This is a Time of Delivery schedule for a federal contract involving the repair and commissioning of three Adult Fish Pump motors over a three-year period from 2027 to 2029.

The contract requires delivery of twelve line items across three pumps (#1, #2, and #3). For each pump, the contractor must deliver: (1) a motor rewind service with specific winding types (Ideal Electric single winding for pumps #2 and #3; Hitachi dual winding for pump #1); (2) time-and-materials asbestos abatement and shop repair hours with not-to-exceed caps ($57,000 for pump #3 by 30 SEP 2027; $71,000 for pump #1 by 28 SEP 2028; $61,000 for pump #2 by 01 OCT 2029); (3) final operation and maintenance manuals; and (4) on-site commissioning support during specified December date ranges. All abatement and repair work requires written pricing submission to the Contracting Officer and written approval before proceeding. Pump #3 motor rewind is due 30 SEP 2027 with commissioning support 15-24 DEC 2027. Pump #1 motor rewind is due 28 SEP 2028 with commissioning support 13-22 DEC 2028. Pump #2 motor rewind is due 01 OCT 2029 with commissioning support 12-21 DEC 2029. All operation and maintenance manuals are due one month after their respective motor rewind deliveries.

View the file

Other files

File Type Posted
DD FORM 1149.pdf PDF
Solicitation - W912EF27QA006.pdf PDF
Wage Determination - 2015-5559 Oct 2 2026.pdf PDF
Supplemental Drawings.pdf PDF
Performance Work Statement.pdf PDF
Plans.pdf PDF
GFP Tracker.xlsx XLSX spreadsheet
DA FORM 3161.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TIME OF DELIVERY

(a) The Government requires delivery to be made according to the following schedule:

ITEM NO. QUANTITY ON OR BEFORE

COB DATE

ADULT FISH PUMP #3 MOTOR REWIND

(IDEAL ELECTRIC SINGLE WINDING)

1 30 SEP 2027

T&M: ASBESTOS ABATEMENT HOURS AND

SHOP REPAIR HOURS (NTE)

All abatement and repairs found during inspection will be priced and submitted to the Contracting Officer in writing. Contractor must have written approval before proceeding with this work.

See TIME & MATERIALS INSTRUCTIONS

NTE $57,000 30 SEP 2027

ADULT FISH PUMP #3 MOTOR FINAL

OPERATION AND MAINTENANCE MANUALS

1 30 OCT 2027

ADULT FISH PUMP #3 MOTOR ON-SITE

COMMISSIONING SUPPORT

1 During the dates 15 DEC

2027 to 24 DEC

ADULT FISH PUMP #1 MOTOR REWIND

(HITACHI DUAL WINDING)

1 28 SEP 2028

T&M: ASBESTOS ABATEMENT HOURS AND

SHOP REPAIR HOURS (NTE)

All abatement and repairs found during inspection will be priced and submitted to the Contracting Officer in writing. Contractor must have written approval before proceeding with this work.

See TIME & MATERIALS INSTRUCTIONS

NTE $71,000 28 SEP 2028

0007 1 30 OCT 2028

ADULT FISH PUMP #1 MOTOR FINAL

OPERATION AND MAINTENANCE MANUALS

ADULT FISH PUMP #1 MOTOR ON-SITE

COMMISSIONING SUPPORT

1 During the dates 13 DEC

2028 to 22 DEC

ADULT FISH PUMP #2 MOTOR REWIND

(IDEAL ELECTRIC SINGLE WINDING)

1 01 OCT 2029

T&M: ASBESTOS ABATEMENT HOURS AND

SHOP REPAIR HOURS (NTE)

All abatement and repairs found during inspection will be priced and submitted to the Contracting Officer in writing. Contractor must have written approval before proceeding with this work.

See TIME & MATERIALS INSTRUCTIONS

NTE $61,000 01 OCT 2029

ADULT FISH PUMP #2 MOTOR FINAL

OPERATION AND MAINTENANCE MANUALS

1 01 NOV 2029

ADULT FISH PUMP #2 MOTOR ON-SITE

COMMISSIONING SUPPORT

1 During the dates 12 DEC

2029 to 21 DEC

(End of condition)