TREASURY/IRS CLAUSES

1052.232-7003 Electronic Submission of Payment Requests (Apr 2015)

(a) Definitions. As used in this clause-

(1) "Payment request" means a bill, voucher, invoice, or request for contract financing payment with associated supporting documentation. The payment request must comply with the requirements identified in FAR 32.905(b), "Content of Invoices" and the applicable Payment clause included in this contract.

(b) Except as provided in paragraph (c) of this clause, the Contractor shall submit payment requests electronically using the Invoice Processing Platform (IPP). Information regarding IPP, including IPP Customer Support contact information, is available at www.ipp.gov or any successor site.

(c) The Contractor may submit payment requests using other than IPP only when the Contracting Officer authorizes alternate procedures in writing in accordance with Treasury procedures.

(d) If alternate payment procedures are authorized, the Contractor shall include a copy of the Contracting Officer's written authorization with each payment request.

(End of clause)

IR1052.232-7003 Electronic Invoicing and Payment Requirements for the Invoice Processing Platform (IPP) (JUL 2015)

(a) Definitions:

"Short payment" as used in this clause means an invoice that includes the cost or price for supplies or services delivered or performed, as well as the cost or price for supplies or services not yet tendered to the Government in accordance with the terms of the contract, order or agreement.

"Short payment" example: The contract requires the delivery of a set number of items, with the price, delivery location, and delivery due date also specified. The vendor delivers 50% of the items as specified but invoices for 100% of the items. Before implementation of the IPP, the IRS would have paid the vendor for the items delivered and instructed the vendor to re-invoice the IRS when the balances of the items were delivered. In other words, the IRS would "short pay" the invoice since the IRS did not remit payment for the full invoice amount. With implementation of the IPP, the IRS can no longer do this because the IRS cannot accept an electronic invoice that includes items not yet received. The IRS will reject the invoice. The vendor needs to submit an invoice for only the items received by the IRS (in this case, 50%), and, assuming that these items meet all other contract terms and conditions, the IRS will pay the invoiced amount. The vendor submits subsequent invoice(s) for items as they are delivered and accepted.

(b) The Invoice Processing Platform (IPP) is a secure Web-based electronic invoicing and payment information service available to all Federal agencies and their suppliers. Effective October 1, 2012, invoicing for payment through the IPP will be mandatory for all new contract awards. Additional information regarding the IPP may be found at the IPP website address https://www.ipp.gov. Contractors must complete the contractor point of contact information below, and submit it with their proposal submissions. Contractors may contact the IPP Helpdesk for assistance via e-mail atippgroup@bos.frb.org or via phone at (866) 973-3131. Once a contract award has been made, the contractor will be contacted by the IPP via e-mail to set-up an account. It will be necessary for contractors to login to their IPP accounts every 90 days to keep their IPP accounts active.

(c) Contractor Point of Contact Information Contractor Name: _______________________ Contractor IPP Point of Contact Name: __________________________ Contractor Phone Number: _________________________ Contractor E-mail Address: _______________________________

(d) Electronic Invoicing and Payment Requirements

Vendor invoices submitted electronically through the IPP should be in the proper format and contain the information required for payment processing. In order to be approved for payment, a "proper invoice" must list the items specified in FAR 52.232-25 (a)(3)(i) through (a)(3)(x), or in the case of a Commercial Item Contract, the items included in 52.212-4(g)(1)(i) through (g)(1)(x).

If the vendor is offering a discount via the IPP, the discount must be reflected on the invoice. The vendor will select 'Create Invoice'. The IPP system will default to `Net 30 Prompt Pay` under the Payment Terms dropdown box. The vendor will select from 54 different discount options for the invoice that is being created. If the vendor chooses to offer a discount on the invoice screen, the information will interface to the payment system for processing. Discounts that are offered on attachments rather than the invoice itself cannot be accepted.

Under this contract, the following documents are required to be submitted as an attachment to the invoice (Contracting Officer fills in additional documentation that must be furnished by the contractor (e.g. timesheet)) Please do not submit into IPP any documentation/attachments that conflict with what is stated on the invoice:

(e) Payment and Invoice Questions

For payment and invoice questions, contact the Beckley Finance Center at (304) 254-3372 or via e-mail at cfo.bfc.ipp.customer.support@irs.gov.

(f) Waiver

If the Contractor is unable to use the IPP for submitting payment requests starting on October 1, 2012, then a waiver form must be completed and submitted with the contractor`s proposal submission for review and approval by the Contracting Officer based on one of the conditions listed in the waiver form included as Attachment 1 to this clause. The vendor will be notified prior to award as to whether their request for waiver has been approved or denied. If the waiver is granted, then a copy of the waiver must be submitted with each paper invoice that the vendor submits to the payment office or the invoice will be returned.

g) Short Payment

Short payment on vendor submitted invoices will no longer be processed or paid. If any portion of the invoice does not meet the requirements for a proper invoice, the entire invoice shall be rejected and returned to the vendor unpaid.

(End of Clause)

IR1052.232-7003 W Internal Revenue Service (IRS) Invoice Processing Platform (IPP) Waiver Form - Attachment 1

The IRS invoicing and payment requirements clause (IR1052.232-7003) requires that all invoices under awards made (or effective) on or after October 1, 2012, be submitted electronically via the IPP unless a waiver is requested and granted. If the Contractor is unable to submit its invoice through the IPP, the Contractor shall complete this waiver form indicating the reason for the waiver request by selecting the appropriate box below and providing a narrative summarizing in detail the circumstances requiring a waiver. For a solicitation, submit the waiver form with the proposal submission. For a modification that incorporates the IPP clause into an existing contract, submit the form with the modification. The CO will notify the vendor via e-mail or another appropriate means of communication prior to award as to whether their waiver has been approved or denied. If the waiver is granted, then a copy of the approved waiver must be submitted with each invoice that the vendor submits to the payment office or the invoice will be returned.

Reason for requesting a waiver of the requirement to submit an electronic invoice via the IPP:

|_|1.Submission of invoices through IPP would impose a hardship on an individual (includes employees and sole proprietors) due to: either a physical or mental disability; a geographic, language, or literacy barrier; or an undue financial burden. The requirement to submit invoices through the IPP is automatically waived for all individuals who do not have payment capability using ACH with a U.S. financial institution.
|_|2. The political, financial or communications infrastructure where the place of business is located does not support access to the IPP for submitting invoices electronically.
|_|3. The contractor is located within an area designated by the President of the United States or an authorized agency administration as a disaster area. (Please identify area/location.)
|_|4.The submission of invoices electronically may pose a threat to national security, the life or physical safety of an individual may be endangered, or a law enforcement action may be compromised.
|_|5. The agency does not expect to receive more than one invoice from the same contractor within a one-year period. i.e., the invoice submission is non-recurring.
|_|6. The contractor customarily submits a high volume of invoices on a regular basis via file format, not currently supported by the IPP (i.e., uses a file format other than XML or CSV) and the high volume of invoices would cause a significant burden to the contractor if submitted through the IPP individually. If utilizing this exception, please identify the file formats supported by your invoicing system so that the IPP may consider implementing the requested file format at a later date. File format(s) used: .
|_|7. Other - Please explain

Attach a separate sheet of paper with a summary narrative substantiating the circumstances for the waiver exception selected from above (1 through 7).

Waiver Submitted By:

Contractor Name

Name of Person Submitting Request for Waiver Title

Signature of Person Submitting Request for Waiver (electronic signature not acceptable)

E-mail Address Phone No.

Contract/Order No. Date Submitted

Waiver Approved By:

Contracting Officer’s Name Printed

Contracting Officer’s Signature Date (electronic signature is not acceptable)

IR1052.224-9008 Safeguards Against Unauthorized Disclosure Of Sensitive But Unclassified Information (Nov 2015)

1. Treasury Directive Publication 15-71 (TD P 15-71), Chapter III – Information Security, Section 24 – Sensitive But Unclassified Information defines SBU information as ‘any information, the loss, misuse, or unauthorized access to or modification of which could adversely affect the national interest or the conduct of Federal programs, or the privacy to which individuals are entitled under Section 552a of Title 5, United States Code (USC) (the Privacy Act) but which has not been specifically authorized under criteria established by an executive order or an act of Congress to be kept secret in the interest of national defense or foreign policy.’ SBU may be categorized in one or more of the following groups—

• Returns and Return Information

• Sensitive Law Enforcement Information

• Employee Information

• Personally Identifiable Information

• Other Protected Information

2. Confidentiality requirements for tax returns and return information are established by Section 6103 of the Internal Revenue Code (26 USC 6103), and the penalties for unauthorized access and disclosure of returns and return information are found in Sections 7213, 7213A and 7431 of the Internal Revenue Code (26 USC 7213, 7213A and 7431).

3. Contractors who perform work at contractor (including subcontractor) managed sites using contractor or subcontractor managed IT resources shall adhere to the general guidance and specific security control standards or requirements contained in Publication 4812, Contractor Security Controls, IRM 10.23.2 - Personnel Security, Contractor Investigations and IRM 10.8.1 - Information Technology (IT) Security, Policy and Guidance. Typically, all contracts that require contractor (including subcontractor) employees to handle, manage, or process SBU information shall be protected at the moderate risk level. Publication 4812 and IRM 10.8.1 and 10.23.2 provide comprehensive lists of all security controls and guidance.

4. As directed by the Contracting Officer, the contractor will be required to input data into Archer or a similar system to describe the security controls being used to protect information.

5. Eligibility, Fitness and Suitability. Contractor (including subcontractor) personnel hired for work within the United States or its territories and possessions and who require access, wherever the location, to IRS owned or controlled facilities or work on contracts that involve the design, operation, repair, or maintenance of information systems, and/or require access to SBU information, must meet the eligibility requirements under IRM 10.23.2, Personnel Security, Contractor Investigations, and shall be subject to security screening and investigative processing, commensurate with the position sensitivity level, and in accordance with IRM 10.23.2, and TD P 15-71. Contractor (including subcontractor) employees must be favorably adjudicated prior to starting work on the contract/order or before being granted staff-like access (or interim staff-like access, if approved by Personnel Security) to IRS information systems or SBU information.

6. General Conditions for Allowed Disclosure. Any SBU information, in any format, made available to contractor (including subcontract) personnel shall be treated as confidential information and shall be used only for the purposes of carrying out the requirements of this contract. Inspection by or disclosure to anyone other than a duly authorized officer or employee of the contractor (including subcontractor) shall require prior written approval of the IRS. Requests to make such inspections or disclosures shall be addressed to the Contracting Officer (CO).

7. Nondisclosure Agreement. Consistent with TD P 15-71, Chapter II, Section 2, and IRM 10.23.2.17 - Nondisclosure Agreement for Sensitive but Unclassified Information, each contractor (including subcontractor) employee who requires access to SBU information shall complete, sign and submit to Personnel Security – through the CO (or COR, if assigned) — an approved Nondisclosure Agreement (See Attachment 2) prior to being granted access to SBU information under any IRS contract or order.

8. Encryption. All SBU information must be protected at rest, in transit, and in exchanges (i.e., internal and external communications). The contractor (including subcontractor) shall employ encryption methods and tools to ensure the confidentiality, integrity, and availability of SBU information.

9. Incident and Situation Reporting. The contractor (including subcontractor) shall report any incident/situation in accordance with IRM 10.8.1.4.8.5 - Incident Reporting and to the COR. Concurrent with its reporting it to the COR, the contractor (including subcontractor) shall report incidents/situations (24x7x365) to Computer Security Incident Response Center (CSIRC)(IT infrastructure)/Situation Awareness Management Center (SAMC) (anything that does not affect the IT infrastructure) through any of the following methods:

Telephone: (202) 283-4809 (local) or toll free hotline at (866) 216-4809

Fax: (202) 283-0345

E-mail: samc@cirsc.irs.gov

In addition, if the SBU information is or involves returns or return information, or threatens the safety or security of personnel or information systems, the contractor shall report the incident/situation to the Treasury Inspector General for Tax Administration (TIGTA) hotline at (800) 366-4484.

10. Access to, Processing and Storage of Sensitive but Unclassified (SBU) Information. The contractor (including subcontractor) shall not allow contractor or subcontractor employees to access, process or store SBU on Information Technology (IT) systems or assets located outside the continental United States and its outlying territories.

Contractors (including subcontractors) utilizing their own IT systems or assets to receive or handle IRS SBU data shall not commingle IRS and non IRS data.

11. Disposition of SBU Information. All SBU information processed during the performance of this contract, or to which the contractor (or subcontractor) was given access (as well as all related output, deliverables, or secondary or incidental by-products, information or data generated by the contractor or others directly or indirectly from the source material), regardless of form or format, shall be completely purged from all data storage components of the contractor’s or subcontractor facility(s) and computer systems, and no SBU/PII information will be retained by the contractor either--

• When it has served its useful, contractual purpose, and is no longer needed to meet the contractor’s (including subcontractor) other, continuing contractual obligations to the IRS or

• When the contract expires, or is terminated by the IRS (for convenience, default, or cause).

The contractor (including subcontractor) shall completely purge from its systems and Electronic Information Technology, and/or return all SBU/PII information (originals, copies, and derivative works) within 30 days of the point at which it has served its useful contractual purpose, or the contract expires or is terminated by the IRS (unless, the CO determines, and establishes, in writing, a longer period to complete the disposition of SBU/PII information).

The contractor shall provide to the IRS a written and signed certification to the COR that all SBU materials/information (i.e., case files, receipt books, PII data and material, removable media (disks, cds, thumb drives)) collected by, or provided to, the contractor been purged, destroyed or returned.

12. Subcontractors. Subcontractors of the contractor are held to the same provisions, investigative requirements, and standards of conduct for handling and protecting SBU information as employees of the prime contractor.

13. Other Safeguards. [Insert any additional disclosure safeguards provided by the Program Office/COR or that the Contracting Officer determines are necessary and in the best interest of the Government and not addressed elsewhere in the contract. If none are entered here, there are no other safeguards applicable to this contract action.]

Contractor Security Requirements

It is the contractor’s responsibility to know and understand which regulations and standards promulgated by the Occupational Health and Safety Administration applies to them and their sub-contractors, as well as any local or state health and safety regulations. Sub-contractors who have less than 10 employees are not exempt from OSHA regulations and standards while working on a federal contract.

Contractors and subcontractors shall be trained in ladder safety per 29 CFR 1910.23 and use the appropriate non-conductive ladders for any work involving electrical devices.

The contractor shall not leave a ladder to climb onto any structures, in the ceiling spaces or anywhere else, that are not meant for human occupancy. The contractor will ensure they provide the necessary equipment for their employees and subcontractors to work at heights safety and in compliance with 29 CFR 1910.28 and 29 CFR 1910 Subpart F.

The contractor will not drill into any wall, ceiling or other substrate without first receiving written consent, from the Building Manager (in non-delegated buildings) or the asbestos program manager in a delegated building, that the area to be penetrated is free of asbestos.

The contractor’s employees and sub-contractors shall be trained in asbestos awareness per 29 CFR 1910.1001.