TG3 Submittal Register.xls
XLS spreadsheet 57 KB Posted
- Attached to
- Turbine 3 Generator Federal contract opportunity
- Solicitation number
- FA500421B0001
About this file
This solicitation package seeks bids for the overhaul of a 5 MW turbine-generator set and auxiliary equipment at Eielson Air Force Base in Alaska. Work includes tear down, inspection, cleaning, repair of the turbine-generator and replacement of the electronic governor and machine monitoring system. Bids are due by April 6, 2021 with award anticipated between $1-5 million as a firm fixed price sealed bid contract. The site visit has already occurred and all questions were due by February 15, 2021. Bids must remain valid until August 5, 2021. The solicitation and drawings are available on SAM.gov and all contractors must register in SAM. The points of contact are listed for questions.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment FA500421B00010001 SF 30 (1).pdf | ||
| TG3 Bidder QA.docx | DOCX document | |
| FA500421B00010001- Conformed Copy.pdf | ||
| TG3 Appendices.pdf | ||
| Solicitation - FA500421B0001.pdf | ||
| Wage Determination AK20210001.pdf | ||
| TG3 Specs Complete.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittal Register
| TITLE: | MAINTAIN TURBINE-GENERATOR #3 | SUBMITTAL REGISTER | ||||||||||||||||||
| JOB NAME: | FTQW 20-1001 | |||||||||||||||||||
| LOCATION: | Eielson AFB, Alaska | |||||||||||||||||||
| CONTRACT NO: | ||||||||||||||||||||
| CONTRACTOR: | ||||||||||||||||||||
| CONTRACTOR SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | ||||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) | |||
| Line | Activity # | Trans-mittal # | Specification Section | SD # | Submittal Description | Item Submitted | Paragraph # | Classification: GOVT or A/E Revwr | Submit | Approval Needed By | Material Needed By | Action Code | Date Of Action | Date FWD to APPR / Auth Date RCD From CONTR | Date FWD To Other Revwr | Date RCD From Other Revwr | Action Code | Date Of Action | Mailed To CONTR/ Date RCD From APPR Authority | Remarks |
| 1 | 01 11 00 | 01 | Preconstruction Submittals | AF Form 103 | 1.3 | |||||||||||||||
| 2 | 01 11 00 | 01 | Preconstruction Submittals | AF Form 3064 | 1.4 | G | ||||||||||||||
| 3 | 01 35 26 | 01 | Preconstruction Submittals | Accident Prevention Plan | 1.7 | G | if required | |||||||||||||
| 4 | 01 35 26 | 01 | Preconstruction Submittals | Request for Use of Ionizing Radiation | 1.13.5 | if required | ||||||||||||||
| 5 | 01 35 26 | 01 | Preconstruction Submittals | Request for Use of Lasers | 1.13.6 | if required | ||||||||||||||
| 6 | 01 35 26 | 01 | Preconstruction Submittals | Request for Use of Radioactive Materials | 1.13 | if required | ||||||||||||||
| 7 | 01 35 26 | 01 | Preconstruction Submittals | Request for Use of Radio Frequency Radiation | 1.13.7 | if required | ||||||||||||||
| 8 | 01 35 26 | 01 | Preconstruction Submittals | Request for Use of Ultraviolet Radiation | 1.13.8 | if required | ||||||||||||||
| 9 | 01 35 26 | 06 | Test Reports | Accident Reports | 1.11.2 | G | if required | |||||||||||||
| 10 | 01 35 26 | 07 | Certificates | Activity Hazard Analysis | 1.7 | as required | ||||||||||||||
| 11 | 01 35 26 | 07 | Certificates | Hot Work Permit | 1.12 | |||||||||||||||
| 12 | 01 45 00.10 | 06 | Test Reports | Construction Progress Photos | 3.4 | |||||||||||||||
| 13 | 01 50 00 | 06 | Test Reports | Backflow Preventer Tests | 1.3 | G | If applicable | |||||||||||||
| 14 | 01 50 00 | 07 | Certificates | Backflow Tester Certification | 1.3.1 | G | If applicable | |||||||||||||
| 15 | 01 50 00 | 07 | Certificates | Backflow Preventers Approval | 1.3 | G | If applicable | |||||||||||||
| 16 | 01 57 19 | 01 | Preconstruction Submittals | Environmental Protection Plan | 1.6 | G | ||||||||||||||
| 17 | 01 57 19 | 01 | Preconstruction Submittals | Hazmat Inventory (Initial) | 1.7 | G | ||||||||||||||
| 18 | 01 57 19 | 01 | Preconstruction Submittals | Stormwater Pollution Prevention Plan | 1.19 | G | If applicable | |||||||||||||
| 19 | 01 57 19 | 01 | Preconstruction Submittals | Hazardous Waste Accumulation Log (initial) | 1.8.d. | G | ||||||||||||||
| 20 | 01 57 19 | 01 | Preconstruction Submittals | Contractor Employee EMS General Awareness Training Certificates. | 1.8.b. | |||||||||||||||
| 21 | 01 57 19 | 01 | Preconstruction Submittals | Eielson Hazardous/Solid Waste Training Certicicates | 1.8.b. | |||||||||||||||
| 22 | 01 57 19 | 6 | Test Reports | Solid Waste Disposal Weight Tickets and Costs (monthly) | 1.5 | |||||||||||||||
| 23 | 01 57 19 | 06 | Test Reports | Lab Test Results for Waste | 1.9 | G | as applicable | |||||||||||||
| 24 | 01 57 19 | 06 | Test Reports | Hazmat Inventory (Quartery) | 1.9 | G | ||||||||||||||
| 25 | 01 57 19 | 07 | Test Reports | Hazardous Waste Accumulation Log (Initial & quarterly) | 1.8.d. | G | ||||||||||||||
| 26 | 07 | Certificates | Completed Spruce Lake Landfill Checklist | 1.5.d & Appx B | as applicable | |||||||||||||||
| 27 | 01 57 19 | 11 | Closeout Submittals | Hazmat Inventory (Final) | 1.7.b | G | ||||||||||||||
| 28 | 01 57 19 | 11 | Closeout Submittals | Haz Waste Log (Final) | 1.8.d | G | ||||||||||||||
| 01 57 19 | 11 | Closeout Submittals | SWPPP Compliancce Notebook | 1.19 | G | if applicable | ||||||||||||||
| 29 | 01 57 19 | 11 | Closeout Submittals | Stormwater Notice of Termination | 1.19.h. | if applicable | ||||||||||||||
| 30 | 01 78 00 | 03 | Product Data | Spare Parts Data | 1.5 | G | ||||||||||||||
| 31 | 01 78 00 | 08 | Manufacturer’s Instructions | Manufacturers' Warranties | 1.4 | G | ||||||||||||||
| 32 | 01 78 00 | 11 | Closeout Submittals | As-Built Drawings | 3.1 | G | ||||||||||||||
| 33 | 01 78 00 | 11 | Closeout Submittals | Record Drawings | 3.2 | G | ||||||||||||||
| 34 | 48 15 00.20 | 01 | Preconstruction Submittals | Tech Rep Qualifications | 3.1 | G | ||||||||||||||
| 35 | 48 15 00.20 | 01 | Preconstruction Submittals | Governor Tech Qualifications | 3.2 | G | ||||||||||||||
| 36 | 48 15 00.20 | 01 | Preconstruction Submittals | Generator Test & Inspection Personnel Qualifications | 1.3 | G | ||||||||||||||
| 37 | 48 15 00.20 | 01 | Preconstruction Submittals | Test & Inspection Qualifications | 3.5.50 | G | ||||||||||||||
| 38 | 48 15 00.20 | 02 | Shop Drawings | Electronic Governor wiring diagrams & shop drawings | 3.5.49.h | G | ||||||||||||||
| 39 | 48 15 00.20 | 02 | Shop Drawings | Machine Monitor System: Wiring diagrams & shop drawings | 3.5.49.i | G | ||||||||||||||
| 40 | 48 15 00.20 | 02 | Shop Drawings | Proposed Deviations from the Specs. | 1.3 | G | if applicable | |||||||||||||
| 41 | 48 15 00.20 | 03 | Product Data | Electronic Governor | 3.5.49.h | G | ||||||||||||||
| 42 | 48 15 00.20 | 03 | Product Data | Machine Monitor Components | 3.5.49.i | G | ||||||||||||||
| 43 | 48 15 00.20 | 03 | Product Data | Oil Temperature Transmitter | 3.5.49.f | G | ||||||||||||||
| 44 | 48 15 00.20 | 06 | Test Reports | Pre-Overhaul Vibration & clearances | 3.5.5 & 3.5.21 | G | ||||||||||||||
| 45 | 48 15 00.20 | 06 | Test Reports | Post-Overhaul Vibration & clearances | 3.5.5 & 3.5.21 | G | ||||||||||||||
| 46 | 48 15 00.20 | 06 | Test Reports | Proximitor Target area runout | 3.7 | G | ||||||||||||||
| 47 | 48 15 00.20 | 08 | Manufacturer's Instructions | Start-up Plan | 3.7 | G | ||||||||||||||
| 48 | 48 15 00.20 | 09 | Manufacturer's Field Reports | Letters of Recommended Repair | 3.6 | G | ||||||||||||||
| 49 | 48 15 00.20 | 10 | Operation & Maintenance Data | Electronic Governor | 3.5.49.h | G | ||||||||||||||
| 50 | 48 15 00.20 | 10 | Operation & Maintenance Data | Machine Monitoring System | 3.5.49.i | G | ||||||||||||||
| 51 | 48 15 00.20 | 10 | Operation & Maintenance Data | Oil Temperature Transmitter | 3.5.49.f | G | ||||||||||||||
| 52 | 48 15 0.20 | 11 | Closeout Submittals | Tech Rep's Inspection and Approval | 3.1 | G | ||||||||||||||
| 53 | 48 15 00.20 | 11 | Closeout Submittals | Governor software, program & settings | 3.5.49.h | G | ||||||||||||||
| 54 | 48 15 00.20 | 11 | Closeout Submittals | Machine Monitoring System: software, program & setttings | 3.5.49.i | G | ||||||||||||||
| 55 | 48 15 00.20 | 11 | Closeout Submittals | Update Control Panl Wiring diagram | 3.5.49 | G | ||||||||||||||
| 56 | 48 15 00.20 | 11 | Closeout Submittals | Post-Overhaul Report | 3.9 | G | ||||||||||||||
| 57 | 48 15 00.20 | 11 | Closeout Submittals | Completed Task Inspection List | 3.5.4 | G |