Mild imbalance.
#3 D/G STBD TURBOCHARGER SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 4 Vibration levels are acceptable. Rotation rate vibration has increased indicating mild imbalance or wear. Wash the rotor. Monitor for further increases.
Summary: Mild imbalance.
#4 D/G STBD TURBOCHARGER SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 5 Vibration levels are acceptable. Rotation rate vibration has increased indicating mild imbalance or wear. Wash the rotor. Monitor for further increases.
Analysis of machine vibration data obtained during the period of:
Wednesday, April 27th 2022 through Friday, May 13th 2022
Machine Description CAC ID Client ID
Prepared for U.S. MARITIME ADMINISTRATION (MARAD), GENERAL RUDDER (06/01/2022) | Page 7/15
014 #2 D/G ATTACHED S/W COOLING PUMP SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 2 Vibration levels are acceptable. Vibration at 57,600 cpm is greater than seen on the other pumps and can be monitored.
016 #4 D/G ATTACHED D/W COOLING PUMP SATISFACTORY
025 #1 PROPULSION MOTOR SATISFACTORY
Fwd Draft: 14.25 Aft Draft: 14.75 Propeller RPM: 80 Occurs: 5 Comment: Crew data Vibration levels are acceptable. Readings were taken by CAC at the dock and by the crew underway. Vibration at 102X-rotation rate has been seen in the past and can be monitored. Vibration at 6X-line frequency is typical for the DC motor.
013 #1 D/G ATTACHED S/W COOLING PUMP SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 2 Vibration levels are acceptable.
015 #3 D/G ATTACHED S/W COOLING PUMP SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 2 Vibration levels are acceptable.
020 BOW THRUSTER SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 40 Occurs: 2 Comment: Pierside.
Vibration levels are acceptable at low rpm.
Analysis of machine vibration data obtained during the period of:
Wednesday, April 27th 2022 through Friday, May 13th 2022
Machine Description CAC ID Client ID
Prepared for U.S. MARITIME ADMINISTRATION (MARAD), GENERAL RUDDER (06/01/2022) | Page 8/15
033 #1 STEERING GEAR SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 40 Occurs: 5 Vibration levels are acceptable. Slight vibration at multiples of 12X-rotation rate is characteristic.
035 STBD SHAFT SEAL SATISFACTORY
Fwd Draft: 14.25 Aft Draft: 14.75 Propeller RPM: 80 Occurs: 3
026 #2 PROPULSION MOTOR SATISFACTORY
Fwd Draft: 14.25 Aft Draft: 14.75 Propeller RPM: 80 Occurs: 5 Comment: Crew data Vibration levels are acceptable. Readings were taken by CAC at the dock and by the crew underway. Vibration at 102X-rotation rate has been seen in the past and can be monitored. Vibration at 6X-line frequency is typical for the DC motor.
034 #2 STEERING GEAR SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 40 Occurs: 5 Vibration levels are acceptable. Vibration at multiples of 12X-rotation rate is characteristic.
036 PORT SHAFT SEAL SATISFACTORY
Fwd Draft: 14.25 Aft Draft: 14.75 Propeller RPM: 80 Occurs: 3
Analysis of machine vibration data obtained during the period of:
Wednesday, April 27th 2022 through Friday, May 13th 2022
Machine Description CAC ID Client ID
Prepared for U.S. MARITIME ADMINISTRATION (MARAD), GENERAL RUDDER (06/01/2022) | Page 9/15
037 EMERGENCY GENERATOR CAT. 3408TA SATISFACTORY
Comment: No load.
Vibration levels are similar to the trend and are acceptable.
040 LUBE OIL TRANSFER PUMP SATISFACTORY
Summary: Short run.
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 1
Comment: Tank full.
Vibration levels are acceptable. The machine was short run which resulted in incomplete testing.
Vibration at multiples of 11X-rotation rate are characteristic of the pump. Sideband vibration can be monitored.
044 #1 SHAFT LUBE OIL PUMP SATISFACTORY
Summary: Mild imbalance.
E/G TURBOCHARGER SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 2 Vibration levels are acceptable. Vibration at rotation rate indicates mild imbalance or wear. Wash the rotor. Monitor for increases.
043 #2 PROP. MOTOR LUBE OIL PUMP SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 4
Vibration levels are acceptable. Vibration at multiples of 12X-rotation rate is characteristic of the pump.
Analysis of machine vibration data obtained during the period of:
Wednesday, April 27th 2022 through Friday, May 13th 2022
Machine Description CAC ID Client ID
Prepared for U.S. MARITIME ADMINISTRATION (MARAD), GENERAL RUDDER (06/01/2022) | Page 10/15
051 #1 AUX. S/W COOLING PUMP SATISFACTORY
Summary: Moderate imbalance/misalignment.
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 2 Comment: Recently overhauled.
Vibration levels are below the alarm but have increased following overhaul.
Vibration at 1X-rotation rate indicates mild imbalance and misalignment. Check the foundation bolts and alignment. Monitor.
061 FUEL OIL PURIFIER SATISFACTORY
071 #2 A/C CHILLER SATISFACTORY
Vibration levels are acceptable. Vibration at 2X-rotation rate is characteristic.
045 #2 SHAFT LUBE OIL PUMP SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 5 Vibration levels are acceptable. Vibration at 2X-rotation rate is characteristic of the pump.
Summary: Decreased.
#2 AUX. S/W COOLING PUMP SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 2
Comment: Recently overhauled.
Vibration levels are acceptable. Levels decreased following overhaul.
065 #1 FIRE/BALLAST PUMP SATISFACTORY
Analysis of machine vibration data obtained during the period of:
Wednesday, April 27th 2022 through Friday, May 13th 2022
Machine Description CAC ID Client ID
Prepared for U.S. MARITIME ADMINISTRATION (MARAD), GENERAL RUDDER (06/01/2022) | Page 11/15
074 #2 CHILLED WATER PUMP SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 1
083 #2 S.S. AIR COMPRESSOR SATISFACTORY
Vibration levels are acceptable. Previous vibration at motor rotation rate has decreased. Compressor vibration is greatest on the motor due to transmissibility in the shared skid. Vibration on the compressor itself is similar to the trend and less than seen on the #1 unit.
101 DECK CRANE SATISFACTORY
073 #1 CHILLED WATER PUMP SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 1 Vibration levels are acceptable.
075 #3 CHILLED WATER PUMP SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 2 Vibration levels are acceptable.
084 ROTARY COMPRESSOR SATISFACTORY
Analysis of machine vibration data obtained during the period of:
Wednesday, April 27th 2022 through Friday, May 13th 2022
Machine Description CAC ID Client ID
Prepared for U.S. MARITIME ADMINISTRATION (MARAD), GENERAL RUDDER (06/01/2022) | Page 12/15
103 #1 MOORING WINDLASS SATISFACTORY
105 #3 MOORING WINDLASS SATISFACTORY
117 PORT ER SUPPY FAN SATISFACTORY
Summary: Check belts.
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 1 Vibration levels are below the alarm. Vibration at multiples of 660 cpm, greatest at 4X, is likely from the belts and indicates mild looseness. Check belt tightness. Continue to monitor.
102 MAIN ANCHOR WINDLASS PUMP SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 2 Vibration levels are acceptable.
104 #2 MOORING WINDLASS SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 2 Vibration levels are acceptable.
111 SUPPLY FAN 1-37-2 SATISFACTORY
Summary: Moderate fan imbalance.
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 1 Vibration levels are acceptable. Vibration at 1X-fan rotation rate indicates moderate imbalance. Cleaning the fan may reduce imbalance levels.
Analysis of machine vibration data obtained during the period of:
Wednesday, April 27th 2022 through Friday, May 13th 2022
Machine Description CAC ID Client ID
Prepared for U.S. MARITIME ADMINISTRATION (MARAD), GENERAL RUDDER (06/01/2022) | Page 13/15
053 PROP. MOTOR S/W COOLING PUMP NOT AVAILABLE
Summary: Not used.
Fwd Draft: 0 Aft Draft: 0 Propeller RPM: 0 Occurs: 3 No data available.
072 #3 A/C CHILLER NOT AVAILABLE
Summary: Out of service.
078 #2 REFRIGERATION COMPRESSOR NOT AVAILABLE
121 STEERING GEAR SUPPLY FAN 2-96-1 SATISFACTORY
Fwd Draft: 15 Aft Draft: 15 Propeller RPM: 0 Occurs: 2
Vibration levels are similar to August 2021 readings. Fan vibration is seen greatest on the motor.
Monitor for increases.
Summary: Out of service.
#1 A/C CHILLER NOT AVAILABLE
Fwd Draft: 0 Aft Draft: 0 Propeller RPM: 0 Occurs: 3
No data available.
077 #1 REFRIGERATION COMPRESSOR NOT AVAILABLE
Analysis of machine vibration data obtained during the period of:
Wednesday, April 27th 2022 through Friday, May 13th 2022
Machine Description CAC ID Client ID
Prepared for U.S. MARITIME ADMINISTRATION (MARAD), GENERAL RUDDER (06/01/2022) | Page 14/15
097 #2 BILGE PUMP NOT AVAILABLE
Summary: Docked.
Fwd Draft: 0 Aft Draft: 0 Propeller RPM: 0 Occurs: 3 Comment: Crew to take data underway.
110 HOUSE VENTILATION FAN NOT AVAILABLE
Summary: Inaccessible.
Fwd Draft: 0 Aft Draft: 0 Propeller RPM: 0 Occurs: 3
Comment: Safety concern.
Summary: Docked.
#1 BILGE PUMP NOT AVAILABLE
Fwd Draft: 0 Aft Draft: 0 Propeller RPM: 0 Occurs: 3 Comment: Crew to take data underway.
No data available.
Summary: Docked.
#3 BILGE PUMP NOT AVAILABLE
Fwd Draft: 0 Aft Draft: 0 Propeller RPM: 0 Occurs: 3
Comment: Crew to take data underway.
No data available.
Summary: Inaccessible.
SUPPLY 1-35-4 NOT AVAILABLE
Fwd Draft: 0 Aft Draft: 0 Propeller RPM: 0 Occurs: 3
Comment: Safety concerns.
Analysis of machine vibration data obtained during the period of:
Wednesday, April 27th 2022 through Friday, May 13th 2022
Machine Description CAC ID Client ID
Prepared for U.S. MARITIME ADMINISTRATION (MARAD), GENERAL RUDDER (06/01/2022) | Page 15/15
113 SUPPLY 1-68-3 NOT AVAILABLE
Fwd Draft: 0 Aft Draft: 0 Propeller RPM: 0 Occurs: 3
115 LAUNDRY ROOM EXHAUST FAN 2-2-1 NOT AVAILABLE
Fwd Draft: 0 Aft Draft: 0 Propeller RPM: 0 Occurs: 3
119 AC RECIRC FAN 2-55-2 NOT AVAILABLE
Fwd Draft: 0 Aft Draft: 0 Propeller RPM: 0 Occurs: 3 Comment: Safety concerns.
No data available.
Summary: Inaccessible.
SUPPLY FAN AC ROOM 2-32-2 NOT AVAILABLE
Fwd Draft: 0 Aft Draft: 0 Propeller RPM: 0 Occurs: 3
No data available.
Summary: Inaccessible.
GALLEY EXHAUST FAN NOT AVAILABLE
Fwd Draft: 0 Aft Draft: 0 Propeller RPM: 0 Occurs: 3
THERMOGRAPHIC INSPECTION
April 2022
Thermographic Inspection – General Rudder – April 2022
Client: Crowley Government Services for the US Maritime Administration
Vessel: GENERAL RUDDER
Start: April 27, 2022 End: April 28, 2022
Embark: Galveston, TX Disembark: Galveston, TX
The purpose of this thermographic inspection is to:
• Evaluate the operating condition of the ship’s electrical systems
• Isolate the locations of "hot spots" and recommend necessary corrective measures.
Temp Rise: Evaluation:
5° ‐ 9° C Corrective measures required at next scheduled maintenance period
10° ‐ 19° C Corrective measures required on a priority‐scheduling basis 20° ‐ 29° C Corrective measures required as soon as possible
30° C and up Corrective measures required immediately
ITEMS FOUND IN NEED OF CORRECTION:
Item #1 ‐ 1 Aux Cooling Pump ‐ 37oC rise (CORRECTED) Item #2 ‐ 1 Aux Cooling Pump ‐ 76oC rise (CORRECTED) Item #3 ‐ Port Aft Capstan –26oC rise Item #4 ‐ STBD Aft Capstan – 8oC rise
Item corrected Equipment: Item #1 ‐ 1 Aux Cooling Pump ‐ 37oC rise (CORRECTED)
Component/Lead: Breaker – Upper Right Lead
Panel/Deck Location: Generator Rm MCC 1A
Severity: Corrected
BEFORE –37oC difference AFTER – 2oC difference
IR_0773 IR_00781
Evaluation
Measurements: (BEFORE) Upper left lead 64oC, middle lead 68oC, right lead 101oC (AFTER) Lower left lead 53oC, middle lead 51oC, right lead 55oC
Probable Causes: Dirty/loose connection(s).
Recommendations: Clean/tighten connection(s). Replace burned lead.
Enter corrective actions below:
Date: 04/28/2022 Performed By: 1 A/E
Corrections:
Cleaned and tighten connections.
Item corrected Equipment: Item #2 ‐ 1 Aux Cooling Pump ‐ 76oC rise (CORRECTED)
Component/Lead: Terminal Strip – Upper Right Lead
Panel/Deck Location: Generator Rm MCC 1A
Severity: Corrected
BEFORE – 76oC difference AFTER –3oC difference
IR_0769 IR_0783
Measurements:…
This is the start of the file's text. The full file is on GovTribe.