This is an Internal Cost Estimate (ICE) document prepared by the Denver Regional Transportation District (RTD) dated March 16, 2026, for the Ticket Vending Machine (TVM) Replacement Project. The project involves the removal of 185 existing TVMs and installation of 173 new full-function TVMs across RTD's service area, with 121 units for RTD locations, 54 units along the East Colfax Bus Rapid Transit corridor, 1 unit at Civic Center Station, and 5 spare units. An optional purchase of 6 additional TVMs for Denver Union Station Bus Concourse is also included. The scope encompasses hardware procurement, software installation for a Central Data Collection and Information System, on-site training, documentation, removal and installation across six scenarios ranging from low-effort to trenching work, grounding, and miscellaneous parts and equipment.
The total base project cost is estimated at $18,236,419, with an additional $1,200,000 in extended hardware, software, and firmware warranty options (Years 1-8 at $150,000 annually), bringing the total project cost to $19,436,419. Cost components include $11,340,000 for hardware (TVMs at approximately $60,000 per unit with suggested updates to $66,000 for full-service machines), $80,000 for software, $2,200,390 for training, removal, and installation, and $1,576,626 for miscellaneous costs including special tools, network equipment, and tariff adjustments. A 20% contingency of $3,039,403 is included in the base cost. The document contains multiple internal threaded comments identifying cost uncertainties and requiring verification from asset management, revenue, and cybersecurity departments regarding warranty pricing, parts determinations, tariff calculation methodologies, and the proper scope of software inclusions.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Denver Regional Transportation District | |||||||||||||
| Date: 3/16/26 | |||||||||||||
| 750124 | |||||||||||||
| Internal Cost Estimates - TVM Replacement Project | |||||||||||||
| Cost Summary - Spread Out Schedule | |||||||||||||
| Description Item | TOTAL Number of Units | Unit Type | Year 2026 Units | Year 2026 Cost | Cost/Unit | Plus Additional Costs | PM Cost | Total Cost Per Unit | Total Cost | 5% | Base | Colfax | Expense |
| Hardware & Software Management Costs | |||||
| Hardware | |||||
| Ticket Vending Machine Units - Full Function for RTD | 121 | Each | 121 | $7,260,000 | $ 60,000 |
tc={A0B5FBAC-C3C7-43D5-B848-C966FECD9C39}: [Threaded comment]
Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924
Comment:
| I believe we need to update this amount. The most recent number I heard was around $66,000 per machine for a full service (cash and card) machine. | $ 7,260,000 | 363,000.00 | 7,623,000 | ||||||||
| Ticket Vending Machine Units - Full Function for BRT/Colfax | 54 | Each | 54 | 3,240,000 | 60,000 | 3,240,000 | 162,000.00 | 3,402,000 | |||
| Spare TVMs | 5 | Each | 5 | 300,000 | 60,000 | 300,000 | 15,000.00 | 315,000 | |||
| Spare Parts | 1 | Total Parts | .05% of Total for new machines | 540,000 | 540,000 | ||||||
| Hardware Total | 181 | $11,340,000 | $ 11,340,000 |
| Software - Central Data Collection System | ||||||
| Central Data Collection & Information System Software Purchase & Install (one time only & is there an hourly rate for future work?) | 1 | Each | $80,000 | $80,000 | 80,000 | |
| Annual License or Subscription Fee? | ||||||
| Annual Software Assurance Fee? | ||||||
| Software Total | $80,000 | $80,000 | ||||
| Hardware and Software Management Costs Total | $ 11,420,000 | $11,420,000 |
| Training, Removal and Installation Costs | ||||||||
| Onsight Training | 1 | Each | 1 | $30,000 | $30,000 | $30,000 | $30,000 | |
| Documentation and Manuals Provision | 1 | Each | 1 | $15,000 | $15,000 | $15,000 | 15,000 |
| Removal and Installation Costs | |||||||
| Scenario A - Low Effort | 32 | $2,826 | $2,733 | $5,559 | $177,888 | ||
| Low Effort but need more work | 11 | 3,250 | 2,733 | 5,983 | 65,813 | ||
| Scenario A - Total | 43 | $243,701 | 243,701 |
| Scenario B - Minimal Work | 16 | $5,493 | $3,007 | $8,500 | $136,000 | ||
| Minimal Work but need more work | 16 | 6,317 | 3,007 | 9,324 | 149,184 | ||
| Scenario B - Total | 32 | $285,184 | 285,184 |
| Scenario C - Trenching | 26 | $8,657 | $3,608 | $12,265 | $318,890 | ||
| Trenching but need more work | 8 | 9,956 | 3,608 | 13,564 | 108,512 | ||
| Scenario C - Total | 34 | $427,402 | 427,402 |
| Scenario D - Removal TVM | 97 | $1,447 | $1,093 | $2,540 | $246,380 | ||
| Removal TVM, but need more work | 6 | 1,881 | 1,093 | 2,974 | 17,844 | ||
| Removal TVM, but need even more work | 15 | 3,847 | 1,093 | 4,940 | 74,100 | ||
| Scenario D - Total | 118 | $338,324 | $338,324 |
| Scenario E - Colfax BRT | 33 | $6,872 | $3,307 | $10,179 | $335,907 | ||
| Colfax BRT, but need more work | 21 | 3,092 | 3,307 | 6,399 | 134,379 | ||
| Scenario E - Total | 54 | $470,286 | 470,286 |
| Scenario F - Civic Center | 1 | $5,455 | $3,458 | $8,913 | $8,913 | |
| Scenario F - Total | $8,913 | 8,913 |
Grounding tc={7FD0FDAD-E021-4011-8D97-C6002FE43ECC}: [Threaded comment]
Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924
Comment:
| What does grounding refer to and how was the amount determined? | $22,345 | 22,345 | |
| Contingency |
tc={40DFF802-714D-4EC7-ACC0-D365A0362565}: [Threaded comment]
Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924
Comment:
how were these amounts determined. $359,235 251,464 107,771
| Total Removal and Installation Costs | 282 | $2,155,390 |
| Training, Removal and Installation Costs Total | $2,200,390 |
Miscellaneous Costs
| Special Tools, Diagnostic and Test Equipment Items | 108,313 | 75,819 | 32,494 |
| Miscellaneous Parts (Network, Cables, Asset Tags, etc…) |
tc={B553A460-3E92-4E20-9605-FE270586A60A}: [Threaded comment]
Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924
Comment:
| How was the amount determined for the parts? | 108,313 | 75,819 | 32,494 | |
| Tariff Cost Adjustment (10%?) |
tc={67198A17-7D82-4002-83CF-B8A31A2A61F6}: [Threaded comment]
Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924
Comment:
My suggestion would be to use a percentage of the total TVM purchase for determining Tariff.
tc={A0B5FBAC-C3C7-43D5-B848-C966FECD9C39}: [Threaded comment]
Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924
Comment:
I believe we need to update this amount. The most recent number I heard was around $66,000 per machine for a full service (cash and card) machine.
tc={7FD0FDAD-E021-4011-8D97-C6002FE43ECC}: [Threaded comment]
Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924
Comment:
What does grounding refer to and how was the amount determined?
tc={40DFF802-714D-4EC7-ACC0-D365A0362565}: [Threaded comment]
Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924
Comment:
| how were these amounts determined. | 1,000,000 | 700,000 | 300,000 | ||||||
| Additional Cost Per TVM for ABT HW and Ingegration (RTD & Colfax/BRT, 10% premium added) | 180 | 180 | 2000 | 360,000 | 252,000 | 108,000 | |||
| Miscellaneous Costs Total | $1,576,626 |
Total Base Direct Costs Sub-Total $15,197,016 10,375,648 4,453,044 368,324
Contingency (20%) $3,039,403 2,127,582 911,821
| Total Base Direct Costs | $ 18,236,419 | 12,503,230 | 5,364,865 | 368,324 | |||
| 18,236,419 | |||||||
| Warranty and License Options (to be assigned per line but paid per year overall) | - 0 | ||||||
| Mandatory | Optional | 2026 Cost | |||||
| Extended Hardware, Software & Firmware Warranty and Support - Year 1 (Parts Only) |
tc={27632E69-9616-430A-9C94-89166027CDDA}: [Threaded comment]
Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924
Comment:
| I would reach out to asset management and possibly Revenue just verify that these yearly amounts are accurate because this is the same warranty prices for that of the current contract. | 1 | Y | N | 0 | $150,000 | ||
| Extended Hardware, Software & Firmware Warranty and Support - Year 2 (Parts Only) | 1 | Y | N | 0 | 150,000 | ||
| Extended Hardware, Software & Firmware Warranty and Support - Year 3 (Parts Only) | 1 | Y | N | 0 | 150,000 | ||
| Extended Hardware, Software & Firmware Warranty and Support - Year 4 (Parts Only) | 1 | Y | 0 | 150,000 | |||
| Extended Hardware, Software & Firmware Warranty and Support - Year 5 (Parts Only) | 1 | Y | 0 | 150,000 | |||
| Extended Hardware, Software & Firmware Warranty and Support - Year 6 (Parts Only) | 1 | Y | 0 | 150,000 | |||
| Extended Hardware, Software & Firmware Warranty and Support - Year 7 (Parts Only) | 1 | Y | 0 | 150,000 | |||
| Extended Hardware, Software & Firmware Warranty and Support - Year 8 (Parts Only) | 1 | Y | 0 | 150,000 | |||
| Total Warranty and License Options Costs | $1,200,000 | ||||||
| TOTAL BASE COST |
tc={0619BFD9-6560-4851-B160-6C1D537C6F42}: [Threaded comment]
Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924
Comment:
If you are going to list Base Cost and the base cost plus options, I would add a line between too for the Total Option Cost so that all are together.
tc={27632E69-9616-430A-9C94-89166027CDDA}: [Threaded comment]
Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924
Comment:
I would reach out to asset management and possibly Revenue just verify that these yearly amounts are accurate because this is the same warranty prices for that of the current contract.
tc={56EEA05E-3609-4D09-9B15-20CDFFB2740A}: [Threaded comment]
Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924
Comment:
I don't believe this should be included in the ICE for the TVM purchase since this appears to be a separate contract but per our 3/6/26 conversation, please confirm with Cybersecurity.
tc={B553A460-3E92-4E20-9605-FE270586A60A}: [Threaded comment]
Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924
Comment:
| How was the amount determined for the parts? | $18,236,419 | ||
| TOTAL OPTION COST | $1,200,000 | ||
| TOTAL COST (BASE COST + ALL OPTIONS) | $ 19,436,419 |
I believe we need to update this amount. The most recent number I heard was around $66,000 per machine for a full service (cash and card) machine.
What does grounding refer to and how was the amount determined?
how were these amounts determined.
I don't believe this should be included in the ICE for the TVM purchase since this appears to be a separate contract but per our 3/6/26 conversation, please confirm with Cybersecurity.
How was the amount determined for the parts?
My suggestion would be to use a percentage of the total TVM purchase for determining Tariff.
I would reach out to asset management and possibly Revenue just verify that these yearly amounts are accurate because this is the same warranty prices for that of the current contract.
If you are going to list Base Cost and the base cost plus options, I would add a line between too for the Total Option Cost so that all are together.