Statement of Work Summary: Thomas Building Renovation – Middle Georgia State University

This is a Statement of Work (SOW) for the renovation of Thomas Hall at Middle Georgia State University's Warner Robins campus under U.S. Air Force contract FA857926Q0034. The contractor must provide all labor, materials, equipment, and supervision to complete architectural, mechanical, plumbing, and electrical work within designated building areas. Specific deliverables include installation of two new 36-inch doors with frames and hardware, one 36-inch sliding service window with security bars, floor-to-ceiling framing and drywall construction (approximately 11 feet 6 inches in height), primer and two-finish-coat painting on new walls with cove base installation, two sprinkler heads for fire protection systems, removal of two existing urinals and installation of two new toilets with extended partitions in the Men's Restroom, 6-inch minimum cross-wall ceiling vents with supply and return duct paths, new electrical receptacles including 6-foot above-finish-floor monitor outlets, power for intrusion/access control equipment, and low-voltage data and communications cabling per referenced drawings.

The period of performance runs from September 14, 2026 through October 29, 2026, with work performed Monday through Friday, 0800–1700, excluding federal holidays. The contractor must submit five contract data requirements: a Safety Plan within 15 working days of award, a Quality Control Plan within 15 working days of award, a Production Roadmap (Integrated Master Schedule) within 7 days after receipt of order, a Bill of Materials within 3 days after receipt of order, and incident/mishap reports within three calendar days of any occurrence. Acceptance criteria require all installations to match project drawings and this SOW, all inspections and fire marshal approvals to be obtained, punch list items to be completed, and final as-built and operations-and-maintenance documentation to be submitted. Performance and payment bonds are required, Davis-Bacon wage requirements do not apply, and all permitting including Georgia State Fire Marshal approval is the contractor's responsibility.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

i

STATEMENT OF WORK (SOW)

THOMAS BUILDING RENOVATION – MIDDLE

GEORGIA STATE UNIVERSITY

U.S AIR FORCE

FA857926Q0034

11/28/2025 Version 1 ii

SOW Modification History

Date Change Paragraph # iii

TABLE OF CONTENTS

1 INTRODUCTION

2 DESCRIPTION OF WORK/OBJECTIVES/SERVICES

2.1 Doors, Frames, and Hardware

2.2 Storefront Systems

2.3 Framing and Drywall

2.4 Painting

2.5 Fire Protection

2.6 Plumbing

2.7 Mechanical

2.8 Electrical

3 REFERENCE DOCUMENTS AND STANDARDS

3.1 Applicable Documents and Standards

4 CDRL SUMMARY

4.1 CDRL Information

5 SCHEDULE

5.1 Place/Period of Performance

5.2 Quality Control Plan

5.3 Quality Assurance

5.4 Safety and Health Standards

5.5 Security

5.6 Keys, Building Access Cards, and Building Badge Control

5.7 Conflicts of Interest

5.8 Inherently Governmental Functions

5.9 Hours of Operation

5.10 GOVERNMENT OBSERVATIONS

5.11 ENVIRONMENTAL

5.12 ACCEPTANCE CRITERIA

APPENDIX A – NAME OF APPENDIX

1 INTRODUCTION

1.1 Purpose

This Statement of Work (SOW) defines the scope, deliverables, assumptions, exclusions, and responsibilities for the renovation of the Thomas Building at Middle Georgia State University’s Warner Robins campus. It establishes the Contractor’s obligations and outlines the work required to complete the renovation in accordance with the project plans and specifications.

1.2 Project Information

The project consists of the renovation of designated areas within the Thomas Hall building. The Contractor shall provide all labor, materials, equipment, and supervision necessary to complete the work described in this document.

1.3 Background

Performance and payment bonds are included and will be provided upon request. No furniture relocation is included in the scope of work. The project schedule assumes that all materials will be ordered in advance and available prior to mobilization. Davis-Bacon wage requirements do not apply to this project. All required permitting, including Georgia State Fire Marshal permitting for fire protection work, is included.

2 DESCRIPTION OF WORK/OBJECTIVES/SERVICES

2.1 Doors, Frames, and Hardware

The Contractor shall install the new 36" door indicated at the Multipurpose Room and the additional door shown near the Security Office as shown on the project plans.

2.2 Storefront Systems

The Contractor will install one 36” sliding service window equipped with security bars as shown on the construction plans in the Collab Room.

2.3 Framing and Drywall

New walls will be constructed floor-to-ceiling as indicated on the project plans. (approx. 11'-6" per architectural drawings)

2.4 Painting

All newly constructed walls shall receive primer and two finish coats be painted to match adjacent construction. New Cove base shall be installed as indicated on project drawing.

2.5 Fire Protection

Two (2) sprinkler heads will added as indicated on the project plans. All required fire protection permitting through the Georgia State Fire Marshal shall be included.

2.6 Plumbing

Two (2) existing urinals in the Men’s Restrooms shall be removed, and two (2) new toilets shall be installed, fixture models.

Existing partitions in the Men’s Restroom shall be extended to accommodate the installation of new toilets.

2.7 Mechanical

Install 6" Min. Cross Wall Vents in Ceiling at multiple locations to include supply and return duct paths as indicated on the project plans.

2.8 Electrical

The Contractor shall install new receptacles, including 6' AFF monitor outlets, and provide power for intrusion/access control equipment as shown. Circuiting information is provided in the electrical plan. Low-voltage cabling (data, communications) is also included in the construction scope. The communications drawing “Thomas Hall SERN cabling” provides communications distribution guidance.

2.9 Production Roadmap

The contractor shall provide a strategic plan that outlines the vision, direction, priorities, and progress of the project over the period of performance. (CDRL A004, DI-IPSC-82297 Production Roadmap).

3 REFERENCE DOCUMENTS AND STANDARDS

3.1 Applicable Documents and Standards

The contractor shall comply with and maintain internal procedures aligned with the references and documents listed below. If the contractor does not already have established processes, the contractor shall utilize the references and documents for implementing program requirements.

Document Title

MGSU Construction areas Jun 2026 (General Construction)

Thomas Hall SERN cabling (Network Drawing)

MGSU Thomas Hall EL work (Electrical Drawing)

3.2 Bill of Material

The contractor shall provide all major assemblies and deliver a structured, single-indenture Bill of Materials (BOM) listing all component parts contained directly within each identified assembly. The summary is used to compare supplier part cost prior to contract ward and post contract award. (CDRL A005, DI-MGMT-81994 Priced Bill of Materials).

4 CDRL SUMMARY

4.1 CDRL Information

4.1.1 Contract data shall be delivered electronically IAW the corresponding requirement for each Data Item listed in the table below. The contractor shall prepare and deliver data to the Government in contractor format except where specific forms are required. Data shall be formatted IAW the requirements specified for each Data Item listed in the table below.

4.1.2 The Contractor shall provide a fully completed installation of all architectural, mechanical, plumbing, and electrical components described in this SOW.

Updated as-built documentation will be provided upon completion. All required inspections, including Fire Marshal approval, will be obtained.

Exhibit Title SOW Paragraph Delivery

A/B/C/D/E001 Safety Plan 5.4.2 15 working days after award

A/B/C/D/E002 Incident/Mishap Report

5.4.3 Copy sent within three

calendar days of incident/mishap

A/B/C/D/E003 Quality Control Plan 5.2 15 working days after award

A/B/C/D/E004 Production Roadmap

(IMS)

2.9 7 Days ARO

A/B/C/D/E005 BOM 3.2 3 Days ARO

5 SCHEDULE

The project schedule is based on the assumption that all materials will be procured and available prior to the start of construction. Work will proceed according to the Contractor’s established timeline.

5.1 Place/Period of Performance

The place of performance shall be at 100 University Boulevard, Warner Robins, GA 31093, hereinafter referred collectively as Thomas Hall.

Period of Performance (PoP)

The PoP shall be 14 September 2026 – 29 October 2026

The Government will provide necessary working space, including heat, light, ventilation, and electrical outlets for the use of contractors’ personnel. The Government will provide access to the necessary facilities where the equipment resides. Government telephones shall be used for official business only. The contractor shall be responsible for safeguarding all Government property provided for contractor use.

5.2 Quality Control Plan

The contractor shall establish a complete Quality Control Plan (QCP) to ensure the requirements of this contract are provided as specified. The contractor's quality management program shall comply with the minimum quality management systems elements specified in the American National Standards Institute (ANSI), American Standards Organization (ASO), and International Standard Organization (ISO) family of standards. The report shall be submitted to the PCO or COR NLT 30 days post contract award (CDRL A003, DI QCIC-81722 Quality Control Plan).

5.3 Quality Assurance

5.3.1 The PCO or COR will perform assessments of the contractor’s performance.

Subsequent to contract award, the specific name and contact information of the employees with a letter defining duties and authority will be furnished to the contractor.

5.3.2 The PCO or COR will inform the task manager in person when discrepancies occur and will request corrective action. The PCO or COR shall make a notation of the discrepancy on the assessment checklist with the date and time the discrepancy was noted and request the task manager (or authorized representative) to initial the entry on the checklist.

5.3.3 The Government may inspect each task as completed or increase the number of quality control inspections if deemed appropriate because of repeated failures discovered during quality control inspections or because of repeated customer complaints.

5.3.4 Any matter concerning a change to the scope, prices, terms or conditions of this contract shall be referred to the PCO.

5.3.5 The services to be performed by the contractor during the period of this contract are, at all times and places, subject to review by the PCO or authorized representative.

5.4 Safety and Health Standards

5.4.1 The contractor shall follow and adhere to all applicable Occupational Safety and Health Administration (OSHA) standards.

5.4.2 System Safety Program Plan. The contractor shall implement a safety program that ensures protection of contractor personnel. As part of the Safety Program, the contractor shall establish a Safety Plan. The contractor shall submit the Safety

Plan within 15 days after contract award (CDRL A001, DI-SAFT-82080/T NOT 1 Safety Plan).

5.4.3 In the event of an accident/mishap, the contactor shall take reasonable and prudent action to establish control of the accident/mishap scene, prevent further damage to persons or property, and preserve evidence. An email copy of the mishap/incident notification shall be sent within three calendar days to the COR

(CDRL A002 DI-SAFT-81563)

5.5 Security

5.5.1 The contractor shall comply with all Security, Force Protection, and Antiterrorism requirements. The contractor shall comply with local unit in- and out-processing procedures for all contractor personnel to ensure proper security-related briefings and debriefings are accomplished. Specific in- and out-processing checklists may be included at the task order level.

5.5.2 The contractor understands that any contractor employee may be summarily and immediately removed from or denied access to the property, facility, and installation at the sole discretion of competent Government authority if that authority determines such action is necessary to protect or preserve property, safety, and security, or to maintain good order and discipline.

5.5.3 Should a security incident occur, the contractor shall:

5.5.3.1 Immediately report to the site location Group SM and COR all available facts related to each instance.

5.5.3.2 Take such precautions as the SM may reasonably require for security purposes.

5.5.3.3 Take reasonable and prudent action to establish control of the scene, prevent further violation, and to preserve evidence until released by proper authority.

5.5.3.4 Cooperate fully and assist Government personnel as the Government conducts an investigation of the violation.

5.5.3.5 Participate in the investigation until it is complete.

5.6 Keys, Building Access Cards, and Building Badge Control

5.6.1 The contractor shall establish and implement methods of making sure that all keys and building badges issued to the contractor by the Government are not lost, misplaced, or used by unauthorized persons. This shall be documented in the contractor’s management plan, if required.

5.6.2 The contractor shall not duplicate any keys issued by the Government.

5.6.3 The contractor shall immediately report the occurrence of a lost key to the appropriate building Facility Manager and building badges to the appropriate SMs.

5.6.4 The contractor shall prohibit the opening of locked areas by the contractor employees to permit entrance of persons other than the contractor’s employees engaged in the performance of assigned work in those areas, or personnel authorized entrance by the SMs.

5.7 Conflicts of Interest

The Contractor shall not assign to the contract or task order performance, any person, including any employee of the U.S. Government, if employing that person would create a conflict of interest under any law, regulation or policy of the United States Government. Additionally, the Contractor shall not assign to the contract or task order performance, any person who is an employee of the Department of the Air Force, either military, reservist, or civilian, unless such person seeks and receives approval according to DoD Directive 5500.7-R and any other applicable regulation or policy of the Department of the Air Force or its subordinate commands, as applicable, including but not limited to Air Force Materiel Command.

5.8 Inherently Governmental Functions

5.8.1 None of the functions to be performed under this requirement are inherently Governmental. Additionally, no part of this SOW, the basic contract or any task order issued under the basic contract shall be construed to require the Contractor to provide personal services to the Government. The contractor shall comply with this SOW in its entirety.

5.8.2 The Government will neither supervise contractor employees nor control the method by which the Contractor performs the required tasks. Under no circumstances shall the Government assign tasks to or prepare work schedules for individual contractor employees. It shall be the responsibility of the contractor to manage its employees and to guard against any actions that are of the nature of personal services or give the perception of personal services. If the Contractor believes or has reason to believe any actions constitute or are perceived to constitute personal services, it shall be the contractor’s responsibility to notify the PM, COR, and PCO immediately. These services shall not be used to perform work of a policy/decision making or management nature, i.e., inherently Governmental functions. All decisions relative to programs supported by the Contractor shall be the sole responsibility of the Government.

5.9 Hours of Operation

5.9.1 Normal Hours of Operation: The contractor shall perform the services required under this contract during the following hours: Monday through Friday 0800-

1700 – EXCEPT FEDERAL HOLIDAYS.

5.9.2 Federal Holidays: Unless otherwise required by the Government, the contractor shall not have access to the Government facilities on the following federal holidays: New Year’s Day, Martin Luther King’s Birthday, Washington’s Birthday, Memorial Day, Independence Day, Juneteenth, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving Day, and Christmas Day. If a holiday falls on Saturday, it is observed on Friday and working hours are Monday through Wednesday for that week. If the holiday falls on a Sunday, it is observed on Monday. Any other circumstances that may prompt base closure, such as Days of National Mourning, may also restrict opportunity to perform the exchanges. In the event of a base closure, exchanges shall be performed on the next business day.

5.9.3 Rescheduling: The contractor shall communicate any work to be done outside the normal hours of operation within seven (7) days advance notice.

5.10 GOVERNMENT OBSERVATIONS

During the PoP, Government personnel other than CO may, from time-to-time, observe contractor operations. However, these personnel may not interfere with contractor performance.

5.11 ENVIRONMENTAL

Weather Hazards. The contractor may encounter hazardous weather conditions including snow, heavy rain, lightning, extreme dust, and other conditions that warrant appropriate precautions.

5.12 ACCEPTANCE CRITERIA

Work will be accepted when all installations match all drawings and this SOW, all inspections are approved, fire protection is approved, punch list items (CDRL Compartment Closeout Schedule Report) are complete, and final as-builts and O&M documentation are submitted.

APPENDIX A – NAME OF APPENDIX

1 Introduction
2 description of work/objectives/services
2.1 Doors, Frames, and Hardware
2.2 Storefront Systems
2.3 Framing and Drywall
2.4 Painting
2.5 Fire Protection
2.6 Plumbing
2.7 Mechanical
2.8 Electrical
2.9 Production Roadmap
3 reference documents and standards
3.1 Applicable Documents and Standards
The contractor shall comply with and maintain internal procedures aligned with the references and documents listed below. If the contractor does not already have established processes, the contractor shall utilize the references and documents for impl...

3.2 Bill of Material

4 CDRL SUMMARY
4.1 CDRL Information
4.1.1 Contract data shall be delivered electronically IAW the corresponding requirement for each Data Item listed in the table below. The contractor shall prepare and deliver data to the Government in contractor format except where specific forms are ...
4.1.2 The Contractor shall provide a fully completed installation of all architectural, mechanical, plumbing, and electrical components described in this SOW. Updated as-built documentation will be provided upon completion. All required inspections, i...
5 SCHEDULE
5.1 Place/Period of Performance
The place of performance shall be at 100 University Boulevard, Warner Robins, GA 31093, hereinafter referred collectively as Thomas Hall.
Period of Performance (PoP)
The PoP shall be 04 September 2026 – 19 October 2026
The Government will provide necessary working space, including heat, light, ventilation, and electrical outlets for the use of contractors’ personnel. The Government will provide access to the necessary facilities where the equipment resides. Governm...
5.2 Quality Control Plan
5.3 Quality Assurance
5.3.1 The PCO or COR will perform assessments of the contractor’s performance. Subsequent to contract award, the specific name and contact information of the employees with a letter defining duties and authority will be furnished to the contractor.
5.3.2 The PCO or COR will inform the task manager in person when discrepancies occur and will request corrective action. The PCO or COR shall make a notation of the discrepancy on the assessment checklist with the date and time the discrepancy was not...
5.3.3 The Government may inspect each task as completed or increase the number of quality control inspections if deemed appropriate because of repeated failures discovered during quality control inspections or because of repeated customer complaints.
5.3.4 Any matter concerning a change to the scope, prices, terms or conditions of this contract shall be referred to the PCO.
5.3.5 The services to be performed by the contractor during the period of this contract are, at all times and places, subject to review by the PCO or authorized representative.
5.4 Safety and Health Standards
5.4.1 The contractor shall follow and adhere to all applicable Occupational Safety and Health Administration (OSHA) standards.
5.4.2 System Safety Program Plan. The contractor shall implement a safety program that ensures protection of contractor personnel. As part of the Safety Program, the contractor shall establish a Safety Plan. The contractor shall submit the Safety Plan...
5.4.3 In the event of an accident/mishap, the contactor shall take reasonable and prudent action to establish control of the accident/mishap scene, prevent further damage to persons or property, and preserve evidence. An email copy of the mishap/incid...
5.5 Security
5.5.1 The contractor shall comply with all Security, Force Protection, and Antiterrorism requirements. The contractor shall comply with local unit in- and out-processing procedures for all contractor personnel to ensure proper security-related briefin...
5.5.2 The contractor understands that any contractor employee may be summarily and immediately removed from or denied access to the property, facility, and installation at the sole discretion of competent Government authority if that authority determi...
5.5.3 Should a security incident occur, the contractor shall:
5.5.3.1 Immediately report to the site location Group SM and COR all available facts related to each instance.
5.5.3.2 Take such precautions as the SM may reasonably require for security purposes.
5.5.3.3 Take reasonable and prudent action to establish control of the scene, prevent further violation, and to preserve evidence until released by proper authority.
5.5.3.4 Cooperate fully and assist Government personnel as the Government conducts an investigation of the violation.
5.5.3.5 Participate in the investigation until it is complete.
5.6 Keys, Building Access Cards, and Building Badge Control
5.6.1 The contractor shall establish and implement methods of making sure that all keys and building badges issued to the contractor by the Government are not lost, misplaced, or used by unauthorized persons. This shall be documented in the contractor...
5.6.2 The contractor shall not duplicate any keys issued by the Government.
5.6.3 The contractor shall immediately report the occurrence of a lost key to the appropriate building Facility Manager and building badges to the appropriate SMs.
5.6.4 The contractor shall prohibit the opening of locked areas by the contractor employees to permit entrance of persons other than the contractor’s employees engaged in the performance of assigned work in those areas, or personnel authorized entranc...
5.7 Conflicts of Interest
5.8 Inherently Governmental Functions
5.8.1 None of the functions to be performed under this requirement are inherently Governmental. Additionally, no part of this SOW, the basic contract or any task order issued under the basic contract shall be construed to require the Contractor to pro...
5.8.2 The Government will neither supervise contractor employees nor control the method by which the Contractor performs the required tasks. Under no circumstances shall the Government assign tasks to or prepare work schedules for individual contracto...
5.9 Hours of Operation
5.9.1 Normal Hours of Operation: The contractor shall perform the services required under this contract during the following hours: Monday through Friday 0800-1700 – EXCEPT FEDERAL HOLIDAYS.
5.9.2 Federal Holidays: Unless otherwise required by the Government, the contractor shall not have access to the Government facilities on the following federal holidays: New Year’s Day, Martin Luther King’s Birthday, Washington’s Birthday, Memorial Da...
5.9.3 Rescheduling: The contractor shall communicate any work to be done outside the normal hours of operation within seven (7) days advance notice.
5.10 GOVERNMENT OBSERVATIONS
5.11 ENVIRONMENTAL
5.12 ACCEPTANCE CRITERIA