liquidated_damages_memo-TVM_(1).docx
DOCX document 32 KB Posted
- Solicitation number
- RFP 126FO005
- Issued by
- Denver County, Denver City, Colorado
About this file
This is a memorandum from the Regional Transportation District (RTD) in Denver, Colorado, establishing liquidated damages for the Ticket Vending Machine (TVM) Replacement Project. The project involves the removal of 185 existing TVMs and installation of 173 new units, including 113 replacements at existing locations, 54 units along the East Colfax Bus Rapid Transit corridor, 1 unit at Civic Center Station, and 5 spare units, with an option to purchase 6 additional TVMs for Denver Union Station Bus Concourse. The memorandum, prepared by the Program Manager and addressed to the Purchasing Agent on May 27, 2025, establishes the contractual penalty framework for project delays.
The liquidated damages have been set at $350 per day for any period the project exceeds its performance timeline. This figure was calculated based on a three-year average of TVM revenue data across the 160-unit system, which generated $3.2 million in average annual cash revenue and $17.6 million in average annual credit/debit revenue, totaling approximately $57,000 in daily system-wide revenue. The per-unit daily revenue loss calculation of $356 ($55 cash and $301 credit/debit) served as the basis for establishing the daily liquidated damages amount, reflecting the anticipated revenue impact from TVM non-operation during project delays.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Regional Transportation District Our mission:
To meet our constituents’ present and future public transit needs by offering safe, clean, reliable, courteous, accessible, and cost-effective service throughout the District.
Memorandum
| To: | Bethany Swank – Purchasing Agent |
| From: | Georges Michel – PMO – Program Manager |
| Date: | May 27, 2025 |
| Subject: | Liquidated Damages, Ticket Vending Machine Replacement Project |
The appropriate liquidated damages are $350 per day that the project exceeds the period of performance.
We have calculated the TVM revenue totals for the past three years and averaged them to determine the anticipated loss of revenue should a TVM cease operation. The average annual Cash revenue is $3.2 million, and the average annual Credit/Debit revenue is $17.6 million.
Utilizing these figures, we have determined that the average system-wide daily amount of Cash revenue is $8,770, and the average daily Credit/Debit revenue is $48,230, resulting in a total daily revenue of $57,000.
Given that there are 160 TVMs, the average daily loss in revenue per TVM would be $356.
When broken down further, the daily loss of Cash revenue would be $55, while the loss of Credit/Debit revenue would be $301.